ML15313A245

From kanterella
Jump to navigation Jump to search

Staff Review of Interim Evaluation Associated with Reevaluated Seismic Hazard Implementation Near-Term Task Force Recommendation 2.1
ML15313A245
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 11/19/2015
From: Nicholas Difrancesco
Japan Lessons-Learned Division
To: William Gideon
Progress Energy Carolinas
Wyman, Stephen, NRR/JLD 415-3041
References
TAC MF5228, TAC MF5229
Download: ML15313A245 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 19, 2015 Mr. William R. Gideon Brunswick Steam Electric Plant Site Vice President Brunswick Steam Electric Plant 8470 River Rd. SE (M/C BNP001)

Southport, NC 28461

SUBJECT:

BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 - STAFF REVIEW OF INTERIM EVALUATION ASSOCIATED WITH REEVALUATED SEISMIC HAZARD IMPLEMENTATING NEAR-TERM TASK FORCE RECOMMENDATION 2.1 (TAC NOS. MF5228 AND MF5229)

Dear Mr. Gideon:

By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information pursuant to Title 1O of the Code of Federal Regulations Part 50, Section 50.54(f) (hereafter referred to as the 50.54(f) letter). The request was issued as part of implementing lessons-learned from the accident at the Fukushima Dai-ichi nuclear power plant. to the 50.54(f) letter requested that licensees reevaluate seismic hazards at their sites using present-day methodologies and guidance. Enclosure 1, Item 6, of the 50.54(f) letter requested that licensees identify "interim evaluation and actions taken or planned to address the higher seismic hazard relative to the design basis as appropriate, prior to completion of the

[seismic] risk evaluation." In addition to the interim evaluation provided in the March 2014 Seismic Screening and Hazard report, the licensees for the Central and Eastern United States committed to providing the Expedited Seismic Evaluation Process (ESEP) report, an interim evaluation, by December 31, 2014.

By letter dated December 18, 2014 1 , Duke Energy Progress, Inc. (Duke, the licensee), provided its ESEP report in response to Enclosure 1, Item (6) of the 50.54(f) letter, for Brunswick Steam Electric Plant, Units 1 and 2 (Brunswick). The NRC staff assessed the licensee's implementation of the ESEP guidance through the completion of a reviewer checklist2. In support of NRC staff questions, Duke provided a response through an electronic reading room, clarifying submittal information. The NRC staff reviewed the response via the audit process and documented the results in an audit report 3 . Based on the NRC staff review of the ESEP report and responses to the staff's questions, the NRC staff concludes that the licensee's implementation of the interim evaluation meets the intent of the guidance.

1 The December 18, 2014, letter can be found under ADAMS Accession No. ML15005A074.

2 The Brunswick ESEP NRC review checklist can be found under ADAMS Accession No. ML15301A909.

3 The audit report of the Duke response to NRC staff questions can be found under ADAMS Accession No. ML15279A450.

W. Gideon The NRC staff concludes that, through the implementation of the ESEP guidance, the licensee identified and evaluated the seismic capacity of certain key installed mitigating strategies equipment that is used for core cooling and containment functions to cope with scenarios that involve a loss of all alternating current power and loss of access to the ultimate heat sink to withstand a seismic event two times the safe shutdown earthquake for Brunswick. The licensee's ESEP assessment provides additional assurance, which supports continued plant safety while the longer-term seismic evaluation is completed to support regulatory decision making. The NRC staff concludes that the licensee responded appropriately to Enclosure 1, Item (6) of the 50.54(f) letter. Application of this review is limited to the interim evaluation as part of the Recommendation 2.1 Seismic review.

If you have any questions, please contact me at (301) 415-1115 or via e-mail at Nicholas.DiFrancesco@nrc.gov.

icholas DiFrancesco, Senior Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-325 and 50-324 cc: Distribution via Listserv

W. Gideon The NRC staff concludes that, through the implementation of the ESEP guidance, the licensee identified and evaluated the seismic capacity of certain key installed mitigating strategies equipment that is used for core cooling and containment functions to cope with scenarios that involve a loss of all alternating current power and loss of access to the ultimate heat sink to withstand a seismic event two times the safe shutdown earthquake for Brunswick. The licensee's ESEP assessment provides additional assurance, which supports continued plant safety while the longer-term seismic evaluation is completed to support regulatory decision making. The NRC staff concludes that the licensee responded appropriately to Enclosure 1, Item (6) of the 50.54(f) letter. Application of this review is limited to the interim evaluation as part of the Recommendation 2.1 Seismic review.

If you have any questions, please contact me at (301) 415-1115 or via e-mail at Nicholas.DiFrancesco@nrc.gov.

Sincerely, IRA Nicholas DiFrancesco, Senior Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-325 and 50-324 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC JLD R/F RidsNrrPMBrunswick RidsNrrDorllpl2-2 RidsNrrLASLent RidsRgn2MailCenter RidsNrrOd DJackson, NRO MShams, NRR NDiFrancesco, NRR ADAMS Accession Number: ML15313A245 *via e-mail OFFICE NRR/JLD/JHMB/PM NRR/JLD/LA DSENRGS2 NAME SWyman Slent DJackson*

DATE 11/6/2015 11/12/2015 10/23/2015 OFFICE NRR/JLD/JHMB/BC NRR/JLD/JHMB/PM NAME MS hams NDiFrancesco DATE 11/18/2015 11/19/2015 OFFICIAL RECORD COPY