Letter Sequence Other |
|---|
|
Initiation
- Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
|
MONTHYEARML0932901092009-11-23023 November 2009 Request for Approval of Cyber Security Plan Project stage: Request ML1000800212010-01-11011 January 2010 Acceptance Review for License Amendment Request to Transition to Areva Fuel-Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2- Project stage: Acceptance Review ML1003409612010-02-23023 February 2010 Acceptance Review of Licensing Action Transition from Westinghouse to Areva Nuclear Fuel - Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Project stage: Acceptance Review ML1007103192010-03-22022 March 2010 Request for Additional Information, Transition from Westinghouse to Areva Advanced CE-14 Htp Fuel Project stage: RAI ML1011600782010-04-22022 April 2010 Response to Request for Additional Information - Transition from Westinghouse Nuclear Fuel to Areva Nuclear Fuel Project stage: Response to RAI ML1015302292010-06-23023 June 2010 Request for Additional Information Proposed Transition from Westinghouse to Areva Nuclear Fuel Project stage: RAI ML1017601942010-07-12012 July 2010 Request for Withholding Information from Public Disclosure Transition to Areva Fuel-Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Project stage: Withholding Request Acceptance ML1018100672010-07-12012 July 2010 Request for Additional Information Proposed Transition from Westinghouse to Areva Nuclear Fuel Project stage: RAI ML1020705512010-07-23023 July 2010 Response to Request for Additional Information Proposed Transition from Westinghouse to Areva Fuel Project stage: Response to RAI ML1022303402010-08-0909 August 2010 Response to Request for Additional Information - Proposed Transition from Westinghouse to Areva Nuclear Fuel Project stage: Response to RAI ML1030800252010-10-29029 October 2010 Supplement to the License Amendment Request: Transition from Westinghouse Nuclear Fuel to Areva Nuclear Fuel Project stage: Supplement ML1032800822010-11-19019 November 2010 Supplement to the License Amendment Request: Transition from Westinghouse Nuclear Fuel to Areva Nuclear Fuel Project stage: Supplement ML1100403742010-12-30030 December 2010 Supplement to the License Amendment Request: Transition from Westinghouse Nuclear Fuel to Areva Nuclear Fuel Project stage: Supplement ML1100401222010-12-30030 December 2010 Supplemental Information Regarding Generic Letter 2004-02 Project stage: Request ML1017605232011-01-0303 January 2011 Issuance of Environmental Assessment for Use of M5 Cladding Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Project stage: Approval ML1033700972011-01-0303 January 2011 Environmental Assessment and Finding of No Significant Impact Project stage: Request ML1030701892011-01-13013 January 2011 Docket Nos. 50-317 and 50-318 Exemption Project stage: Other ML1030701132011-01-13013 January 2011 Issuance of Exemption for Use of M5 Cladding Project stage: Approval ML1101806212011-01-14014 January 2011 Supplement to the License Amendment Request: Transition from Westinghouse Nuclear Fuel to Areva Nuclear Fuel Project stage: Supplement ML1102000652011-01-18018 January 2011 Supplement to the License Amendment Request: Transition from Westinghouse Nuclear Fuel to Areva Nuclear Fuel Project stage: Supplement ML1103202432011-01-28028 January 2011 Supplement to License Amendment Request: Transition from Westinghouse Nuclear Fuel to Areva Nuclear Fuel Project stage: Supplement ML1104505372011-02-11011 February 2011 Supplement to License Amendment Request: Transition from Westinghouse Nuclear Fuel to Areva Nuclear Fuel Project stage: Supplement ML1104704032011-02-15015 February 2011 Supplement to License Amendment Request: Transition from Westinghouse Nuclear Fuel to Areva Nuclear Fuel Project stage: Supplement ML1030103832011-02-17017 February 2011 Request for Withholding Information from Public Disclosure Transition to Areva Fuel Project stage: Withholding Request Acceptance ML1103902242011-02-18018 February 2011 License Amendment, Transition from Westinghouse Nuclear Fuel to Areva Nuclear Fuel Project stage: Other ML1103902632011-02-18018 February 2011 Non-Prop SE - Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 - License Amendment Transition from Westinghouse Nuclear Fuel to Areva Nuclear Fuel Project stage: Other ML1105301992011-02-23023 February 2011 Correction Letter to License Amendment No. 297 Project stage: Other ML15275A2772015-10-0202 October 2015 Formal Notification of New Fuel Design Project stage: Other ML16131A3832016-05-10010 May 2016 Formal Notification of New Fuel Design Project stage: Other 2010-08-09
[Table View] |
Text
200 Exelon Way Exelon Generation Kennett Square. PA 19348 www.exeloncorp.com October 2, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Renewed Facility Operating License Nos. DPR-53 and DPR-69 NRC Docket Nos. 50-317 and 50-318
Subject:
Formal Notification of New Fuel Design for Calvert Cliffs 10 CFR 50.90
References:
- 1. Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 - Amendment:
Transition from Westinghouse Nuclear Fuel to AREVA Nuclear Fuel (TAC Nos. ME2831 and ME2832), dated February 18, 2011.
- 2. Safety Evaluation of Siemens Power Corporation Topical Report EMF-92-116(P) "Generic Mechanical Design Criteria for PWR Fuel Designs," dated February 2, 1999.
- 3. License Amendment Request - Transition from Westinghouse Nuclear Fuel to AREVA Nuclear Fuel, dated November 23, 2009.
This letter satisfies Exelon Generation Company, LLC (Exelon) requirement as described in the Calvert Cliffs Fuel Transition Safety Evaluation Report (SER), dated February 18, 2011.
Specifically, page 4 of the SER [Reference 1] states:
"... Any first batch application of a new or modified assembly component design or material or first batch application of a prior assembly design or material to a new reactor meets the staff's interpretation of a new fuel design and necessitates formal notification in accordance with this SE [Reference 2]
restriction."
The current AREVA NP Inc. (AREVA) fuel design for Calvert Cliffs is described in of Reference 3. The AREVA fuel design includes the use of Ms for the fuel rod cladding and both end caps.
AREVA is implementing a change in material for the fuel rod end caps from MS to Zircaloy-4. The fuel rod cladding will continue to use Ms. This material change meets the threshold criteria for notification of the NRC per the SER requirements on page 4 of Reference 1.
Formal Notification of New Fuel Design for Calvert Cliffs October 2, 2015 Page 2 AREVA will start fabrication of the new fuel design in early 2016, and implement this change in 2017 starting with Calvert Cliffs Unit 2, Cycle 22 and follow-on reloads for both Calvert Cliffs units.
AREVA has communicated to Exelon that this design change was evaluated against the criteria contained in their approved methodology as described in Reference 2 and concluded that all criteria will continue to be satisfied. AREVA has confirmed to Exelon that the Zircaloy-4 material used for the end caps does not impact any of the design parameters considered in their approved methods.
Furthermore, AREVA concluded that the fuel rod welds behave comparably to welds using M5 end caps, with respect to mechanical properties, corrosion, LOCA, neutronics, and fuel rod growth. Therefore, there is no adverse impact on the fuel assembly's performance, safety, or reliability.
This letter satisfies Exelon requirement of notification to the NRC as described in Reference 1.
There are no regulatory commitments contained in this letter.
If you should have any questions regarding this submittal, please contact Enrique Villar at 610-765-5736.
Respectfully, Jama=:~
Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC cc:
NRC Project Manager, NRR - Calvert Cliffs NRC Regional Administrator, Region I NRC Resident Inspector, Calvert Cliffs S. T. Gray, MD-DNR