MONTHYEARIR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000318/LER-2023-004, Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-16016 January 2024 Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-002, Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-0808 January 2024 Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 ML23318A4722023-11-14014 November 2023 Supplement to License Amendment Request to Adopt TSTF-59-A ML23317A1032023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23310A0442023-11-0707 November 2023 Project Manager Assignment IR 05000317/20230402023-11-0202 November 2023 95001 Supplemental Inspection Report 05000317/2023040 and Follow-Up Assessment Letter IR 05000317/20230032023-11-0101 November 2023 Integrated Inspection Report 05000317/2023003 and 05000318/2023003 IR 05000317/20230902023-10-26026 October 2023 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000317/2023090 ML23289A1202023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23279A1202023-10-0606 October 2023 Response to NRC Inspection Report and Preliminary White Finding IR 05000317/20230502023-09-29029 September 2023 Special Inspection Report 05000317/2023050 and Preliminary White Finding and Apparent Violation ML23272A1032023-09-29029 September 2023 Condition Prohibited by Technical Specifications Due to Inoperable Nuclear Instrumentation at Very Low Power IR 05000317/20234012023-09-18018 September 2023 Cyber Security Inspection Report 05000317/2023401 and 05000318/2023401 ML23254A0012023-09-0505 September 2023 Registration of Use of Casks to Store Spent Fuel IR 05000317/20230052023-08-31031 August 2023 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2023005 and 05000318/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23241A8412023-08-29029 August 2023 Response to Request for Additional Information - Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping ML23240A3872023-08-28028 August 2023 Senior Reactor and Reactor Operator Initial License Examinations ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration ML23219A1662023-08-16016 August 2023 Request for Additional Information Regarding Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping (EPID: L-2023-LLR-0006) - Non-proprietary ML23228A1002023-08-15015 August 2023 Notification of Readiness for NRC 95001 Inspection ML23188A0402023-08-0808 August 2023 Issuance of Amendment Nos. 346 and 324 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 ML23214A1572023-08-0707 August 2023 Correction to the Renewed Facility Operating License Page 3 in Amendment No 345 IR 05000317/20230022023-08-0303 August 2023 Integrated Inspection Report 05000317/2023002 ML23188A0512023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 336 and 314 ML23186A0372023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 340 and 318 IR 05000317/20233012023-07-12012 July 2023 Initial Operator Licensing Examination Report 05000317/2023301 and 05000318/2023301 IR 05000317/20230122023-07-10010 July 2023 Commercial Grade Dedication Report 05000317/2023012 and 05000318/2023012 ML23180A2362023-06-29029 June 2023 Correction of Errors on Technical Specification Pages RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators ML23156A6752023-06-20020 June 2023 Request for Withholding Information from Public Disclosure for Proposed Alternative to the Requirements for Repair/Replacement of Saltwater System Buried Piping 2024-02-01
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARML23317A1032023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23241A8432023-08-29029 August 2023 Enclosure 3 - Response to Request for Additional Information - Non-Proprietary Version ML23241A8412023-08-29029 August 2023 Response to Request for Additional Information - Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping ML23166A1052023-06-15015 June 2023 Response to Request for Additional Information Related to the License Amendment Request to Modify the Long-Term Coupon Surveillance Program ML23155A0012023-06-0404 June 2023 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation to Support Review of an Emergency License Amendment Request - One-Time Extension of the Control Room Emergency Ventilation System (C RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator RS-22-084, Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator .2022-06-17017 June 2022 Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator . RS-22-074, Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds .2022-05-20020 May 2022 Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds . RS-22-027, Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated2022-02-23023 February 2022 Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated P ML21334A3422021-11-30030 November 2021 Supplement to Response to Request for Additional Information Regarding the Spent Fuel Pool Cooling - Shutdown Cooling Systems Licensing Design Basis License Amendment Request ML21320A2422021-11-16016 November 2021 Stations - Response to Request for Additional Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML21308A5072021-11-0404 November 2021 Supplement to Response to Request for Additional Information Regarding the Spent Fuel Pool Cooling - Shutdown Cooling Systems Licensing Design Basis License Amendment Request ML21298A0432021-10-25025 October 2021 Response to Request for Additional Information Regarding the Spent Fuel Pool Cooling - Shutdown Cooling Systems Licensing Design Basis License Amendment Request JAFP-21-0087, Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments2021-09-16016 September 2021 Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments ML21208A0072021-07-26026 July 2021 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-567 Rev 1, Add Containment Sump TS to Address GSI-191 Issues NMP2L2773, Company - Response to Request for Additional Information2021-06-30030 June 2021 Company - Response to Request for Additional Information JAFP-21-0044, Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments2021-06-11011 June 2021 Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments JAFP-21-0032, Response to Request for Additional Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting2021-04-20020 April 2021 Response to Request for Additional Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting RS-20-017, Response to Request for Additional Information - Proposed Alternative to Utilize Code Case N-8852021-02-0101 February 2021 Response to Request for Additional Information - Proposed Alternative to Utilize Code Case N-885 ML20317A1122020-11-12012 November 2020 Final Response and Close-out to Generic Letter 2004-02 ML20280A5132020-10-0606 October 2020 Response to Request for Additional Information - End of Interval Relief Request Associated with the Fourth Ten-Year Inservice Inspection (ISI) Interval ML20188A2642020-07-0606 July 2020 Clinton Power Station, R.E. Ginna Station, Limerick Station, Nine Mile Point Station & Peach Bottom Station - Proposed Alternative to Utilize Code Case OMN-26 - Response to Request for Additional Information ML20182A1102020-06-30030 June 2020 Response to Request for Additional Information to License Amendment Request - Proposed Changes to Technical Specification (TS) 3.8.1 Emergency Diesel Generator Surveillance Requirements Voltage ML20107F7652020-04-16016 April 2020 Response to Request for Additional Information to License Amendment Request - Revision to Technical Specification 5.5.7, Reactor Coolant Pump Flywheel Inspection Program NMP2L2711, Byron Station; Calvert Cliffs; Clinton Power Station; LaSalle County Station; Limerick Generating Station; and Nine Mile Point Nuclear Station - Proposed Alternative to Utilize Code Case N-8792019-10-16016 October 2019 Byron Station; Calvert Cliffs; Clinton Power Station; LaSalle County Station; Limerick Generating Station; and Nine Mile Point Nuclear Station - Proposed Alternative to Utilize Code Case N-879 ML19282B7182019-10-0909 October 2019 Revised Response to Request for Additional Information Regarding the Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML19277D1032019-10-0303 October 2019 Response to Request for Additional Information Revised - Final Response to Generic Letter 2004-02 ML19217A3372019-08-0606 August 2019 Response to RAI #6 Regarding the Application to Adopt 10 CFR 50.69 ML19217A1432019-08-0505 August 2019 Revised Response to Request for Additional Information Regarding the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML19200A2162019-07-19019 July 2019 Response to Request for Additional Information Regarding the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML19183A0122019-07-0101 July 2019 Response to Request for Additional Information Regarding the Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power ... JAFP-19-0057, Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-8802019-06-0404 June 2019 Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-880 NMP1L3279, Response to Request for Additional Information - Proposed Alternatives to Utilize Code Cases N-878 and N-880 for Plants2019-05-0101 May 2019 Response to Request for Additional Information - Proposed Alternatives to Utilize Code Cases N-878 and N-880 for Plants JAFP-19-0006, Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-8802019-01-0808 January 2019 Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-880 ML18316A0342018-11-12012 November 2018 Response to Request for Additional Information: Proposed Changes to Technical Specification 3.8.1 Actions A.3 and D.3 to Extend the Offsite Circuit Inoperable Completion Times from 72 Hours to 14 ... ML18283A0342018-10-10010 October 2018 Supplement to Final Response to Generic Letter 2004-02, Dated August 13, 2018 ML18239A2602018-08-27027 August 2018 Supplement to Response to Request for Additional Information License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk .. ML18201A4062018-06-21021 June 2018 Plants, Units 1 and 2 - Exelon'S Response to NRC Questions ML18172A1452018-06-21021 June 2018 Response to Request for Additional Information License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed ... NMP1L3221, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 & 2, R. E. Ginna - Response to Request for Additional Information License Amendment Request to Adopt Emergency Action Level Schemes.2018-05-10010 May 2018 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 & 2, R. E. Ginna - Response to Request for Additional Information License Amendment Request to Adopt Emergency Action Level Schemes. RS-18-061, Response to Request for Additional Information Regarding Decommissioning Funding Plans for Independent Spent Fuel Storage Installations (Isfsis)2018-05-0202 May 2018 Response to Request for Additional Information Regarding Decommissioning Funding Plans for Independent Spent Fuel Storage Installations (Isfsis) ML18047A1242018-02-16016 February 2018 Relief Requests Associated with Fifth Ten-Year Lnservice Testing Interval: Supplement 1 - Response to Request for Additional Information ML18025A7992018-01-25025 January 2018 Response to Request for Additional Information Regarding Generic Letter 2016-01 ML18018B3402018-01-18018 January 2018 Response to Request for Additional Information License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times. ML18011A6652018-01-11011 January 2018 Response to Request for Additional Information License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times. RS-17-053, Response to Request for Additional Information Regarding Generic Letter 2016-012017-04-27027 April 2017 Response to Request for Additional Information Regarding Generic Letter 2016-01 ML17081A3032017-03-22022 March 2017 Response to Request for Additional Information to License Amendment Request - Control Room Emergency Ventilation System RS-17-044, Response to Request for Additional Information Regarding Proposed Alternative for the Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography2017-03-13013 March 2017 Response to Request for Additional Information Regarding Proposed Alternative for the Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography RS-17-003, Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal2017-01-0505 January 2017 Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal ML16246A2022016-09-0101 September 2016 Response to Request for Additional Information Regarding Relief Request for Dissimilar Metal Butt Weld Examinations 2023-08-29
[Table view] |
Text
EExe~on Generation, .
10 CFR 50.54(f)
RS- 15-247 September 23, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Calvert Cliffs Nuclear Power Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-53 and DPR-69 NRC Docket Nos. 50-317 and 50-318
Subject:
Exelon Generation Company, LLC Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flood Hazard Reevaluation Report
References:
- 1. NRC Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012 (ML12053A340)
- 2. NRC Letter, Prioritization of Response Due Dates for Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Flooding Hazard Reevaluations for Recommendations 2.1 of the Near-Term Task Force Review of Insights From the Fukushima Dai-ichi Accident, dated May 11, 2012 (ML12097A0509)
- 3. Letter from David L. Skeen, U.S. Nuclear Regulatory Commission, to Joseph E. Pollock, Nuclear Energy Institute - Trigger Conditions for Performing an Integrated Assessment and Due Date for Response, dated December 3, 2012 (ML12326A912)
- 4. Letter from J. A. Spina (CENG) to Document Control Desk (NRC), Calvert Cliffs Nuclear Power Plant, Units 1 and 2, Flood Hazard Reevaluation Report, dated March 12, 2013 (ML13078A010)
- 5. Email from M. Thadani (NRC) to E. Tyler (CENG), "Calvert Cliffs R2.1 Flooding Reevaluations: RAIs," dated January 9, 2014 (ML14010A015)
- 6. Letter from Maria G. Korsnick to NRC dated February 10, 2014,
Subject:
Calvert Cliffs Nuclear Power Plant Units 1 and 2, Renewed Facility Operating License Nos. DPR-53 and DPR-69, Docket Nos. 50-317 and 50-318, Response to NRC 10 CFR 50.54(f)
Request for Information Regarding Near-Term Task Force Recommendation 2.1, Flooding-Flood Hazard Reevaluation, (ML14052A052)
- 7. Letter from Maria G. Korsnick to NRC dated March 7, 2014,
Subject:
Calvert Cliffs Nuclear Power Plant Units 1 and 2, Renewed Facility Operating License Nos. DPR-53 and DPR-69, Docket Nos. 50-317 and 50-31 8, Additional Response to NRC 10 CFR 50.54(f) Request for Information Regarding Near-Term Task Force Recommendation 2.1, Flooding-Flood Hazard Reevaluation, (ML14162A261) A I
U.S. Nuclear Regulatory Commission NTTF Recommendation 2.1 - Amended Flood Hazard Reevaluation Report for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 September 23, 2015 Page 2
- 8. NRC Letter, Response Requirements for Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Flooding Hazard Integrated Assessments for Recommendations 2.1 of the Near-Term Task Force Review of Insights From the Fukushima Dai-ichi Accident, dated November 21, 2014, (ML14303A465)
- 9. Calvert Cliffs Nuclear Power Plant, Units 1 And 2 - Staff Assessment of Response to 10 cFR 50.54(F) Information Request- Flood-Causing Mechanism Reevaluation (TAC Nos.
MF3097 And MF3098), Letter: NRC to George H GellInch, Dated April 16, 2015, (ML15077A103)
- 10. NRC Letter, Response Requirements for Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Flooding Hazard Integrated Assessments for Recommendations 2.1 of the Near-Term Task Force Review of Insights From the Fukushima Dai-ichi Accident, dated May 26, 2015, (ML15112A051)
On March12, 2012, the NRC issued Reference 1 to request information associated with Near-Term Task Force (NTTF) Recommendation 2.1 for Flooding. One of the ReqUired Responses in this letter directed licensees to submit a Flood Hazard Reevaluation Report, including the interim action plan requested in Item 1.d of Reference 1, Enclosure 2, if appropriate. In Reference 2, the NRC issued the prioritization plan developed by the NRC and the resultant Flood Hazard Reevaluation due dates for all sites. Reference 2, Enclosure 1 identified Calvert Cliffs Nuclear Power Plant, Units 1 and 2, as a Category 1 site requiring a Flood Hazard Reevaluation Report submittal due date of March 12, 2013. In Reference 4, Exelon Generation Company, LLC (EGO), previously Constellation Energy Nuclear Group, LLC (Exelon, the licensee) submitted the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 Flood Hazard ReevalUation Report.
During a conference call on December 11, 2014, EGO notified the NRC that the Calvedt Cliffs Nuclear Power Plant, Units 1 and 2, Flood Hazard Reevaluation Report (FHRR) would be amended to incorporate new information resulting from a site specific meteorological study being performed to more accurately characterize the flooding hazard.
The information in the enclosure to this letter provides the amended Calvedt Cliffs Nuclear Power Plant, Units 1 and 2 Flood Hazard Reevaluation Repodt. No changes were made to the following aspects of the flood hazard reevaluation:
- Flooding in Stream and Rivers;
- Dam Breaches and Failures;
- Ice Induced Flooding; and
- Channel Migration or Diversion.
The FHRR previously submitted, Reference 4, identified two hazards not bounded by the Current Licensing Basis (CLB), Local Intense Precipitation (LIP) and Probable Maximum Storm Surge (PMSS). Based on these results, Calvert Cliffs Nuclear Power Plant, Units 1 and 2
U.S. Nuclear Regulatory Commission NTTF Recommendation 2.1 - Amended Flood Hazard Reevaluation Report for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 September 23, 2015 Page 3 committed to Interim Actions and performance of an Integrated Assessment as described by the Trigger Points discussed in Reference 3.
By performing a site specific meteorological study, the amended FHRR results are now bounded by the Current Design Basis (CDB), which is part of the CLB, for the PMSS. For LIP, the peak reevaluated flood elevation of 43.64 feet MSL at the lA Emergency Diesel Generator (EDG) Building is bounded by the CDB elevation (44.8 feet MSL) at the same location. Other buildings were not analyzed for LIP in the CDB. Therefore, LIP was considered to be not bounded in these areas. "Scenario 2" of Reference 3 indicates that, if LIP is the only portion of the reevaluated hazard not bounded by the CDB, a limited evaluation Can be performed to assess the impact of the reevaluated LIP flood on the plant. Reference 3 also states that the results of the limited evaluation should be submitted with the FHRR report (in this case, the amended FHRR). A limited evaluation was conducted that involved reviewing unanalyzed areas for' potential ingreSs of floodwaters into structures containing safety related systems or components. The results of the review indicated that these structures are protected from LIP flood ingress up to elevation 45.0 feet MSL, by at least 0.14 foot above the maximum reevaluated LIP flood level.
Updated results for the LIP and PMSS from the amended FHRR, compared with the OLB, and results from the March 12, 2013 report are presented in Table 1, "Comparison of LIP and PMSS Results".
Table 1 - Comparison of LIP and PMSS Results Parameter CLB 0311 212013 Amended FHRR FHRR.
LIP (ft.-MSL) 44.81 45.1 - 47 43.64 - 44.86 PMSS + Wave Runu (ft-NGVD29) 28.14 31.30 26*81 1CLB value is for the 1A EDG Building only, where the peak reevaluated LIP flood elevation is computed to be 43.64 feet MSL. UFSAR does not identify LIP OLB for other buildings The enclosure to this letter provides the amended Calvert Cliffs Nuclear Power Plant, Units 1 and 2 Flood Hazard Reevaluation Report and identifies all of the FHRR sections and chapters affected by the amendment.
As a result of this amended FHRR, all of the flood causing mechanisms do not pose a potential for water ingress into any structure containing safety related systems or components.
Therefore*, no additional interim or compensatory actions are necessary. The existing commitments for interim actions to address the higher flooding hazards contained in Reference 4 are not being revised at this time.
This letter contains no new or revised regulatory commitments.
If you have any questions regarding this submittal, please contact Ron Gaston at (630) 657-3359.
U.S. Nuclear Regulatory Commission NTTF Recommendation 2.1 - Amended Flood Hazard Reevaluation Report for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 September 23, 2015 Page 4 I declare under penalty of perjury that the foregoing is true and correct. Executed on the 23 rd day of September 2015.
Respectfully submitted, c&vv~
James Barstow Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC
Enclosure:
Amendment 1 to the Flood Hazard Reevaluation Report for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 cc: Regional Administrator - NRC Region I NRC Senior Resident Inspector - Calvert Cliffs Nuclear Power Plant NRC Project Manager, NRR - Calvert Cliffs Nuclear Power Plant Ms. Tekia Govan, NRR/JLD/PPSD/HMB S. Gray, MD-.DNR