UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001
.op
'July 1, 1999 LICENSEES: Baltimore Gas and Electric Company and Duke Energy Corporation (Duke)
FACILITIES:
Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 and Oconee Nuclear Station Unit Nos. 1, 2, and 3
SUBJECT:
SUMMARY
OF JUNE 30, 1999 MEETING WITH BALTIMORE GAS AND ELECTRIC COMPANY (BGE) AND DUKE REGARDING LICENSE RENEWAL ACTIVITIES FOR CALVERT CLIFFS NUCLEAR POWER PLANT (CCNPP)
UNIT NOS. 1 AND 2, AND OCONEE NUCLEAR STATION (ONS) UNITS NOS.
1, 2, AND 3 On June 30, 1999, the Nuclear Regulatory Commission (NRC) staff held a public meeting with representatives of BGE and Duke at Rockville, Maryland, to discuss the status of the NRC's review of BGE's and Duke's license renewal applications (LRA) for the CCNPP Units 1, and 2 and the ONS Units 1, 2, and 3. Enclosure 1 to this meeting summary provides a list of the meeting attendees. Enclosure 2 provides a copy of slides that were used by the NRC, BGE, and Duke staff to summarize the status of the review of BGE's and Duke's LRAs.
Highlights from the BGE portion of the meeting:
The meeting began with a discussion of the status of BGE's LRA review. BGE stated that they were planning to submit their responses to the open items and confirmatory items contained in the safety evaluation report (SER) written on BGE's LRA by July 2, 1999, and that comments on the content of the SER would be forwarded by July 19, 1999. BGE then stated progress between the staff and BGE to address several of the open items had been good although there was one open item that concerned BGE which was related to the update of the final safety analysis report. As a result, BGE stated they were eager to work with the staff to resolve the issue. The NRC stated that both sides should plan on additional interaction to address this open item in the very near future and that the resolution of this item was necessary before issuance of the final SER. The NRC then summarized the status, as outlined in Enclosure 2, of recently completed activities in the environmental and inspection areas to support the review of BGE's LRA.
Highlights from the Duke portion of the meeting:
Duke noted that several items had been completed since the last management meeting.
Specifically, the staff issued the draft supplemental environmental impact statement on May 20, 1999, the first license renewal inspection report was issued on May 24, 1999, the draft safety evaluation for BAW-2248, "Reactor Vessel Internals Report" was issued on May 26, 1999, and the SER written on Duke's LRA for Oconnee was issued on June 16, 1999. Duke noted that it supported license renewal site inspections during June. The inspections were performed as part of the aging management review inspections that were scheduled for the week of July 12, 1999, and July 26, 1999. The staff had performed portions of the inspection early because Unit 1 was in an outage in June, which allowed the staff access to areas of the plant that would not be readily accessible during the July inspections. Duke noted that the three separate inspections in 9907120009 990701 PDR ADOCK 05000269 PD PDR July 1, 1999 June were a resource impact and that for future applications the staff should consider combining these inspections and should also consider that the staff may not be able to inspect a unit during an outage depending on the timing of submittals from future license renewal applications. The staff stated that it would consider this information for future applicants.
The staff and Duke noted that resolution of the issues associated with BAW-2248 would involve coordination with the Babcock and Wilcox owner's group as well as with Duke. Duke noted that a July 19, 1999, meeting is scheduled to discuss the open items in the draft safety evaluation for the BAW-2248. Duke indicated that the owner's group provided responses to the open items on June 30, 1999, and that during the July 19, 1999, meeting it was hoped that the staff and the owner's group could come to agreement on the resolution of the open items. During the July meeting Duke will also discuss how it intends to resolve the open items in the SER for Oconee that are related to BAW-2248.
David L. Solorio, Project Manager License Renewal and Standardization Branch Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Joseph M. Sebrosky, Project Manager License Renewal and Standardization Branch Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318 (BGE) 50-269, 50-270, and 50-287 (Duke)
Enclosures:
- 1. List of Attendees
- 2. Meeting Slides cc w/ encls: See next page DISTRIBUTION: See next page DOCUMENT NAME: G:\\RLSB\\SOLORIO\\June 30th 1999 BGE & Duke monthly management meeting summa.WPD OFFICE LA RLSB RLSB RLSB:D NAME El DISoloriov JMSebrosk ClGrimes DATE
///99 Ir7l /99 99 1/( /99 OFFICIAL RECORD COPY
Baltimore Gas & Electric Company Calvert Cliffs Nuclear Power Plant cc:
Unit Nos. 1 and 2 President Mr. Joseph H. Walter, Chief Engineer Calvert County Board of Public Service Commission of Commissioners Maryland 175 Main Street Engineering Division Prince Frederick, MD 20678 6 St. Paul Centre Baltimore, MD 21202-6806 James P. Bennett, Esquire Counsel Kristen A. Burger, Esquire Baltimore Gas and Electric Company Maryland People's Counsel P.O. Box 1475 6 St. Paul Centre Baltimore, MD 21203 Suite 2102 Baltimore, MD 21202-1631 Jay E. Silberg, Esquire Shaw, Pittman, Potts, and Trowbridge Patricia T. Birnie, Esquire 2300 N Street, NW Co-Director Washington, DC 20037 Maryland Safe Energy Coalition P.O. Box 33111 Mr. Bruce S. Montgomery, Director Baltimore, MD 21218 NRM Calvert Cliffs Nuclear Power Plant Mr. Loren F. Donatell 1650 Calvert Cliffs Parkway NRC Technical Training Center Lusby, MD 20657-4702 5700 Brainerd Road Chattanooga, TN 37411-4017 Resident Inspector U.S. Nuclear Regulatory Commission David Lewis P.O. Box 287 Shaw, Pittman, Potts, and Trowbridge St. Leonard, MD 20685 2300 N Street, NW Washington, DC 20037 Mr. Richard I. McLean Nuclear Programs Douglas J. Walters Power Plant Research Program Nuclear Energy Institute Maryland Dept. of Natural Resources 1776 I Street, N.W.
Tawes State Office Building, B3 Suite 400 Annapolis, MD 21401 Washington, DC 20006-3708 DJW@NEI.ORG Regional Administrator, Region I U.S. Nuclear Regulatory Commission Barth W. Doroshuk 475 Allendale Road Baltimore Gas and Electric Company King of Prussia, PA 19406 Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Mr. Charles H. Cruse, Vice President NEF 1st Floor Nuclear Energy Division Lusby, Maryland 20657 Baltimore Gas and Electric Company 1650 Calvert Cliffs Parkway National Whistleblower Center Lusby, MD 20657-47027 3233 P Street, N.W.
Washington, DC 20007
Oconee Nuclear Station (License Renewal) cc:
Ms. Lisa F. Vaughn Duke Energy Corporation Mr. J. E. Burchfield 422 South Church Street Compliance Manager Mail Stop PB-05E Duke Energy Corporation Charlotte, North Carolina 28201-1006 Oconee Nuclear Site P. 0. Box 1439 Anne W. Cottingham, Esquire Seneca, South Carolina 29679 Winston and Strawn 1400 L Street, NW.
.Ms.
Karen E. Long Washington, DC 20005 Assistant Attorney General North Carolina Department of Justice Mr. Rick N. Edwards P.0. Box629 Framatome Technologies Raleigh, North Carolina 27602 Suite 525 1700 Rockville Pike L. A. Keller Rockville, Maryland 20852-1631 Manager - Nuclear Regulatory Licensing Duke Energy Corporation Manager, LIS 526 South Church Street NUS Corporation Charlotte, North Carolina 28201-1006 2650 McCormick Drive, 3rd Floor Clearwater, Florida 34619-1035 Mr. Richard M. Fry, Director Division of Radiation Protection Senior Resident Inspector North Carolina Department of U. S. Nuclear Regulatory Commission Environment, Health, and 7812B Rochester Highway Natural Resources Seneca, South Carolina 29672 3825 Barrett Drive Raleigh, North Carolina 27609-7721 Regional Administrator, Region II U. S. Nuclear Regulatory Commission Gregory D. Robison Atlanta Federal Center Duke Energy Corporation 61 Forsyth Street, SW, Suite 23T85 Mail Stop EC-12R Atlanta, Georgia 30303 P. 0. Box 1006 Charlotte, North Carolina 28201-1006 Virgil R. Autry, Director Division of Radioactive Waste Management Robert L. Gill, Jr.
Bureau of Land and Waste Management Duke Energy Corporation Department of Health and Mail Stop EC-12R Environmental Control P. 0. Box 1006 2600 Bull Street Charlotte, North Carolina 28201-1006 Columbia, South Carolina 29201-1708 RLGILL@DUKE-ENERGY.COM County Supervisor of Oconee County Douglas J. Walters Walhalla, South Carolina 29621 Nuclear Energy Institute 1776 1 Street, NW W. R. McCollum, Jr., Vice President Suite 400 Oconee Site Washington, DC 20006-3708 Duke Energy Corporation DJW@NEl.ORG P. 0. Box 1439 Seneca, SC 29679
.Chattooga River Watershed Coalition P.O. Box 2006 Clayton, GA 30525
NRC MANAGEMENT MEETING TO DISCUSS STATUS OF BGE & DUKE LRA REVIEW ATTENDANCE LIST JUNE 30, 1999 NAME TITLE JAKE ZIMMERMAN NRC/DRIP/RLSB JIM ANDERSON NRC/DRIP/RLSB WILLIAM KENWORTHY GSI JENNY WElL MCGRAW-HILL STEVE HOFFMAN NRC/DRIP/RLSB JIM WILSON NRC/DRIP/RGEB TOM KENYON NRC/DRIP/RGEB VICTOR MCCREE REGION II DAVID SOLORIO NRC/DRIP/RLSB JACK STROSNIDER NRC/DE JOE SEBROSKY NRC/DRIP/RLSB CHRIS GRIMES NRC/DRIP/RLSB SCOTT NEWBERRY NRC/DRIP DICK HEIBEL BGE DON SHAW BGE ROBERT GILL DUKE ENERGY MIKE TUCKMAN DUKE ENERGY GREG ROBISON DUKE ENERGY JIM BENNETT BGE CHRISTER DAHLGREN JANUS LYNN CONNOR DSA SHERRY BERNHOFT FPC MICHAEL SEMMLER DUKE ENERGY MARK RINCKEL FRAMALOME PAUL COLAIANNI DUKE POWER
MEETING SLIDES
a Duke Powe Oconee License Renewal Project Duke/NVRC Management meeting 9,9-99F-99-4gggg June 30, 1999 MDuke C&Power.
A D&E.
Agenda a Safety Review a Environmental Review a Expectations a Meeting Plans June 30, 1999 Oconee License Renewal Project 2
MDuke SPower A D,6 wVQM"YSafety Review Chronolog a Received Inspection Report 99-11 on May 24 documenting results of first onsite license renewal inspection
- Received the NRC draft Safety Evaluation on the BWOG Reactor Vessel Internals Report, BAW-2248, on May 26 a Supported phone calls on May 27 and June 2 with the staff on several questions
- Supported NRC license renewal site inspections during the weeks of June 1, June 7 and June 21
- Received the NRC Safety Evaluation Report on June 16 a Submitted letter on June 22 describing our scoping process (per commitment made May 11, 1999) a Presentations to ACRS License Renewal Subcommittee on June 30 June 30, 1999 Oconee License Renewal Project 3
If Duke r&Power.
AD. -V C",
Safety Review Highights a Fifteen additional questions were addressed during phone calls on May 27 and June 2 in support of the Safety Evaluation Report
- BWOG Reactor Vessel Internals report (BAW-2248):
- The Draft SE has been reviewed and comments will be submitted shortly by BWOG
- BWOG/Duke/NRC Meeting scheduled for July 19
- Oconee-specific responses to Renewal Applicant Action Items will be provided following issuance of the final SE by the staff June 30, 1999 Oconee License Renewal Project 4
2
t Po we Safety Evaluation Report Initial Feedback E 43 Open Items, 6 Confirmatory Items a 28 of 49 items are relatively straight forward to address a 3 of 49 items concern portions of the UFSAR Supplement a 18 of 49 items will require meetings to address/resolve:
- 1. Scoping Process and Results
- 2. Complex Assembly Boundaries
- 3. Consumables
- 4. CASS Components
- 5. RV Internals a Duke plans to provide written comments and responses to open items and confirmatory items by September 30 June 30, 1999 Oconee License Renewal Project 5
r P Duke A DJ-ffVC-p.ySite Inspections a Inspectors have been onsite the weeks of June 1, June 7 and June 21 during the Unit 1 RFO to perform portions of the Aging Management Review, inspection a No major concerns have been identified a Results of these inspections will be described in the Inspection Report for the 2nd site inspection a The Aging Management Program Site Inspection is scheduled for the weeks of July 12th and 26th June 30, 1999 Oconee License Renewal Project 6
3
A Dwi EwVScoping Methodology a Safety Evaluation Report Open Item 2.1.3.1-1 captures the issue that has arisen concerning the basis of the scoping criteria used in the Oconee License Renewal 54.4 mechanical scoping a Most recent interactions:
- 3/11/99 NRC/Duke Technical Meeting
- 3/18/99 Duke letter Providing additional description
- 3/25/99 NRC/Duke Telecon
- 5/11/99 NRC/Duke Management Meeting
- 6/22/99 Duke letter describing the process N Issue status
- The scoping process is consistent with the Oconee CLB and meets the requirements of Part 54
- Duke is awaiting NRC approval of the scoping process June 30, 1999 Oconee License Renewal Project 7
&Duke
&Po wer.
A DJEnvironmental Reve s Received the draft Supplemental Environmental Impact Statement on May 21, 1999 m Public meeting scheduled for July 8 in Clemson, SC m Duke is reviewing the draft SEIS a We agree with the conclusion that the environmental impacts of Oconee license renewal are not significant a Written comments will be provided by August 16 June 30, 1999 Oconee License Renewal Project a
4
,, W~fke ower Expectations Sxpectations to be accomplished by next NRC/Duke Managemnt~ Meeting
- Conduct Environmental Public Meeting on July 8,1999 (NRC Staff)
- RV Internals Meeting on July 19 (BWOG, Duke and NRC Staff)
- Process Safety Evaluation Report Open Items (Duke and NRC Staff)
- Conduct Aging Management Programs Site Inspection (Weeks of July 12th and 26th) (Duke and NRC Staff)
June 30, 199g Oconee License Renewal Project 9
Duke Power.
a Schedule for next NRC/Duke management
+ July 28, 1999
- August 27, 1999
- September date not set June 30, 1999 Oconee License Renewal Project 10 5
Calvert Cliffs License Renewal Application Status Report to the US Nuclear Regulatory Commission Dick Heibel, Manager, Nuclear Projects Don Shaw, Senior Engineer, LR Project June 30, 1999
Objectives of Meeting
- Brief NRC line management on progress of license renewal application review
- Determine if any issues need elevating to NRC Steering Committee by BGE or NRC,
- Establish performance indicators for next review meeting CCNPP License Renewal Status Report to the USNRC 2
99-030
Proposed Performance Indicators for June 1999
- Safety Review Open Items and Confirmatory Items "resolved" 2
- SEIS Comments reviewed for any new and significant information 1
- Region I AMR Inspection report issued
- ACRS interim letter open items, if any, have success paths or are closed (letter issued, no open items)
- Staff has information necessary to recommend finding in 10CFR54.29 ;
CCNPP License Renewal Status Report to the USNRC 3
99-030
June 1999 Calvert Cliffs LRA Report Card June 30, 1999
June 1999 Report Card
- Schedule Adherence
- Accomplishments On track Nearly all SER Ols and Cis
- Quality of Work resolved Regional AMR inspection Good report issued
- Communications SEIS comments reviewed Good no new & significant information identified
- Concerns UFSAR update illustration exercise needs to be comp leted CCNPP License Renewal Status Report to the USNRC 5
99-030
Technical Review SER being reviewed for "accuracy Open Items/Confirmatory Items Response in Site Review, targeted for July 2 submittal General Comments to be Submitted by July 19 due date CCNPP License Renewal Status Report to the USNRC 6
99-030
Proposed Performance Indicators for July 1999
- All SER Responses submitted
- Gameplan established for UFSAR Supplement Open Item and Exchanges Begun CCNPP License Renewal Status Report to the USNRC 7
99-030
NRC Schedule for BGE Calvert Cliffs License Renewal Application CCNPP License Renewal Status Report to the USNRC 8
99-030
NRC Overall Schedule 1998 4/10/98 - Application Submitted - completed 5/10/98 - Acceptance and Docketing Completed - completed 7/8/98
- Notice of Opportunity for Hearing Filed by NRC - completed 7/7-7/10 - NRC Environmental Site/Public Visit - completed 7/9/98
- Public Meetings for Environmental Impact Statement Scoping - completed 8/7/98 Filing of Intervener Petitions Ends - completed 9/7/98
- NRC Completes Technical Requests for Additional Information (RAI) - completed 9/28/98 -
Management Progress Review - completed CCNPP License Renewal Status Report to the USNRC 9
99-030
NRC Overall Schedule 1998 (continued) 10/1/98 - Deadline for Whistleblower Center Filing - completed 10/7/98 - NRC Completes Environmental RAls - completed 10/16/98-Whistleblower Center Petition Dismissed - completed 10/22/98-BGE EQ Presentation to NRC Staff - completed 10/29/98-Management Program Review; NRC Steering Committee Meeting - completed 11/21/98-BGE Completes Technical Responses - completed 12/6/98 - BGE Completes Environmental Responses - completed 12/16/98-Management Progress Review - completed CCNPP License Renewal Status Report to the USNRC 10 99-030
NRC Overall Schedule 1999-2000 1/14/99 - Management Progress Review - completed 2/26/99 Management Progress Review - completed 3/6/99 NRC Issues Draft Supplemental Environmental Impact Statement (SEIS) for Comment - completed 3/21/99 -
NRC Completes Initial Safety Evaluation Report (SER) and Open Items - completed 4/6/99 Public Meeting for Draft SEIS Comments - completed 5/5/99 ACRS Meeting - completed 5/20/99 - NRC Comment Period on Draft SEIS Closes - completed 7/19/99 -
BGE Completes Response to SER 11/16/99-NRC Issues Final SER and SEIS TBD Commission Decision on Application CCNPP License Renewal Status Report to the USNRC 99-030
Oconee License Renewal Application Status Report to Duke Energy June 30,1999
Oconee Renewal Status 6/30/99 Schedule Adherence SER issued on 6/16/99 Draft SEIS issued by the staff on 5/20/99 Public meeting to receive comments on the draft SEIS is scheduled for 7/8/99.
On 4/15/99, the Commission affirmed the Atomic Safety and Licensing Board decision denying Chattooga River Watershed Coalition's petition to intervene. Deadline to file an appeal has passed with no appeal being filed.
I
Oconee Renewal Status (cont) 6130/99 Accomplishments SER and draft SEIS issued ahead of schedule Communications continue to be good Region-based inspection status Public meeting held at site on 5/26/99 to discuss results of first regional-based inspection. First inspection looked at the scoping and screening process.
Second regional based inspection, currently scheduled for the weeks of 7/12/99 and 7/26/99, will concentrate on the aging management review. Regional and headquarters staff have already begun portions of this inspection.
2
Oconee Renewal Status (cont) 6/30/99 Accomplishments (cont)
Draft safety evaluation for BAW-2248, "Demonstration of the Management of Aging Effects for the Reactor Vessel Internals," issued on 5/26/99 Concerns Identify process to close-out 43 open items and 6 confirmatory items Resolution of open items associated with BAW-2248 3
Oconee Renewal Status (cont) 6/30/99 Concerns (cont) 10 CFR Part 54 Scoping Issue Duke provided response to SER open item on 6/22/99 Staff evaluating need and scope of additional activities required to resolve open item 4
Status Report on Baltimore Gas and Electric Company License Renewal Application June 30, 1999 David Matthews, Director, Division of Regulatory Improvement Programs Chris Grimes, Branch Chief, License Renewal & Standardization Branch
Summary of LRA Review Activities Open Item & Confirmatory Items BGE submitted several responses, documented in 6/17/99 letter Conference calls to clarify question or response 2
Summary of LRA Review Activities - cont.
- Environmental Review Status
- End of public comment period 5/20/99
- Staff received 17 submittals with comments
- Staff evaluating and will be addressing public comments in Final EIS
Summary of LRA Review Activities - cont.
Inspection Status IR 99-04 on aging management 5/21/99
- Concluded there was reasonable assurance the effects of aging will be adequately managed to maintain intended functions of SSCs during period of extended operation 4
Summary of LRA Review Activities-cont.
Inspection Status - cont.
- NRC identified few potential/plausible aging effects not addressed - action taken
- NRC identified cases where existing procedures or programs credited were not currently able to completely manage aging effect - action taken 5
Summary of LRA Review Activities - cont.
Petitioner Status
- DC Court set schedule for briefing NWC's appeal of Commissions decision NWC's brief 6/14/99 NRC's brief 7/14/99 BGE & NEI briefs 7/29/99 NWC's reply 8/12/99 Oral argument 10/6/99 6
DISTRIBUTION:
Hard copy D-cketF-iie PUBLIC RLSB RF N. Dudley, ACRS - T2E26 EHylton E-mailW.
Cook R. Zimmerman MEvans W. Kane R.Bores D. Matthews S.Stewart S. Newberry F. Bower C. Grimes B. Latta C. Carpenter B. Zalcman R. Emch J. Strosnider D. LaBarge R. Wessman L. Plisco E. Imbro C. Ogle W. Bateman R. Trojanowski J. Calvo M. Scott H. Brammer C. Julian T. Hiltz J. Peralta G. Holahan J. Wilson T. Collins C. Sochor C. Gratton C.
GrttonD.
Walters, NEI B. Boger R. Gill, Duke R. Correia R. Latta J. Moore J, Rutberg R. Weisman M. Zobler M. Mayfield S. Bahadur N. Chokshi J. Vora A. Murphy D. Martin W. McDowell S. Droggitis RLSB Staff S. Bajwa A.FDromerick T. Kenyon KD Leigh W.CHeh.