June 18, 1979 Docket Nos. 50-269/270/287 Mrs. Peggy Cover Clemson University Library Science, Technology and Agricultural Services
- Clemson, SC 29631
Dear Mrs. Cover:
Enclosed are copies of reportable occurrence-reports and the April 1979 performance and operating status report for Duke Power Company's Oconee Nuclear Station. As we discussed, these documents:.are being sent to the Library at the request of Berniece Holt and are for use by the students and faculty of Clemson Universityand members of the general public. As additional reports are received, they will be sent to you.for incorporation into these files.
Thank you for your assistance in helping us make these documents available to the public. -If you. have any questions regarding this material, please feel free to-contact me in writing or by phone at (301) 492-7536.
Sincerely, Jona L. Souder, Chief Local Public Document Room Branch Division of Rules and Records Office of Administration
Enclosures:
- 1. Reportable Occurrence File.
DISTRIBUTION:
- 2. Performance & Operating Status Docket File Report File LPDR
- 3.
List of. Documents Transmitted NRC PDR JFelton cc:
Ms. Berniece B. Holt Hoefling, OELD Ketchen, OELD
. O Fairtile, PM 790827 RIngram, LA KClark, PAO, Region II S.............
SURNAME
.S D A Tr *
./
7....
N OM87)C2u.
.ovRNE PRINING NRC FORM 31 -8 (9-76) NRCM 0240
- U1 S. GOVERNMEZNt PRINTING OFFICE: 1976 626-62Z
DOCUMENTS TRANSMITTED TO CLEMSON UNIVERSITY RE DUKE POWER COMPANY, OCONEE NUCLEAR STATION Reportable Occurrences RO 287/79-10 RO 269/79-12 RO 269/79-13 RO 269/79-14 NRC Notification of RO 269/79-13 NRC Notification of RO 269/79-16 Monthly Operating Report April 1979 Performance & Operating Status Report
~
DISTRIBUTION:
L;;uocket File UNITED STATES ORB#4 HI Rdg NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555
.May 30, 1979 Docket No. 50-269/270/287 Addressees:
See next page
Subject:
OCONEE UNITS NOS. 1, 2 & 3 The following documents concerning our review of the subject facility are transmitted for your information:
0I Notice of Receipt of Application.
El Draft/Final Environmental Statement, dated O
Safety Evaluation, or Supplement No.
, dated Notice of Hearing on Application for Construction Permit.
Notice of Consideration of Issuance of Facility Operating License.
El Application and Safety Analysis Report, Vol.
O Amendment No.
to Application/SAR, dated OI Construction Permit. No. CPPR-
. dated Facility Operating License No. DPR-
, NPF-dated Ol Amendment No....
to CPPR -
or DRR -
,dated.
Other: Monthly Operating Report for April 1979 Division of Operating Reactors, ORB#4 Office of Nuclear Reactor Regulation
Enclosures:
As stated cc:
OFFICE T OR.#4MRMb1 RIngram/cb SURNAME I
/797 DATE_ _ _I 1
NRC-21. (6-76)
Duke Power Company 2
Chief Division of Ecological Services Bureau of Sport Fisheries & Wildlife U. S. Department of the Interior Washington, D. C. 20240 Director National Oceanographic Data Center Environmental Data Service National Oceanic & Atmospheric Administration U. S. Department of Commerce Washington, D. C. 20235 Dr. James T. Tanner National Bureau of Standards Reactor Building 235 Washington, D.C.
20234 Director, Technical Assessment Division Office of Radiation Programs (AW-459)
U. S. Environmental Protection Agency Crystal Mall #2 Arlington, Virginia 20460 U. S. Environmental Protection Agency Region IV Office ATTN:
'EIS COORDINATOR 345 Courtland Street, NE Atlanta, Georgia 30308
eRcUNITED STATES o
NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 May 29, 1979 OFFICE OF THE SECRETARY Director Office of the Federal Register National Archives and Records Service Washington, D.C. 20403
Dear Sir:
Enclosed for publication in the Federal Register are an original and two certified copies of a document entitled:
DUKE POWER COMPANY Docket Nos. 50-269/270/287 NOTICE OF AUTHdRIZATION D RESUME OPERATION Publication of the above document at the earliest possible date would be appreciated.
This material is to be charged to requisition number E-146.
Sincerely, Samuel J. Chilk Secretary of the Comission
Enclosures:
Original and 2 certified copies bcc:
ra '
adsF-ailit' R'-rnch Office of Public Affairs Executive Legal Director Office of Congressional Affairs Office of the General Counsel SECY -
C&R Branch
/0 u-u I UNITED STATES NUCLEAR REGULATORY COMMISSION DUKE POWER COMPANY DOCKETS NOS. 50-269, 50-270, AND 50-287 NOTICE OF AUTHORIZATION TO RESUME OPERATION The United States Nuclear Regulatory Commission issued an Order on May 7, 1979 (44 F.R. 27776, May 11, 1979), to Duke Power Company (the licensee), holder of Facility Operating Licenses Nos. DPR-38, DPR 47 and DPR-55 for Oconee Nuclear Station, Units Nos. 1, 2 and 3, con firming that the licensee accomplish a series of actions, both immediate and long term, to increase the capability and reliability of Oconee Units Nos. 1, 2 and 3 to respond to various transient events. In addition, the Order confirmed that the licensee would shut down Oconee 3 on April 28, 1979, an additional Oconee unit on May 12, 1979, and remaining unit on May 19, 1979, unless, with respect to the latter two units, the following actions had been accomplished prior to the prescribed dates:
(a) Install automatic starting of the interconnected emergency feedwater system so that all three pumps will receive a start signal from any affected unit, and test the system for stability. The emergency feedwater pump discharge flow will be connected to the interconnection headers such that each or all of the emergency feedwater pumps can supply water to any unit. Until these modifications and tests are completed, operating personnel will be stationed at each emergency feedwater pump with a direct communication link to that unit's control room. In addition, the following procedural changes, put into effect on April 25, 1979 to enhance the reliability of the emergency feedwater system, will remain in force:
(1)
The discharges of these pumps have been tied together by alignment of manual valves such that each and all of the pumps can supply emergency feedwater to any Oconee Unit requiring it.
7590-01
-2 (2) Administrative controls have been established so that in the event of loss of both main feedwater pumps on an affected unit, that unit's emergency feedwater pump will start automatically, backed up by remote manual start from the control room. If the pump fails to start automatically, the operator stationed at that pump will start the pump locally, and has been trained to do so, In addition, the other two available emergency feedwater pumps will be started remotely from their unit's control room or locally if required to provide two more sources of feedwater to the affected unit.
(3) Emergency feedwater flow to the steam generators will be assured by the control room operator who has been trained to maintain the necessary level.
(b) Develop and implement operating procedures for initiating and controlling emergency feedwater independent of Integrated Control System control.
(c) Implement a hard-wired control-grade reactor trip on loss of main feedwater and/or turbine trip.
(d) Complete analyses for potential small breaks and develop and implement operating instructions to define operator action.
(e) All licensed reactor operators and senior reactor operators assigned to the Oconee Control rooms will have completed the Three Mile Island Unit No. 2 simulator training at Babcock & Wilcox.
By submittal of May 7, 1979, as supplemented by two letters dated May 9, 1979, the licensee has documented the actions taken in response to the May 7 Order. Notice is hereby given that the Director of Nuclear Reactor Regulation (the Director) has reviewed this submittal and has concluded that the licensee has satisfactorily completed the actions prescribed in items (a) through (e) of paragraph (1) of Section IV of the Order, that the specified analyses are acceptable and the specified implementing procedures are appropriate. Accordingly, by letter dated May 18, 1979, the Director has authorized the licensee to resume or continue operation of Oconee Units. 1, 2 and 3.
The bases for the Director's conclusions are more fully set forth in a Safety Evaluation dated May 18, 1979.
7590-01 3
Copies of (1) the licensee's letter dated May 7, 1979, and two letters dated May 9, 1979, (2) the Director's letter dated May 18, 1979 and (3) the Safety Evaluation dated May 18, 1979 are available for inspection at the Commission's Public Document Room at 1717 H Street, N.W., Washington, D.C. 20555, and are being placed in the Commission's local public document room at the Oconee County Library, 201 South Spring, Walhalla, South Carolina 29691. A copy of items (2) and (3) may be obtained upon re quest addressed to the U. S. Nuclear Regulatory Commission, Washington, D.C.
20555, Attention:
Director, Division of Operating Reactors.
FOR THE NUCLEAR REACTOR REGULATION Robert W. Reid, Chief Operating Reactors Branch #4 Division of Operating Reactors Dated at Bethesda, Maryland this 18th day of May 1979.