Docket Nos.:
50-269, 50-270 and 50-287 December 15, 1987 Mr. H. B. Tucker, Vice President Nuclear Production Department Duke Power Company 422 South Church Street Charlotte, North Carolina 28242
Dear Mr. Tucker:
Subject:
Errors Found in Correspondence Re:
Oconee Units 1, 2, and 3 A review of your correspondence shows that several errors have been made.
You have been using an incorrect docket number for Oconee Unit 3. For example, in Licensee Event Reports (LERs) dated December 7, November 25 (two LERs) and November 23, you used docket no. 50-289 (for Three Mile Island, Unit 1) instead of 50-287 for Oconee Unit 3. These are only some examples.
Also, you have been using inconsistent dates in LERs. For example, in LER 269/87-05 the event date in block 5 and the event date in the abstract are different. In LER 287/86-03, again the event date in block 5 is differ ent from the event date in the abstract.
Please correct these inconsistencies and errors. Thank you.
Sincerely, Helen N. Pastis, Project Manager Project Directorate 11-3 Division of Reactor Projects-I/II cc: See next page DISTRIBUTION:
NRC PDR Local PDR PRC System PD23 Reading MRood HPastis ACRS (10) 8712162076 PDR.
ADOCO 0O0269i ii OGC-Bethesda R
EJordan JStone SVa
/GLainas P# -3/DRP-I/II PDJI3/DRP-I/II PD#I r/DRP I/II is/mac MR Actin PD 12/
/87 12// V/87 12/1 T/87
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 December 15, 1987 Docket Nos.:
50-269, 50-270 and 50-287 Mr. H. B. Tucker, Vice President Nuclear Production Department Duke Power Company 422 South Church Street Charlotte, North Carolina 28242
Dear Mr. Tucker:
Subject:
Errors Found in Correspondence Re:
Oconee Units 1, 2, and 3 A review of your correspondence shows that several errors have been made.
You have been using an incorrect docket number for Oconee Unit 3. For example, in Licensee Event Reports (LERs) dated December 7, November 25 (two LERs) and November 23, you used docket no. 50-289 (for Three Mile Island, Unit 1) instead of 50-287 for Oconee Unit 3. These are only some examples.
Also, you have been using inconsistent dates in LERs. For example, in LER 269/87-05 the event date in block 5 and the event date in the abstract are different. In LER 287/86-03, again the event date in block 5 is differ ent from the event date in the abstract.
Please correct these inconsistencies and errors. Thank you.
Sincerely, Helen N. Pastis, Project Manager Project Directorate 11-3 Division of Reactor Projects-I/II cc:
See next page
Mr. H. B. Tucker Oconee Nuclear Station Duke Power Company Units Nos. 1, 2 and 3 cc:
Mr. A. V. Carr, Esq.
Mr. Paul Guill Duke Power Company Duke Power Company P. 0. Box 33189 Post Office Box 33189 422 South Church Street 422 South Church Street Charlotte, North Carolina 28242 Charlotte, North Carolina 28242 J. Michael McGarry, III, Esq.
Bishop, Liberman, Cook, Purcell & Reynolds 1200 Seventeenth Street, N.W.
Washington, D.C. 20036 Mr. Robert B. Borsum Babcock & Wilcox Nuclear Power Generation Division Suite 525 1700 Rockville Pike Rockville, Maryland 20852 Manager, LIS NUS Corporation 2536 Countryside Boulevard Clearwater, Florida 33515 Senior Resident Inspector U.S. Nuclear Regulatory Commission Route 2, Box 610 Seneca, South Carolina 29678 Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street, N.W., Suite 2900 Atlanta, Georgia 30323 Mr. Heyward G. Shealy, Chief Bureau of Radiological Health South Carolina Department of Health and Environmental Control 2600 Bull Street Columbia, South Carolina 29201 Office of Intergovernmental Relations 116 West Jones Street Raleigh, North Carolina 27603 Honorable James M. Phinney County Supervisor of Oconee County Walhalla, South Carolina 29621