Other: ML14034A339, ML14037A228, ML14056A067, ML15147A056, ML15253A721, RC-13-0109, Online Reference Portal for Review of Mitigation Strategies, Submittal in Response to Order EA-12-049, RC-13-0123, V. C. Summer, Unit 1 - First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049), RC-14-0030, South Carolina Electric & Gas Companys Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External, RC-14-0144, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-04), RC-15-0030, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, RC-15-0031, Fourth 6-Month Status Report of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, RC-15-0126, Fifth 6-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)
|
MONTHYEARML13183A1142013-07-0909 July 2013 (Vcsns), Unit 1, Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 Project stage: Approval RC-13-0109, Online Reference Portal for Review of Mitigation Strategies, Submittal in Response to Order EA-12-0492013-07-26026 July 2013 Online Reference Portal for Review of Mitigation Strategies, Submittal in Response to Order EA-12-049 Project stage: Other RC-13-0123, V. C. Summer, Unit 1 - First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2013-08-28028 August 2013 V. C. Summer, Unit 1 - First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) Project stage: Other 05000395/LER-2013-004, Regarding Spray System Relief Valve Failure to Lift at Required Setpoint Renders the Reactor Building Spray System Inoperable2013-09-30030 September 2013 Regarding Spray System Relief Valve Failure to Lift at Required Setpoint Renders the Reactor Building Spray System Inoperable Project stage: Request ML14056A0672014-02-21021 February 2014 Fifth Batch SE Final Revision 3- 1 Site (VC Summer) Project stage: Other ML14037A2282014-02-21021 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Virgil C. Summer Nuclear Station, Unit 1, TAC MF2338 Project stage: Other ML14034A3392014-02-21021 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Other RC-14-0030, South Carolina Electric & Gas Companys Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External2014-02-27027 February 2014 South Carolina Electric & Gas Companys Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Project stage: Other RC-14-0144, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-04)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-04) Project stage: Other RC-15-0031, Fourth 6-Month Status Report of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2015-02-27027 February 2015 Fourth 6-Month Status Report of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Other RC-15-0030, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML15147A0562015-06-0202 June 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other RC-15-0126, Fifth 6-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)2015-08-20020 August 2015 Fifth 6-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) Project stage: Other ML15253A7212015-09-16016 September 2015 Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML15243A4502015-10-0404 October 2015 Relaxation of the Schedule Requirements of Order EA-12 049 Issuance of Order T Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events Project stage: Approval RC-16-0001, V.C. Summer, Report of Full Compliance with March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) and Responses to Requests for Additional Information2016-01-22022 January 2016 V.C. Summer, Report of Full Compliance with March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) and Responses to Requests for Additional Information Project stage: Response to RAI RC-16-0028, Notification of an Intended Changed to a Commitment Date for Response to Request for Additional Information Regarding Phase 2 Staffing Submittals Associated with Near-Term Task Force Recommendation 9.3 Related to the Fukushima2016-02-26026 February 2016 Notification of an Intended Changed to a Commitment Date for Response to Request for Additional Information Regarding Phase 2 Staffing Submittals Associated with Near-Term Task Force Recommendation 9.3 Related to the Fukushima Project stage: Response to RAI 2014-08-28
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 4, 2015 Mr. Thomas D. Gatlin, Vice President Nuclear Operations South Carolina Electric and Gas Company Virgil C. Summer Nuclear Station Post Office Box 88, Mail Code 800 Jenkinsville, SC 29065
SUBJECT:
VIRGIL C. SUMMER NUCLEAR STATION, UNIT 1 - RELAXATION OF THE SCHEDULE REQUIREMENTS OF ORDER EA-12-049, "ISSUANCE OF ORDER TO MODIFY LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS" (TAC NO. MF2338)
Dear Mr. Gatlin:
By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12054A735), the U.S. Nuclear Regulatory Commission (NRC) ordered South Carolina Electric and Gas Company (SCE&G, the licensee) to take certain actions at Virgil C. Summer Nuclear Station, Unit 1 (VCSNS), associated with the Fukushima Near-Term Task Force Recommendations. Order EA-12-049 directed that actions be taken by licensees to develop and implement strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities during beyond-design-basis external events.
Section IV of the order states that licensees proposing to deviate from requirements contained in NRC Order EA-12-049 may request that the Director, Office of Nuclear Reactor Regulation, relax or rescind certain conditions. By letter dated August 13, 2015 (ADAMS Accession No. ML15231A025), SCE&G submitted a request for relaxation of the schedule requirement for full implementation for VCSNS, Unit 1, as prescribed in Section IV A.2 of NRC Order EA-12-049. That requirement states, in part, "All holders of operating licenses issued under Part 50... shall complete full implementation no later than two (2) refueling cycles after submittal of the overall integrated plan, as required in Condition C.1.a, or December 31, 2016, whichever comes first."
The licensee stated in its request that the second refueling outage will commence in October 2015. Therefore, consistent with the schedule requirements of Order EA-12-049, full implementation of the mitigating strategies for VCSNS must be completed prior to startup from the fall 2015 refueling outage (RF-22). The licensee requested that the required date for full implementation for VCSNS be relaxed until July 31, 2016. The requested schedule relaxation would allow the licensee additional time to design and implement a new alternate emergency feedwater suction strategy, update FLEX procedures, and complete training associated with this new FLEX Strategy.
In its August 13, 2015, letter, SCE&G noted that the Condensate Storage Tank (CST) does not
meet the high wind protection from the tornado hazard requirements in Nuclear Energy Institute (NEI) 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision 0, and therefore cannot be credited for those events. The licensee identified this vulnerability during its April 2015 FLEX Self-Assessment. As such, VCSNS is pursuing an alternate emergency feedwater suction strategy to supply water to the Turbine Driven Emergency Feedwater Pump in the event the CST is rendered inoperable. The July 31, 2016, relaxation date was also requested due to the number of procedure changes and station training activities scheduled for the first quarter of 2016 to ensure compliance with the National Fire Protection Association 805 standard by March 31, 2016.
In its August 13, 2015, letter, SCE&G stated that if the CST is unavailable during this relaxation period, the station has the capacity to take suction from the Demineralization Water Storage Tank (DWST) and Filtered Water Storage Tank (FWST) for emergency feedwater (EFW).
Although the DWST and FWST are not protected, these two sources would be preferred over the Monticello Reservoir or Service Water Pond due to the improved water quality. Further defense in depth is provided because the station can also deploy a Pumper Truck or the Ultimate Heat Sink System to provide water from the Monticello Reservoir or Service Water Pond. In addition to maintaining the non-protected water sources described above, VCSNS will implement the following interim action after the fall 2015 refueling outage (RF-22) until the alternate EFW modification, procedure changes and associate training can be completed. The Operations Administrative Policy (OAP) -1 09.1, "Guidelines for Severe Weather," will be changed so that after a tornado watch has been issued for the VCSNS area, the Emergency Response Unit personnel will be instructed to deploy a Pumper Truck to a location where Beyond-Design-Basis Mitigating Guideline (BDMG)-5, "Manually Depressurize SGS [steam generator system] and Use Low Pressure Water Sources (Turbine Driven Emergency Feedwater Pump Not Available)," can be performed. This will enable restoration per BDMG-5, as quickly as possible. The licensee also stated that the other FLEX equipment, modifications, and procedures required to implement the mitigating strategies, required by Order EA-12-049, will be completed and available for use in accordance with the implementation schedule requirements specified in the order.
In light of the facts presented, the NRC staff has determined that the licensee has demonstrated good cause to relax the order implementation date. The NRC staff agrees that, based on the importance of the alternate EFW suction strategy, additional time is warranted to ensure a successful strategy is developed and implemented with procedures and training completed as necessary. The NRC staff also considered that, following the accident at Fukushima Dai-ichi, the NRC concluded that a sequence of events such as the Fukushima Dai-ichi accident is unlikely to occur in the United States, based on the current regulatory requirements and existing plant capabilities. Therefore, the extension of time (approximately eight months) for VCSNS to achieve full implementation of the requirements of the mitigation strategies order is justified.
Given the plant-specific circumstances at VCSNS, and that the proposed completion date is prior to the ultimate December 2016 implementation date of the order, the NRC staff approves the relaxation request.
Accordingly, based upon the authority granted to the Director, Office of Nuclear Reactor Regulation, the requirement of the order for full order implementation for VCSNS is relaxed until July 31, 2016.
If you have any questions, please contact Tony Brown at 301-415-1924.
Sincerely, William M. Dean, Director Office of Nuclear Reactor Regulation Docket No. 50-395 cc: Listserv
ML15243A450 OFFICE NRR/JLD/JOMB NRR/JLD NRR/DORL/LPL2-1
- NAME TBrown Slent SWilliams DATE 9/3/2015 9/3/2015 9/3/2015 OFFICE OE OGC NRR/JLD NAME RFretz DCylkowski JDavis DATE 9/9/2015 9/21/2015 9/24/2015