Informs That safety-grade Design of Anticipatory Reactor Trip Sys Is Acceptable.Environ Qualification Review of Applicable Components Incomplete.Safety Evaluation Providing Basis for Installation & Operation of Sys Encl
ML15238B235
Person / Time
Site: Oconee  
Issue date: 12/04/1980
From: Reid R
Office of Nuclear Reactor Regulation
To: Parker W
DUKE POWER CO.
Shared Package
ML15238B236 List:
References
NUDOCS 8012290480
Download: ML15238B235 (3)


Text

DECEMBER 0 4 198 DISTRIUTW

~

AO j1 TR BNIS1G -AEOD ORB#4dg-ray, File C P

~TDR, MFairtile-Phc PBender L PDR RReid PBendet TERA-3 RUngram HOrnstein Dockets'Nos.

69, 50-270 EBlackwood and 60-DEisenhut RPurple ACRS-16JRoe OELD RTedeo Mr. William 0. Parker, Jr.

GLainas Vice President - Steam Production TNoyak Duke Power Company P. 0. Box 2178 422 South Church Street Charlotte, North Carolina 28242

Dear Mr. Parker:

By letter dated Augtust 18 1980 you submitted information requested by our December 20, 1979 letter regarding the safety-grade anticipatory reactor trip (ART) system design.

e requested this information in order to complete our review of your proposed up rade of the AT system from control grade to safety-grade.

Based on our review in the enclosed Safety Evaluation, we conclude that the safety-grade design of the 'ARt system satfisfies the safety require ments and criteria of redundac independence; single failure and testa bility; therefore, we find the design acceptable.

The environmental qualification review of the applicable components of the system Is incomplete.

Our Sa'fety Evaluation provides the basis for installation and operation of the system prior to metion of our equip ment qualifiction review.

Within 60 days of receipt of this letter, kindly submit appropriate Tech nical Specifications including "'Limiting Cond.itioIs f O

a a

veilance Requirements for the ART system.

'Sincerely, Originligned by

'Robert W. Reid

'Robert W. Reid,. Chief Operating Reactors Branch 4

'Division of Licensing Encldy ure:

Safety Evaluation cc w/enclosure: See next page 8012290 ORB 4:L OFFICE,.

SURNAME031 l

a.cb

.DATE80 NFC FORM.3j.49-76) NRCM 0240 U.S. GOVERNMENT PRINTING OFFICE: 1979-289-369

o UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON. D. C. 20555 December 4, 1980 Dockets Nos. 50-269, 50-270 and 50-287 Mr. William 0. Parker, Jr.

Vice President - Steam Production Duke Power Company P. 0. Box 2178 422 South Church Street Charlotte, North Carolina 28242

Dear Mr. Parker:

By letter dated August 18, 1980 you submitted information requested by our December 20, 1979 letter regarding the safety-grade anticipatory reactor trip (ART) system design. We requested this information in order to complete our review of your proposed upgrade of the ART system from control grade to safety-grade.

Based on our review in the enclosed Safety Evaluation, we conclude that the safety-grade design of the ART system satisfies the safety require ments and criteria of redundancy, independence, single failure and testa bility; therefore, we find the design acceptable.

The environmental qualification review of the applicable components of the system is incomplete.

Our Safety Evaluation provides the basis for installation and operation of the system prior to completion of our equip ment qualification review.

Within 60 days of receipt of this letter, kindly submit appropriate Tech nical Specifications including Limiting Conditions for Operation and Sur veillance Requirements for the ART system.

Sincerely, Robert W. Reid, Chief Operating.Reactors Branch #4 Division of Licensing

Enclosure:

Safety Evaluation cc w/enclosure:

See next page

Duke Power Company cc w/enclosure(s):

Mr. William L. Porter Duke Power Company P. 0. Box 2178 422 South Church Street Office of Intergovernmental Relations Charlotte, North Carolina 28242 116 West Jones Street Raleigh, North Carolina 27603 Oconee Public Library 201 South Spring Street Walhalla, South Carolina 29691 Honorable James M. Phinney County Supervisor of Oconee County Walhalla, South Carolina 29621 Director, Criteria and Standards Division Office of Radiation Programs (ANR-460)

U. S. Environmental Protection Agency Washington, D..C. 20460 U. S. Environmental Protection Agency Region IV Office ATTN: EIS COORDINATOR 345 Courtland Street, N.E.

Atlanta, Georgia -30308 Mr. Francis Jape U.S. Nuclear Regulatory Commission Route 2, Box 610 Seneca, South Carolina 29678 Mr. Robert B. Borsum Babcock & Wilcox Nuclear Power Generation Division Suite 420, 7735 Old Georgetown Road Bethesda, Maryland 20014 Manager, LIS NUS Corporation 2536 Countryside Boulevard Clearwater, Florida 33515 J. Michael McGarry, III, Esq.

DeBevoise & Liberman 200 17th Street, N.W.

Washington, D. C. 20036