2015/06/22 Pre-Submittal Teleconference Meeting Slides: LOCA Analyses Supporting MPS2 Upgrade to Areva Standard CE14 Htp Fuel Assembly
ML15198A343
Person / Time
Site: Millstone Dominion icon.png
Issue date: 06/22/2015
From: Craft W
Dominion, Dominion Nuclear Connecticut
To: Richard Guzman
Plant Licensing Branch 1
Guzman R
References
Download: ML15198A343 (14)


Text

Pre-Submittal P S b itt l Teleconference T l f for LOCA Analyses Supporting Millstone Power Station, Unit 2 Upgrade pg to AREVA Standard CE14 HTP Fuel Assembly Junee 22,, 2015 Ju 0 5

Agenda

1) Background on fuel product upgrade at Millstone Power Station Unit 2 (MPS2)
2) Licensing Li i overviewi for f fuel f l product d t upgrade d
3) License Amendments for LOCA Analyses
  • Small Break Loss of Coolant Accident (SBLOCA)
  • Large Break Loss of Coolant Accident (LBLOCA) 4)) Licensing ce s g ttimeline/schedule e e/sc edu e
5) Future Dominion/NRC interactions Pg. 2

Background on Fuel Product Upgrade

  • Goal is to implement the change for Cycle 25 (Spring 2017)
  • Upgrade pg fuel p product is called the AREVA Standard CE14 HTP Fuel Assembly
  • Upgrades pg to the current MPS2 fuel p product:

- M5 cladding

- Advanced fuel rod geometry Zircaloy-44 MONOBLOC' guide tubes

- Zircaloy Pg. 3

Licensing Overview

  • Dominion identified 2 required submittals:

- M5 LAR and Exemption Request

  • Amendment approved on May 18, 2015

- LAR to add RLBLOCA topical report to MPS2 TS 6.9.1.8 (list of analytical methods used to determine COLR limits)

  • Statement made to NRC in a Dominion letter dated November 1, 2012 regarding SBLOCA:

- A reanalysis of the SBLOCA event will be submitted within one year of NRC approval of Supplement 1 to the AREVA SBLOCA methodology

- NRC reiterated in Sleicher-Rouse Closure Evaluation dated July 18, 2013

  • To address above statement, SBLOCA LAR will upgrade EM to Supplement 1 of EMF-2328(P)(A)

Pg. 4

SBLOCA Analysis

  • Analysis completed using EMF-2328(P)(A) including Supplement 1

- Analysis conforms to draft NRC safety evaluation

- Change to TS 6.9.1.8 will add Supplement 1 to Reference 5

- LAR will omit revision number and vendor names to avoid confusion

- Dominion plans to submit LAR in July 2015 (more schedule discussion later))

- Dominion seeks NRC feedback on referencing the draft SE Pg. 5

SBLOCA Analysis

  • Analysis of Record (AOR) presented in the LAR was performed for fuel product with M5 cladding

- Assessment performed for full core of the fuel product with Zr-4 cladding to develop PCT for comparison to the AOR (fuel product with M5 cladding)

- PCT difference will be maintained as a 10 CFR 50.46 estimate until fuel product p

with Zr-4 cladding is non-limiting

- Addressing the fuel product with Zr-4 cladding explicitly supports implementation oof tthee LAR with w t SBLOCA S OC EM Supp Supplement e e t 1 soo soon aafter te NNRC C app approval ova

  • No need to wait for fuel product with M5 cladding introduction in 2017

- Dominion prefers this approach as the AOR represents the M5 clad fuel configuration fi ti th thatt will ill be b usedd for f compliance li with ith 50.46c 50 46

- Dominion seeks NRC feedback on this approach Pg. 6

SBLOCA Analysis

  • SBLOCA LAR will incorporate Supplement 1 of EMF-92-116(P)(A)

- RODEX used to develop fuel rod inputs for SBLOCA analysis

- Change g to TS 6.9.1.8 will add Supplement pp 1 to Reference 16

- LAR will remove the revision number and omit vendor names to avoid confusion Pg. 7

LBLOCA Analysis

  • Analysis completed using EMF-2103(P)

EMF 2103(P) Revision 3

- Analysis is in progress and is being performed in accordance with the submitted EM as modified by the AREVA RAI responses

- AREVA engineering products for MPS2 will be completed after affirmation from NRC that RAI responses from January 2015 are acceptable

- LAR A willill be b submitted b i d after f reviewi off the h ddraft f NRC C SE S to ensure conformance f

- Analysis does not apply to the fuel product with Zr-4 cladding. Implementation of the LAR will be requested for the Spring 2017 refueling outage with first use of the fuel product with M5 cladding

- Fuel product with Zr-4 cladding will be addressed for mixed cores

- Dominion seeks NRC feedback on referencing the draft SE in the LAR Pg. 8

Licensing timeline/schedule

  • Need LOCA Analysis LARs approved by October 2016
  • Supports M5 Cladding for Cycle 25 (Spring 2017)
  • SBLOCA schedule has delayed 10 months from the initial project schedule presented in July 2013

- Planned l d submittal b i l date d still ill allows ll for f 12 monthh NRC review i off the h LAR

  • LBLOCA schedule has delayed at least 6 months from the initial project schedule presented in July 2013

- Planned submittal date still allows for 12 month NRC review of the LAR with minimal schedule float Pg. 9

SBLOCA Licensing timeline/schedule Pg. 10

LBLOCA Licensing timeline/schedule Pg. 11

Future Dominion/NRC Interactions

  • Implementation of the fuel product upgrade at MPS2 for Cycle 25 in Spring 2017 relies on the schedule presented
  • LAR with SBLOCA analysis to be submitted in July 2015 with reference to draft SE
  • LAR with LBLOCA analysis to be submitted in September 2015 with reference to draft SE

- Schedule depends on NRC agreement with AREVA RAI responses

  • Potential re-work of AREVA engineering products for MPS2 Pg. 12

Discussion Pg. 13

Acronym List

  • AOR Analysis of Record
  • CFR Code of Federal Regulations
  • COLR Core Operating Limits Report
  • EM Evaluation Model
  • HTP High Thermal Performance
  • LAR License Amendment Request
  • LBLOCA Large Break Loss of Coolant Accident
  • LOCA Loss of Coolant Accident
  • MPS2 Millstone Power Station, Unit 2
  • RAI Request for Additional Information
  • RLBLOCA Realistic Large Break Loss of Coolant Accident
  • SBLOCA Small Break Loss of Coolant Accident
  • SE Safety Evaluation
  • TS Technical Specifications Pg. 14