Letter Sequence Other |
---|
|
|
MONTHYEARRS-14-306, First Six-Month Status Report Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses W/ Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Condition2014-12-17017 December 2014 First Six-Month Status Report Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses W/ Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Condition Project stage: Other ML15089A4212015-04-0101 April 2015 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-13-109,Severe Accident Capable Hardened Vents. Project stage: Other RS-15-152, Second Six-Month Status Report for Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe..2015-06-30030 June 2015 Second Six-Month Status Report for Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe.. Project stage: Other RS-17-069, Sixth Six-Month Status Report for Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe..2017-06-27027 June 2017 Sixth Six-Month Status Report for Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe.. Project stage: Other 2015-04-01
[Table View] |
|
---|
Category:Letter type:RS
MONTHYEARRS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-078, Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval2024-08-20020 August 2024 Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations RS-24-053, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed2024-06-0606 June 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-042, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-05-10010 May 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-046, 10 CFR 50.46 Annual Report2024-05-0606 May 2024 10 CFR 50.46 Annual Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-032, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-04-0505 April 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-019, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF2024-03-19019 March 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF RS-24-020, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS2024-03-15015 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS RS-24-015, Submittal of RP-01 Relief Request Associated with the Sixth Inservice Testing Interval2024-02-29029 February 2024 Submittal of RP-01 Relief Request Associated with the Sixth Inservice Testing Interval RS-24-001, Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2024-01-0303 January 2024 Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-128, Response to Request for Additional Information for the Emergency License Amendment Request – Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-15015 December 2023 Response to Request for Additional Information for the Emergency License Amendment Request – Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-104, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-113, Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 262023-10-20020 October 2023 Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 26 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-089, Sixth Ten-Year Interval Inservice Testing Program2023-09-0505 September 2023 Sixth Ten-Year Interval Inservice Testing Program RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-086, Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-08-28028 August 2023 Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-060, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2023-06-0808 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors RS-23-059, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0808 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-22-067, 10 CFR 50.46 Annual Report2023-05-0404 May 2023 10 CFR 50.46 Annual Report RS-23-068, Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell2023-04-28028 April 2023 Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell RS-23-058, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges2023-04-24024 April 2023 Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-007, Application to Adopt TSTF-564, Safety Limit MCPR2023-03-0303 March 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-032, Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location2023-02-0303 February 2023 Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location RS-23-034, Notification of Extension to the Fifth Ten-Year Interval of the Inservice Testing Program2023-02-0202 February 2023 Notification of Extension to the Fifth Ten-Year Interval of the Inservice Testing Program RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-23-033, Request for Exemption from 10 CFR 2.109(b)2023-01-27027 January 2023 Request for Exemption from 10 CFR 2.109(b) RS-23-005, Response to Request for Additional Information for Quad Cities Relief Request RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves2023-01-17017 January 2023 Response to Request for Additional Information for Quad Cities Relief Request RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves RS-22-127, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-10 Reactor Pressure Vessel Penetration N-11B Repair2022-12-14014 December 2022 Submittal of Sixth Inservice Inspection Interval Relief Request I6R-10 Reactor Pressure Vessel Penetration N-11B Repair RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-119, Withdrawal of Relief Request RV-11 Associated with the Sixth Inservice Testing Interval2022-10-31031 October 2022 Withdrawal of Relief Request RV-11 Associated with the Sixth Inservice Testing Interval RS-22-109, Response to Request for Additional Information License Amendments Related to Fuel Storage2022-10-12012 October 2022 Response to Request for Additional Information License Amendments Related to Fuel Storage RS-22-112, Submittal of RV-04 Relief Request Associated with the Sixth Inservice Testing Interval2022-10-0707 October 2022 Submittal of RV-04 Relief Request Associated with the Sixth Inservice Testing Interval RS-22-108, Response to Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage2022-10-0505 October 2022 Response to Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-102, Supplement to Request to Revise Technical Specification 3.1.4, Control Rod Scam Times2022-08-18018 August 2022 Supplement to Request to Revise Technical Specification 3.1.4, Control Rod Scam Times RS-22-095, Response to Request for Additional Information Regarding Request to Expand Applicability of GNF Thermal Mechanical Analysis Methods to Framatome Fuel2022-08-10010 August 2022 Response to Request for Additional Information Regarding Request to Expand Applicability of GNF Thermal Mechanical Analysis Methods to Framatome Fuel RS-22-096, Response to Request for Additional Information Related to Relief Request I6R-01 Associated with the Sixth Inservice Inspection Interval2022-08-10010 August 2022 Response to Request for Additional Information Related to Relief Request I6R-01 Associated with the Sixth Inservice Inspection Interval 2024-08-20
[Table view] Category:Status Report
MONTHYEARML23044A3662023-02-15015 February 2023 Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III ML21091A0362021-03-30030 March 2021 Midamerican Energy Company, Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1), Including ISFSI Decommissioning Funding (10 CFR 72.30) RS-18-011, Tenth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design-Basis External Events ...2018-02-28028 February 2018 Tenth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design-Basis External Events ... RS-17-156, Seventh Six-Month Status Report for Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe.2017-12-11011 December 2017 Seventh Six-Month Status Report for Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe. RS-17-097, Ninth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2017-08-28028 August 2017 Ninth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) RS-17-069, Sixth Six-Month Status Report for Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe..2017-06-27027 June 2017 Sixth Six-Month Status Report for Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe.. RS-17-045, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2017-03-30030 March 2017 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-16-046, Annual Property Insurance Status Report2017-03-29029 March 2017 Annual Property Insurance Status Report RS-17-022, Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2017-02-28028 February 2017 Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events RS-17-008, Fifth Six-Month Status Report for Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident.2017-01-26026 January 2017 Fifth Six-Month Status Report for Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident. RS-16-150, Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-08-26026 August 2016 Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-16-110, Fourth Six-Month Status Report for Phases 1 & 2 Overall Integrated Plan in Response to 06/06/2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2016-06-30030 June 2016 Fourth Six-Month Status Report for Phases 1 & 2 Overall Integrated Plan in Response to 06/06/2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions RS-16-094, Property Insurance Status Report for Braidwood Station, Byron Station, Calvert Cliffs, Clinton Power, Dresden Nuclear, LaSalle County, Limerick Generating, Nine Mile Point, Oyster Creek, Peach Bottom, Quad Cities, R.E Ginna, Three Mile Isl2016-04-25025 April 2016 Property Insurance Status Report for Braidwood Station, Byron Station, Calvert Cliffs, Clinton Power, Dresden Nuclear, LaSalle County, Limerick Generating, Nine Mile Point, Oyster Creek, Peach Bottom, Quad Cities, R.E Ginna, Three Mile Isla RS-15-215, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order.2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order. RS-15-152, Second Six-Month Status Report for Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe..2015-06-30030 June 2015 Second Six-Month Status Report for Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe.. RS-15-024, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-15-033, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RS-14-213, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-14-025, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)2014-02-28028 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) RS-14-015, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design-Basis External Events (Order No. EA-12-049)2014-02-28028 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design-Basis External Events (Order No. EA-12-049) RS-13-128, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RS-13-129, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-13-100, Report on Status of Decommissioning Funding for Reactors2013-04-0101 April 2013 Report on Status of Decommissioning Funding for Reactors RA-13-030, Annual Property Insurance Status Report2013-04-0101 April 2013 Annual Property Insurance Status Report ML13091A0112013-03-27027 March 2013 Midamerican Energy Company'S Decommissioning Funding Status Report for Their Twenty-Five Percent Share of Quad Cities, Units 1 and 2, Pursuant to 10 CFR 50.75(f)(1) RA-12-032, Annual Property Insurance Status Report2012-03-30030 March 2012 Annual Property Insurance Status Report ML1009200492010-04-0101 April 2010 Annual Property Insurance Status Report ML0909202562009-04-0101 April 2009 Annual Property Insurance Status Report RS-09-041, Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC2009-03-31031 March 2009 Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC ML0709305562007-03-30030 March 2007 Submittal of Midamerican Energy Company'S 2006 Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1) ML0509101242005-03-30030 March 2005 Decommissioning Funding Status Report Pursuant to 10 CFR 50.75(f)(1) ML0508703272005-03-25025 March 2005 Annual Property Insurance Status Report RS-05-035, Report on Status of Decommissioning Funding for Reactors2005-03-24024 March 2005 Report on Status of Decommissioning Funding for Reactors ML0226002922002-09-17017 September 2002 Memorandum Regarding Report on the Status of Open TIAs Assigned to NRR 2023-02-15
[Table view] |
Text
Exelon Generation Order No. EA-13-109 RS-15-152 June 30, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRG Docket Nos. 50-254 and 50-265
Subject:
Second Six-Month Status Report For Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)
References:
- 1. NRG Order Number EA-13-109, "Issuance of Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," dated June 6, 2013
- 2. NRG Interim Staff Guidance JLD-ISG-2015-01, "Compliance with Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 0, dated April 2015
- 3. NEI 13-02, "Industry Guidance for Compliance with NRG Order EA-13-109, BWR Mark I
& II Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 1, dated April 2015
- 4. Exelon Generation Company, LLC's Answer to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated June 26,2013
- 5. Exelon Generation Company, LLC Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated June 30, 2014 (RS-14-063)
- 6. Exelon Generation Company, LLC First Six-Month Status Report Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated December 17, 2014 (RS-14-306)
- 7. NRG letter to Exelon Generation Company, LLC, Quad Cities Nuclear Power Station, Units 1 and 2 - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Phase 1 of Order EA-13-109 (Severe Accident Capable Hardened Vents) (TAC Nos.
MF4460 and MF4461), dated April 1, 2015
U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-13-109 June 30, 2015 Page2 On June 6, 2013, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to Exelon Generation Company, LLC (EGC). Reference 1 was immediately effective and directs EGC to require their BWRs with Mark I and Mark II containments to take certain actions to ensure that these facilities have a hardened containment vent system (HCVS) to remove decay heat from the containment, and maintain control of containment pressure within acceptable limits following events that result in loss of active containment heat removal capability while maintaining the capability to operate under severe accident (SA) conditions resulting from an Extended Loss of AC Power (ELAP). Specific requirements are outlined in of Reference 1.
Reference 1 required submission of a Phase 1 Overall Integrated Plan pursuant to Section IV, Condition D by June 30, 2014. Reference 2 endorses industry guidance document NEI 13-02, Revision 1 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the EGC initial answer to the Order regarding reliable hardened containment vents capable of operation under severe accident conditions. Reference 5 provided the Quad Cities Nuclear Power Station, Units 1 and 2 Phase 1 Overall Integrated Plan.
Reference 1 requires submission of a status report at six-month intervals following submittal of the Phase 1 overall integrated plan. Reference 3 provides direction regarding the content of the status reports. Reference 6 provided the first six-month status report pursuant to Section IV, Condition D.3 of Reference 1 for Quad Cities Station. The purpose of this letter is to provide the second six-month status report for Phase 1 pursuant to Section IV, Condition D.3, of Reference 1, that delineates progress made in implementing the requirements of Reference 1.
The enclosed report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any. The enclosed report also addresses the NRC Interim Staff Evaluation open items contained in Reference 7.
This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact David P. Helker at 610-765-5525.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 30th day of June 2015.
Respectfully submitted,
&;~~
Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC
Enclosure:
Quad Cities Nuclear Power Station, Units 1 and 2 Second Six-Month Status Report for Phase 1 Implementation of Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions
U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-13-109 June 30, 2015 Page3 cc: Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region 111 NRC Senior Resident Inspector - Quad Cities Nuclear Power Station, Units 1 and 2 NRC Project Manager, NRR - Quad Cities Nuclear Power Station, Units 1 and 2 Mr. Charles H. Norton, NRR/JLD/PPSD/JOMB, NRC Mr. John P. Boska, NRR/JLD/JOMB, NRC Illinois Emergency Management Agency - Division of Nuclear Safety
Enclosure Quad Cities Nuclear Power Station, Units 1 and 2 Second Six-Month Status Report for Phase 1 Implementation of Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (7 pages)
Enclosure Quad Cities Nuclear Power Station, Units 1 and 2 Second Six Month Status Report for the Implementation of Order EA-13-109, "Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions" 1 Introduction Quad Cities Nuclear Power Station, Units 1 and 2 (Quad Cities Station) developed an Overall Integrated Plan (Reference 1), documenting the installation of a Hardened Containment Vent System (HCVS) that provides a reliable hardened venting capability for pre-core damage and under severe accident conditions, including those involving a breach of the reactor vessel by molten core debris, in response to Reference 2. This enclosure provides an update of milestone accomplishments since submittal of the Phase 1 Overall Integrated Plan First Six Month Update, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
2 Milestone Accomplishments The following milestone(s) have been completed since the development of the Overall Integrated Plan (Reference 1), and are current as of June 30, 2015.
- Second Six-Month Update (complete with this submittal) 3 Milestone Schedule Status The following provides an update to Part 5 of the Overall Integrated Plan (OIP) (Ref. 1). It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.
The revised milestone target completion dates do not impact the order implementation date.
Target Comments Activity Milestone Completion Status Date Phase 1 HCVS Milestone Table Submit Phase 1 Overall Integrated Plan June 2014 Complete Page 1of7
Quad Cities Nuclear Power Station, Units 1 and 2 Second Six Month Status Report for the Implementation of HCVS Phase 1 June 30, 2015 Submit 6 Month Updates:
December Update 1 Phase 1 Complete 2014 Complete Update 2 Phase 1 June 2015 with this submittal December Update 3 [Simultaneous with Phase 2 OIP] Not Started 2015 Update 4 Phase 1 and 2 June 2016 Not Started December Update 5 Phase 1 and 2 Not Started 2016 Update 6 Phase 1 and 2 June 2017 Not Started December Update 7 Phase 1 and 2 Not Started 2017 Modifications:
Hold preliminary/conceptual design meeting June 2014 Complete July 2014 Modifications Evaluation March 2016 In Progress Unit 1 Design Engineering Complete March 2016 In Progress Unit 1 Implementation Outage (Phase 1) April 2017 Not Started Unit 1 Implementation Outage (Phase 2) April 2019 Not Started Unit 1 Phase 1 Walk Through April 2017 Not Started Demonstration/Functional Test Unit 2 Design Engineering Complete March 2017 Not Started Unit 2 Implementation Outage (Phase 1 and April 2018 Not Started 2)
Unit 2 Phase 1 and 2 Walk Through April 2018 Not Started Demonstration/Functional Test Procedure Changes December Operations Procedure Changes Developed Not Started 2016 Site Specific Maintenance Procedure December Not Started Developed 2016 Procedure Changes Active April 2017 Not Started Training:
Page 2of7
Quad Cities Nuclear Power Station, Units 1 and 2 Second Six Month Status Report for the Implementation of HCVS Phase 1 June 30, 2015 December Training Complete Not Started 2016 Completion Unit 1 Phase 1 HCVS Implementation April 2017 Not Started Unit 1 Phase 1 Completion Report [60 days June 2017 Not Started after Unit 1 Phase 1 compliance]
Unit 2 HCVS Implementation (Phase 1 and April 2018 Not Started 2}
Unit 2 Phase 1 and 2 Completion Report [60 June 2018 Not Started days after Unit 2 compliance]
Unit 1 Phase 2 HCVS Implementation April 2019 Not Started Unit 1 Phase 2 Completion Report [60 days June 2019 Not Started after Unit 1 Phase 2 compliance]
4 Changes to Compliance Method The following changes have been made to the compliance method for Phase 1 (the Phase 1 Overall Integrated Plan was provided under Reference 1):
- The Quad Cities HCVS Design has been changed to replace all previous references to a Secondary Containment Isolation Valve (SCIV) with a rupture disc rated for a pressure sufficient to withstand leakage through the downstream PCIV during a Design Basis Accident or LLRT.
- An Argon purge system has been determined to be the method of preventing hydrogen deflagration. The Argon purge system will be used to rupture the disc to allow anticipatory venting.
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Quad Cities Station expects to comply with the order implementation date; therefore, no relief/relaxation is required at this time.
6 Open Items from Overall Integrated Plan and Interim Staff Evaluation The following tables provide a summary of the open items documented in the Phase 1 Overall Integrated Plan (identified by Exelon), or the Interim Staff Evaluation (ISE), and the status of each item.
Overall Integrated Plan Phase 1 Open Item Status
- 1. Determine how Motive Power and/or HCVS Complete - Conceptual design Battery Power will be disabled during normal (completed July 2014) determined Page 3of7
Quad Cities Nuclear Power Station, Units 1 and 2 Second Six Month Status Report for the Implementation of HCVS Phase 1 June 30, 2015 operation. the HCVS primary control panel will be provided with a key lock switch to activate the system. This must be unlocked prior to performing any actuations of the DC powered components. Since the panel will be located in the MCR, unlocking and turning the switch can be performed in an ELAP with minimal operator action.
- 2. Confirm that the Remote Operating Station Superseded by ISE Open Item (ROS) will be in an area accessible following a No. 4.
Severe Accident (SA).
- 3. Confirm diameter on new common HCVS Piping. Superseded by ISE Open Item No. 5.
- 4. Confirm suppression pool heat capacity. Complete - The MAAP analysis verifies that the vent is not required for at least 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> (Reference 7). At 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />, the decay heat will be less than 1%.
- 5. Determine the approach for combustible gases. Superseded by ISE Open Item Nos. 1O and 11.
- 6. Develop a procedure for HCVS out-of-service Started.
requirements and compensatory measures.
- 7. Provide procedures for HCVS Operation. Superseded by ISE Open Item No.14.
- 8. Confirm 125 Volt DC Station Battery Life. Complete - QDC-8300-E-2100 (Reference 6) confirms that the 125 VDC Station Battery will continue to supply necessary power during the 8-hour duration prior to aligning the FLEX diesel generator. Also, refer to NRC ISE Open Item No. 1.
- 9. Supply Part 3 Drywell Boundary Condition. Not Started - Will be provided with Phase 2 OIP (December 2015).
Page 4of7
Quad Cities Nuclear Power Station, Units 1 and 2 Second Six Month Status Report for the Implementation of HCVS Phase 1 June 30, 2015 Interim Staff Evaluation Open Item Status
- 1. Make available for NRC staff audit the calculation Complete - Supplied to NRC (QDC-8300-E-2100) that confirms that Order EA- Audit team during onsite FLEX 12-49 actions to restore power are sufficient to evaluation (Jan 2015). (Reference ensure continuous operation of non-dedicated 6).
containment instrumentation.
- 2. Make available for NRC staff audit the final sizing Started - HCVS Battery design in evaluation for HCVS batteries/battery charger progress. (References 8 and 9) including incorporation into FLEX DG loading calculation.
- 3. Make available for NRC staff audit Started - HCVS Nitrogen system documentation of the HCVS nitrogen pneumatic design in progress. (References 8 system design including sizing and location. and 9)
- 4. Make available for the NRC staff audit an Started - Temperature evaluation evaluation of temperature and radiological (Calculation 2014-02948) was conditions to ensure that operating personnel can made available to NRC Audit team safely access and operate controls and support during onsite FLEX evaluation equipment. (Jan 2015). Radiological evaluation in progress.
(References 8 and 9)
- 5. Make available for NRC staff review Started - Ref er to the response to documentation that confirms the final design ISE Open Item No. 6.
diameter of the HCVS piping.
- 6. Make available for NRC staff audit analyses Started - The required 1% vent demonstrating that HCVS has the capacity to capacity at the lower of PCPL or vent the steam/energy equivalent to one percent containment design pressure will be verified using RELAP which of licensed/rated thermal power (unless a lower models the line size and routing.
value is justified) and that the suppression pool In addition, MAAP analyses will be and HCVS together are able to absorb and reject credited to verify that ( 1) venting decay heat, such that following a reactor can be delayed for at least three shutdown from full power containment pressure hours and (2) anticipatory venting is restored and then maintained below the sufficiently limits the suppression primary containment design pressure and the pool heat up to maintain RCIC primary containment pressure limit. functional. (References 8 and 9)
- 7. Make available for NRC staff audit the seismic Started - The HCVS stack seismic and tornado missile final design criteria for the design criteria is the Station's HCVS stack. design basis earthquake.
The HCVS line will exit the Reactor Building more than 30 feet above any highest ground elevation located within 'V2 mile.
The tornado missile criterion for Page 5of7
Quad Cities Nuclear Power Station, Units 1 and 2 Second Six Month Status Report for the Implementation of HCVS Phase 1 June 30, 2015 above 30 feet is under evaluation.
(References 8 and 9)
- 8. Make available for NRG staff audit the Started - Component location descriptions of local conditions (temperature, design and local condition impacts radiation and humidity) anticipated during ELAP are in progress. The HCVS and severe accident for the components (valves, primary control panel will be instrumentation, sensors, transmitters, indicators, located in the MGR. (References 8 electronics, control devices, and etc.) required for and 9}
HCVS venting including confirmation that the components are capable of performing their functions during ELAP and severe accident conditions.
- 9. Make available for NRG staff audit Not Started.
documentation that demonstrates adequate communication between the remote HCVS operation locations and HCVS decision makers during ELAP and severe accident conditions.
- 10. Provide a description of the final design of the Started - Argon purge system HCVS to address hydrogen detonation and design in progress. (References 8 deflagration. and 9) 11 . Provide a description of the strategies for Started - As described in the 01 P hydrogen control that minimizes the potential for (Ref. 1), the HCVS torus vent path hydrogen gas migration and ingress into the in each Quad Cities unit starting Reactor Building or other buildings. with, and including, the downstream PCIV will be a dedicated HCVS flow path. There are no interconnected systems downstream of the dedicated HCVS PCIV. Interconnected systems are upstream of the HCVS PCIV and are isolated by normally shut, fail shut (air-to-open, spring-to-shut) PCIVs which, if open, would shut on an ELAP. There is no shared HCVS piping between the two units.
The vent path will rely on an Argon purge system to prevent line failure due to potential hydrogen deflagration and detonation. (References 8 and 9)
- 12. Make available for NRG staff audit Not Started.
documentation of a seismic qualification Page 6of7
Quad Cities Nuclear Power Station, Units 1 and 2 Second Six Month Status Report for the Implementation of HCVS Phase 1 June 30, 2015 evaluation of HCVS components.
- 13. Make available for NRC staff audit descriptions of Started - Instrument design in all instrumentation and controls (existing and progress. (References 8 and 9) planned) necessary to implement this order including qualification methods.
- 14. Make available for NRC staff audit the Not Started.
procedures for HCVS operation.
7 Interim Staff Evaluation Impacts There are no potential impacts to the Interim Staff Evaluation identified at this time.
8 References The following references support the updates to the Phase 1 Overall Integrated Plan described in this enclosure.
- 1. Quad Cities Nuclear Power Station, Units 1 and 2, Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated June 30, 2014.
- 2. NRC Order Number EA-13-109, "Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions" dated June 6, 2013.
- 3. NEI 13-02, "Industry Guidance for Compliance with NRC Order EA-13-109, 'To Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 1, dated April 2015.
- 4. NRC Interim Staff Guidance JLD-ISG-2015-01 , "Compliance with Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 0, dated April 2015 (Accession No. ML15104A118).
- 5. NRC Endorsement of Industry "Hardened Containment Venting System (HCVS) Phase 1 Overall Integrated Plan Template (EA-13-109) Rev O," dated May 14, 2014 (Accession No. ML14128A219).
- 6. Exelon Calculation QDC-8300-E-2100, Unit 1(2) 125 VDC Battery Coping Calculation for Beyond Design Basis FLEX Event, dated September 26, 2014.
- 7. QC-MISC-013, Revision 3, MAAP Analysis to Support FLEX Initial Strategy.
- 8. EC 392256 - Unit 1 Hardened Containment Vent System (Non-Outage Portion) as Required by NRC Order EA-13-109.
- 9. EC 392257 - Unit 1 Hardened Containment Vent System (Outage Portion) as Required by NRC Order EA-13-109.
Page 7of7