MONTHYEARRS-14-306, First Six-Month Status Report Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses W/ Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Condition2014-12-17017 December 2014 First Six-Month Status Report Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses W/ Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Condition Project stage: Other ML15089A4212015-04-0101 April 2015 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-13-109,Severe Accident Capable Hardened Vents. Project stage: Other RS-15-152, Second Six-Month Status Report for Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe..2015-06-30030 June 2015 Second Six-Month Status Report for Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe.. Project stage: Other RS-17-069, Sixth Six-Month Status Report for Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe..2017-06-27027 June 2017 Sixth Six-Month Status Report for Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe.. Project stage: Other 2015-04-01
[Table View] |
|
---|
Category:Letter type:RS
MONTHYEARRS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-078, Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval2024-08-20020 August 2024 Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations RS-24-053, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed2024-06-0606 June 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-042, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-05-10010 May 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-046, 10 CFR 50.46 Annual Report2024-05-0606 May 2024 10 CFR 50.46 Annual Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-032, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-04-0505 April 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-019, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF2024-03-19019 March 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF RS-24-020, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS2024-03-15015 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS RS-24-015, Submittal of RP-01 Relief Request Associated with the Sixth Inservice Testing Interval2024-02-29029 February 2024 Submittal of RP-01 Relief Request Associated with the Sixth Inservice Testing Interval RS-24-001, Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2024-01-0303 January 2024 Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-128, Response to Request for Additional Information for the Emergency License Amendment Request – Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-15015 December 2023 Response to Request for Additional Information for the Emergency License Amendment Request – Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-104, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-113, Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 262023-10-20020 October 2023 Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 26 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-089, Sixth Ten-Year Interval Inservice Testing Program2023-09-0505 September 2023 Sixth Ten-Year Interval Inservice Testing Program RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-086, Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-08-28028 August 2023 Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-060, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2023-06-0808 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors RS-23-059, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0808 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-22-067, 10 CFR 50.46 Annual Report2023-05-0404 May 2023 10 CFR 50.46 Annual Report RS-23-068, Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell2023-04-28028 April 2023 Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell RS-23-058, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges2023-04-24024 April 2023 Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-007, Application to Adopt TSTF-564, Safety Limit MCPR2023-03-0303 March 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-032, Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location2023-02-0303 February 2023 Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location RS-23-034, Notification of Extension to the Fifth Ten-Year Interval of the Inservice Testing Program2023-02-0202 February 2023 Notification of Extension to the Fifth Ten-Year Interval of the Inservice Testing Program RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-23-033, Request for Exemption from 10 CFR 2.109(b)2023-01-27027 January 2023 Request for Exemption from 10 CFR 2.109(b) RS-23-005, Response to Request for Additional Information for Quad Cities Relief Request RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves2023-01-17017 January 2023 Response to Request for Additional Information for Quad Cities Relief Request RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves RS-22-127, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-10 Reactor Pressure Vessel Penetration N-11B Repair2022-12-14014 December 2022 Submittal of Sixth Inservice Inspection Interval Relief Request I6R-10 Reactor Pressure Vessel Penetration N-11B Repair RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-119, Withdrawal of Relief Request RV-11 Associated with the Sixth Inservice Testing Interval2022-10-31031 October 2022 Withdrawal of Relief Request RV-11 Associated with the Sixth Inservice Testing Interval RS-22-109, Response to Request for Additional Information License Amendments Related to Fuel Storage2022-10-12012 October 2022 Response to Request for Additional Information License Amendments Related to Fuel Storage RS-22-112, Submittal of RV-04 Relief Request Associated with the Sixth Inservice Testing Interval2022-10-0707 October 2022 Submittal of RV-04 Relief Request Associated with the Sixth Inservice Testing Interval RS-22-108, Response to Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage2022-10-0505 October 2022 Response to Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-102, Supplement to Request to Revise Technical Specification 3.1.4, Control Rod Scam Times2022-08-18018 August 2022 Supplement to Request to Revise Technical Specification 3.1.4, Control Rod Scam Times RS-22-095, Response to Request for Additional Information Regarding Request to Expand Applicability of GNF Thermal Mechanical Analysis Methods to Framatome Fuel2022-08-10010 August 2022 Response to Request for Additional Information Regarding Request to Expand Applicability of GNF Thermal Mechanical Analysis Methods to Framatome Fuel RS-22-096, Response to Request for Additional Information Related to Relief Request I6R-01 Associated with the Sixth Inservice Inspection Interval2022-08-10010 August 2022 Response to Request for Additional Information Related to Relief Request I6R-01 Associated with the Sixth Inservice Inspection Interval 2024-08-20
[Table view] Category:Routine Status Report (Recurring Weekly/Monthly)
[Table view] |
Text
Exelon Generation Order No. EA-13-109 RS-14-306 December 17, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265
Subject:
First Six-Month Status Report Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)
References:
- 1. NRC Order Number EA-13-109, "Issuance of Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," dated June 6, 2013
- 2. NRC Interim Staff Guidance JLD-ISG-2013-02, "Compliance with Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 0, dated November 14, 2013
- 3. NEI 13-02, "Industry Guidance for Compliance with NRC Order EA-13-109, BWR Mark I
& II Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 0, dated November 2013
- 4. Exelon Generation Company, LLC's Answer to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated June 26, 2013
- 5. Exelon Generation Company, LLC Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated June 30, 2014 (RS-14-063)
On June 6, 2013, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to Exelon Generation Company, LLC (EGC). Reference 1 was immediately effective and directs EGG to require their BWRs with Mark I and Mark II containments to take certain actions to ensure that these facilities have a hardened containment vent system (HCVS) to remove decay heat from the containment, and maintain control of containment pressure
U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-13-109 December 17, 2014 Page 2 within acceptable limits following events that result in loss of active containment heat removal capability while maintaining the capability to operate under severe accident (SA) conditions resulting from an Extended Loss of AC Power (ELAP). Specific requirements are outlined in of Reference 1.
Reference 1 required submission of an initial status report 20 days following issuance of the final interim staff guidance (Reference 2) and a Phase 1 Overall Integrated Plan pursuant to Section IV, Condition D by June 30, 2014. Reference 2 endorses industry guidance document NEI 13-02, Revision 0 (Reference 3) with clarifications and exceptions identified in Reference 2.
Reference 4 provided the EGC initial status report regarding reliable hardened containment vents capable of operation under severe accident conditions. Reference 5 provided the Quad Cities Nuclear Power Station, Units 1 and 2 Phase 1 Overall Integrated Plan.
Reference 1 requires submission of a status report at six-month intervals following submittal of the Phase 1 overall integrated plan. Reference 3 provides direction regarding the content of the status reports. The purpose of this letter is to provide the first six-month status report for Phase 1 pursuant to Section IV, Condition D.3, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The enclosed report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.
This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact David P. Helker at 610-765-5525.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 17th day of December 2014.
Respectfully submitted, Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC
Enclosure:
Quad Cities Nuclear Power Station, Units 1 and 2 First Six-Month Status Report for Phase 1 Implementation of Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions
U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-13-109 December 17, 2014 Page 3 cc: Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector Quad Cities Nuclear Power Station, Units 1 and 2 NRC Project Manager, NRR Quad Cities Nuclear Power Station, Units 1 and 2 Mr. Charles H. Norton, NRR/JLD/PPSD/JOMB, NRC Mr. John P. Boska, NRR/JLD/JOMB, NRC Illinois Emergency Management Agency - Division of Nuclear Safety
Enclosure Quad Cities Nuclear Power Station, Units 1 and 2 First Six-Month Status Report for Phase 1 Implementation of Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (4 pages)
Enclosure Quad Cities Nuclear Power Station, Units 1 and 2 First Six Month Status Report for the Implementation of Order EA-13-109, "Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions" 1 Introduction Quad Cities Nuclear Power Station, Units 1 and 2 (Quad Cities Station) developed an Overall Integrated Plan (Reference 1 in Section 8), documenting the installation of a Hardened Containment Vent System (HCVS) that provides a reliable hardened venting capability for pre-core damage and under severe accident conditions, including those involving a breach of the reactor vessel by molten core debris, in response to Reference 2. This attachment provides an update of milestone accomplishments since submittal of the Phase 1 Overall Integrated Plan, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
2 Milestone Accomplishments The following milestone(s) have been completed since the development of the Overall Integrated Plan (Reference 1), and are current as of December 15, 2014.
- Held preliminary/conceptual design meeting
- First Six-Month Update (complete with this submittal) 3 Milestone Schedule Status The following provides an update to Part 5 of the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.
The revised milestone target completion dates do not impact the order implementation date.
Target Comments Activity Milestone Completion Status Date Phase 1 HCVS Milestone Table Submit Phase 1 Overall Integrated Plan June 2014 Complete Page 1 of 4
Quad Cities Nuclear Power Station, Units 1 and 2 First Six Month Status Report for the Implementation of HCVS Phase 1 December 17, 2014 Submit 6 Month Updates:
Complete Update 1 Phase 1 December 2014 with this submittal Update 2 Phase 1 June 2015 Not Started Update 3 [Simultaneous with Phase 2 OIP] December 2015 Not Started Update 4 Phases 1 and 2 June 2016 Not Started Update 5 Phases 1 and 2 December 2016 Not Started Update 6 Phases 1 and 2 June 2017 Not Started Update 7 Phases 1 and 2 December 2017 Not Started Modifications:
Hold preliminary/conceptual design meeting June 2014 Complete July 2014 Modifications Evaluation March 2016 Not Started Unit 1 Design Engineering Complete March 2016 Not Started Unit 1 Implementation Outage (Phase 1) April 2017 Not Started Unit 1 Implementation Outage (Phase 2) April 2019 Not Started Unit 1 Phase 1 Walk Through April 2017 Not Started Demonstration/Functional Test Unit 2 Design Engineering Complete March 2017 Not Started Unit 2 Implementation Outage (Phases 1 and 2) April 2018 Not Started Unit 2 Phases 1 and 2 Walk Through April 2018 Not Started Demonstration/Functional Test Procedure Changes Operations Procedure Changes Developed December 2016 Not Started Site Specific Maintenance Procedure Developed December 2016 Not Started Procedure Changes Active April 2017 Not Started Training:
Training Complete December 2016 Not Started Completion Unit 1 Phase 1 HCVS Implementation April 2017 Not Started Unit 1 Phase 1 Completion Report [60 days after June 2017 Not Started Unit 1 Phase 1 compliance]
Unit 2 HCVS Implementation (Phases 1 and 2) April 2018 Not Started Page 2 of 4
Quad Cities Nuclear Power Station, Units 1 and 2 First Six Month Status Report for the Implementation of HCVS Phase 1 December 17, 2014 Unit 2 Phases 1 and 2 Completion Report [60 June 2018 Not Started days after Unit 2 compliance]
Unit 1 Phase 2 HCVS Implementation April 2019 Not Started Unit 1 Phase 2 Completion Report [60 days after June 2019 Not Started Unit 1 Phase 2 compliance]
4 Changes to Compliance Method There are no changes to the compliance method as documented in the Phase 1 Overall Integrated Plan (Reference 1).
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Quad Cities Station expects to comply with the order implementation date; therefore, no relief/relaxation is required at this time.
6 Open Items from Overall Integrated Plan and Interim Staff Evaluation The following tables provide a summary of the open items documented in the Phase 1 Overall Integrated Plan, or the Interim Staff Evaluation (ISE), and the status of each item.
Overall Integrated Plan Phase 1 Open Item Status
- 1. Determine how Motive Power and/or HCVS Battery Complete Conceptual design Power will be disabled during normal operation (completed July 2014) determined the HCVS control panel will be provided with a key lock switch to activate the system. This must be unlocked prior to performing any actuations of the DC powered components.
- 2. Confirm that the Remote Operating Station (ROS) Not Started Design Dependent will be in an area accessible following a Severe Accident (SA)
- 3. Confirm diameter on new common HCVS Piping Not Started Design Dependent
- 4. Confirm suppression pool heat capacity Complete Vent not required for at least 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> (Reference 7)
- 5. Determine the approach for combustible gases Not Started Design Dependent
- 6. Develop a procedure for HCVS out-of-service Started requirements and compensatory measures.
- 7. Provide procedures for HCVS Operation. Not Started Design Dependent Page 3 of 4
Quad Cities Nuclear Power Station, Units 1 and 2 First Six Month Status Report for the Implementation of HCVS Phase 1 December 17, 2014
- 8. Confirm 125 VDC DC Station Battery Life Complete Battery life meets minimum FLEX strategy intent of 8- hours (Reference 6)
- 9. Supply Part 3 Drywell Boundary Condition Not Started Will be provided with Phase 2 01P (December 2015)
Interim Staff Evaluation Open Item Status No items at the present time.
7 Interim Staff Evaluation Impacts There are no potential impacts to the Interim Staff Evaluation identified at this time.
8 References The following references support the updates to the Phase 1 Overall Integrated Plan described in this enclosure.
- 1. Quad Cities Nuclear Power Station, Units 1 and 2, Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)," dated June 30, 2014.
- 2. NRC Order Number EA-13-109, "Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions" dated June 6, 2013.
- 3. NE! 13-02, "Industry Guidance for Compliance with NRC Order EA-13-109, 'To Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 0, dated November 2013.
- 4. NRC Interim Staff Guidance JLD-ISG-2013-02, "Compliance with Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 0, dated November 14, 2013 (Accession No. ML13304B836).
- 5. NRC Endorsement of industry "Hardened Containment Venting System (HCVS) Phase 1 Overall Integrated Plan Template (EA-13-109) Rev 0" (Accession No. ML14128A219).
- 6. Exelon Calculation QDC-8300-E-2100, Unit 1(2) 125 VDC Battery Coping Calculation for Beyond Design Basis FLEX Event, 09/26/2014.
- 7. QC-MISC-013, Revision 2, MAAP Analysis to Support FLEX Initial Strategy, 09/16/2014.