05000482/LER-2015-002

From kanterella
(Redirected from ML15173A094)
Jump to navigation Jump to search
LER-2015-002, Two Control Room Air Conditioning Trains Inoperable Due to Failure to Meet Surveillance Requirement
Docket Number
Event date: 4-16-2015
Report date: 08-26-2015
Reporting criterion: 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications

10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor
4822015002R01 - NRC Website

PLANT CONDITIONS PRIOR TO THE EVENT

Mode 5 The plant was in Refueling Outage 20 when this event was identified. At the time of identification, both Control Room Air Conditioning System (CRACS) trains had successfully met the unit air flow capacity of > 21,012 cfm.

DESCRIPTION

From January 3, 2013, through August 13, 2013, the Conditions and Required Actions of limiting condition for operation (LCO) LCO 3.7.11, LCO 3.0.3 and LCO 3.0.4 were not met.

On April 16, 2015, an apparent cause evaluation on Condition Report (CR) 92274, "Application of TS SR 3.0.1," identified the potential that the acceptance criteria in procedures STS PE-010A/B, "Control Room NC System Flow Rate Verification [NB] Train," may not have been met when the acceptance criteria was revised on January 3, 2013 from > 18,360 cfm and In December 1999, Wolf Creek Nuclear Operating Corporation (WCNOC) implemented license amendment number 123 that converted the current Technical Specifications to the improved Technical Specifications. The amendment included new specification 3.7.11, "Control Room Air Conditioning System (CRACS)," and new surveillance requirement (SR) SR 3.7.11.1. SR 3.7.11.1 verifies that the heat removal capability of the CRACS air conditioning units (SGKO4A and SGKO4B) [El IS: VI, ACU] is adequate to remove the heat load assumed in the control room during design basis accidents. This SR consists of verifying the heat removal capability of the condenser heat exchanger, ensuring the proper operation of major components in the refrigeration cycle, verification of unit air flow capacity, and water flow measurement. Procedures STS PE-010A/B, "Control Room A/C System Flow Rate Verification [NB] Train," were initially issued on December 18, 1999 for verification of unit air flow capacity. An acceptance criteria of > 20,400 cfm was specified.

Procedures STS PE-010A/B were revised on March 11, 2002 and changed the acceptance criteria from > 20,400 cfm to > 18,360 cfm and Request (now referred to as Condition Report) 2001-3149 which determined that a +/- 10% flow rate specified in ASME/ANSI N510-1980, "Testing of Nuclear Air-Cleaning Systems," could be utilized in determining the acceptance criteria.

On November 20, 2012, Condition Report (CR) 60099 identified that procedures STS PE-010A/B should be revised to remove the +/- 10% flow rate based on concerns identified in CR 58535 on the use of the +/- 10% flow rate in procedures STS PE-016A/B, "[NB] Train Class 1E Electrical System NC Flow Rate Verification." The Operability Screening Review for CR 60099 indicated that SGKO4A and SGKO4B were operable based on Operability Evaluation OE GK-12-017, which addressed a separate issue on the same equipment, specifying a minimum air flow rate of 19,449 cfm (that excluded instrument uncertainty).

Procedures STS PE-010A/B were revised on January 3, 2013 and specified a new acceptance criteria of > 21,012 cfm.

The prior performances of STS PE-010A/B did not meet the new acceptance criteria. Additionally, procedure STS PE-010B was not performed until July 8, 2013 and procedure STS PE-010A was not performed until August 13, 2013. These performances met the new acceptance criteria. An adjustable sheave was installed in the 'B' CRACS train in July 2013 and in the 'A' CRACS train in March 2015.

Technical Specification (TS) SR 3.0.1 specifies that SRs shall be met during the Modes of Applicability and that failure to meet a Surveillance, whether such failure is experienced during the performance of the Surveillance or between performance shall be a failure to meet the LCO. On January 3, 2013 with the revision of STS PE-010A/B, LCO 3.7.11 should have been declared not met and the applicable Conditions/Required Actions entered. Condition E of LCO 3.7.11 specifies to enter LCO 3.0.3 with two CRACS trains inoperable in Modes 1, 2, 3, 4, 5, and 6 and during movement of irradiated fuel assemblies.

The plant was in Mode 1 on January 3, 2013. Refueling Outage 19 was conducted from February 4, 2013 through April 16, 2013. A forced outage occurred from May 6, 2013 through May 13, 2013. As such, the Conditions and Required Actions of LCO 3.7.11, LCO 3.0.3 and LCO 3.0.4 were not met.

REPORTABILITY

This event is reportable under 10 CFR 50.73(a)(2)(i)(B) as an operation or condition prohibited by TSs when it was determined that the Conditions and Required Actions of LCO 3.7.11, LCO 3.0.3 and LCO 3.0.4 were not met from January 3, 2013 through August 13, 2013.

Additionally, this event is reportable under 10 CFR 50.73(a)(2)(v)(A) an event or condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to: (A) Shut down the reactor and maintain it in a safe shutdown condition. Updated Safety Analysis Report (USAR) Section 9.4.1.1.1 specifies that the control room air conditioning system is required to function following a design basis accident and to achieve and maintain the plant in a post accident safe shutdown condition. From January 3, 2013 through July 8, 2013, two CRACS trains where inoperable when the acceptance criteria in procedures STS PE-010A/B were not met resulting in a failure to meet SR 3.7.11.1. NUREG-1022, Rev. 3, "Event Report Guidelines 10 CFR 50.72 and 50.73," indicates that for systems, subsystems and components within the scope of this criterion, a report is required when 1) there is a determination that the SSC is inoperable in a required mode or other specified condition in the TS Applicability, 2) the inoperability is due to one or more personnel errors, including procedure violations; equipment failures; inadequate maintenance; or design, analysis, fabrication, equipment qualification, construction, or procedural deficiencies, and 3) no redundant equipment in the same system was operable.

CAUSE

The apparent cause of this event is the information in Operability Evaluation OE GK-12-017, which addressed a separate issue on the same equipment, enabled control room operators and engineering personnel to rationalize the assumption that the change to the acceptance criteria was bounded and did not impact the ability to meet SR 3.7.11.1.

CORRECTIVE ACTIONS

Corrective maintenance has been performed on the CRACS trains to increase the airflow to meet the procedure acceptance criteria and subsequent performance of procedure STS PE-010A/B was successful.

Licensed operators were provided training during Requalification Cycle 15-3 that addressed the initiating event for this LER. Training will be provided to engineering personnel in accordance with CR 95378.

Procedure AP 15C-004, "Preparation, Review and Approval of Procedures, Instructions and Forms," is being revised to require Operations Surveillance Coordinator review of TS surveillance requirement procedures that result in a change in acceptance criteria.

SAFETY SIGNIFICANCE

The design basis of the CRACS is to maintain control room temperature for 30 days of continuous occupancy. The CRACS components are arranged in redundant, safety related trains. During normal or emergency operations, the CRACS maintains the temperature could result in equipment operating temperatures exceeding limits in the event of the accident. During the duration of this event, one CRACS train remained in operation with an air flow rate slightly less than the design specified flow rate. As such, the safety significance of this event is low.

OPERATING EXPERIENCE/PREVIOUS EVENTS

Condition Report 92274 identified an event where the 'A' CRACS train failed to meet the acceptance criteria for procedure STS PE-010A. The 'A' CRACS train was not declared inoperable in accordance with SR 3.0.1 when information obtained from an operability evaluation was used to justify that the train was operable but degraded.