STATE OF NEW YORK OFFICE OF THE ATTORNEY GENERAL ERIC T. SCHNEIDERMAN DIVISION OF SOCIAL JUSTICE ATTORNEY GENERAL ENVIRONMENTAL PROTECTION BUREAU June 9, 2015 Lawrence G. McDade, Chair Richard E. Wardwell, Administrative Judge Michael F. Kennedy, Administrative Judge Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mailstop 3 F23 Two White Flint North 11545 Rockville Pike Rockville, MD 20852-2738 Re: Indian Point Nuclear Generating Station, Unit 2 and Unit 3 Docket Nos. 50-247-LR/50-286-LR; ASLBP No. 07-858-03-LR-BD01
Dear Administrative Judges:
Intervenor State of New York will serve today Exhibits NYS000531 through NYS000562 (as indicated on the attached Table of Exhibits) relative to Joint Contention NYS-38/RK-TC-5. Certain exhibits, indicated as non-public or proprietary in the attached exhibit list, will be served via the EIEs non-public submission portal. Certificates of service will follow.
If there is any difficulty in opening the submissions or other questions about the filing, please contact me.
Respectfully submitted, Signed (electronically) by Brian Lusignan Assistant Attorney General (518) 776-2399 Brian.Lusignan@ag.ny.gov Copies to: EIE service list THE CAPITOL, ALBANY, N.Y. 12224-0341 PHONE (518) 776-2400 FAX (518) 350-9363 WWW.AG.NY.GOV
Submitted: June 9, 2015 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Exhibit Name Exhibit
- Addressed by Submission /
Exhibit Revision Date NYS000531 NYS-38/RK-TC-5 Revised Statement of Position of the State of New 6/9/2015 York in support of Contention NYS-38/RK-TC-5 (Public, Redacted) (June 9, 2015)
NYS000531 NYS-38/RK-TC-5 Revised Statement of Position of the State of New 6/9/2015 York in support of Contention NYS-38/RK-TC-5 (Non-Public, Non-Redacted) (June 9, 2015)
NYS000532 NYS-38/RK-TC-5 Revised Pre-filed Written Testimony of David J. 6/9/2015 Duquette in support of Contention NYS-38/RK-TC-5 (Public, Redacted) (June 8, 2015)
NYS000532 NYS-38/RK-TC-5 Revised Pre-filed Written Testimony of David J. 6/9/2015 Duquette in support of Contention NYS-38/RK-TC-5 (Non-Public, Non-Redacted) (June 8, 2015)
NYS000533 NYS-38/RK-TC-5 Report, Indian Point 3 Steam Generator Program, Rev. 6/9/2015 8, IP3-RPT-SG-01796 (July 26, 2007) (IPEC00243554)
NYS000534 NYS-38/RK-TC-5 Entergy, Engineering Report, Review of the Steam 6/9/2015 Generator Integrity Management Program for License Renewal Implementation, IP-RPT-11-LRD36, Rev. 0 (June 25, 2012) (IPEC00269432) 1
Submitted: June 9, 2015 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Exhibit Name Exhibit
- Addressed by Submission /
Exhibit Revision Date NYS000535 NYS-38/RK-TC-5 Commitment Closure Verification Form, Commitment 41, 6/9/2015 IP2 and IP3 Steam Generator Inspections (April 24, 2013) (IPEC00277180)
NYS000536 NYS-38/RK-TC-5 Indian Point Nuclear Generating Units 2 and 3 - NRC 6/9/2015 Integrated Inspection Report 05000247/2013002 and 05000286/2013002 (May 3, 2013) (ML13123A280)
NYS000537 NYS-38/RK-TC-5 Dacimo, Fred, Entergy, letter to Document Control 6/9/2015 Desk, USNRC, Technical Specification 5.6.8. - IP3 Steam Generator Tube Inspection Report - Spring 2013 Refueling Outage, NL-13-032 (August 15, 2013)
NYS000538 NYS-38/RK-TC-5 NRC Information Notice 2013-20: Steam Generator 6/9/2015 Channel Head and Tubesheet Degradation (October 3, 2013) (ML13204A143)
NYS000539 NYS-38/RK-TC-5 Ventosa, John, Entergy, letter to Document Control 6/9/2015 Desk, USNRC, Proposed License Amendment for Alternate Repair Criteria for Steam Generator Tube Inspection and Repair, NL-14-001 (January 16, 2014)
(ML14027A514) 2
Submitted: June 9, 2015 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Exhibit Name Exhibit
- Addressed by Submission /
Exhibit Revision Date NYS000540 NYS-38/RK-TC-5 Indian Point Nuclear Generating Unit No. 3 - Staff 6/9/2015 Summary of the Steam Generator Tube Inservice Inspections for the Spring 2013 Refueling Outage (TAC No. MF2614) (January 30, 2014) (ML14015A417)
NYS000541 NYS-38/RK-TC-5 Indian Point Power Station - NRC Integrated 6/9/2015 Inspection Report 05000247/2014002 and 05000286/2014002 (May 9, 2014) (ML14132A170)
NYS000542 NYS-38/RK-TC-5 Indian Point Nuclear Generating Unit No. 2 - Issuance 6/9/2015 of Amendment Re: H* Alternate Repair Criteria for Steam Generator Tube Inspection and Repair (TAC No.
MF3369) (September 5, 2014) (ML14198A161) with Correction Letter (September 30, 2014) (ML14252A679)
NYS000543 NYS-38/RK-TC-5 Ventosa, John, Entergy, letter to Document Control 6/9/2015 Desk, USNRC, Steam Generator Examination Program Results 2014 Refueling Outage (2R21), Indian Point Unit No. 2, NL-14-113 (September 8, 2014)
(ML14262A059) 3
Submitted: June 9, 2015 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Exhibit Name Exhibit
- Addressed by Submission /
Exhibit Revision Date NYS000544 A NYS-38/RK-TC-5 EPRI, Technical Report (3002002850), Steam Generator 6/9/2015
- D Management Program: Investigation of Crack Initiation and Propagation in the Steam Generator Channel Head Assembly, Final Report (October 2014)
(IPECPROP00080904) [PROPRIETARY]
NYS000545 NYS-38/RK-TC-5 Coyle, Lawrence, Entergy, letter to Document Control 6/9/2015 Desk, USNRC, Response to Request for Additional Information (RAI) for the Steam Generator Examination Program Results 2014 Refueling Outage (2R21), Indian Point Unit No. 2, NL-15-001 (January 15, 2014)
NYS000546 NYS-38/RK-TC-5 Slides, NRC/EPRI Steam Generator Task Force Meeting 6/9/2015 (February 12, 2015) (ML15043A610)
NYS000547 NYS-38/RK-TC-5 Westinghouse WCAP-17828 Indian Point Unit 2 H* 6/9/2015 Alternate Repair Criteria (January 2014)
NYS000548 NYS-38/RK-TC-5 Indian Point Nuclear Generating Unit 3 Event 51046 6/9/2015 Offsite Notification Due To Shutdown For An Unisolable Steam Leak (May 7, 2015) 4
Submitted: June 9, 2015 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Exhibit Name Exhibit
- Addressed by Submission /
Exhibit Revision Date NYS000549 NYS-38/RK-TC-5 Letter, C579MPENT-12-002, Westinghouse Nuclear Safety 6/9/2015 Advisory Letter NSAL-12-1, Steam Generator Channel Head Degradation (January 6, 2012) (IPECPROP00078537)
[PROPRIETARY]
NYS000550 NYS-38/RK-TC-5 Slides, NRC/EPRI Steam Generator Task Force Meeting 6/9/2015 (February 6, 2013) (ML13037A891)
NYS000551 NYS-38/RK-TC-5 NRC Information Notice 2013-11: Crack-Like Indication 6/9/2015 at Dents/Dings and in the Freespan Region of Thermally Treated Alloy 600 Steam Generator Tubes (July 3, 2013) (ML13127A236)
NYS000552 NYS-38/RK-TC-5 Review of Lessons Learned from the San Onofre Steam 6/9/2015 Generator Tube Degradation Event (March 6, 2015)
NYS000553 NYS-38/RK-TC-5 Commitment Closure Verification Form, Commitment 42, 6/9/2015 IP2 and IP3 Develop Plan for Each Unit to Address the Potential for Cracking of the Primary to Secondary Pressure Boundary Due to PWSCC of Tube-to-tubesheet welds (October 15, 2014) (IPEC00277167) 5
Submitted: June 9, 2015 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Exhibit Name Exhibit
- Addressed by Submission /
Exhibit Revision Date NYS000554 NYS-38/RK-TC-5 Indian Point Nuclear Generating Unit 2 Steam 6/9/2015 Generator Program Report Revision 2 (July 25, 2007) (IPEC00243510)
NYS000555 NYS-38/RK-TC-5 Indian Point Nuclear Generating Units 2 and 3 Steam 6/9/2015 Generator Program Update (November 15, 2011)
(IPEC00243625)
NYS000556 NYS-38/RK-TC-5 Indian Point Nuclear Generating Unit Nos. 2 and 3- 6/9/2015 Issuance Of Amendments Regarding Iplementation Of Technical Specification Task Force 510, "Revision To Steam Generator Program Inspection Frequencies And Tube Sample Selection" (TAC NOS. MF3752 AND MF3753)
(May 26, 2015) (ML15110A009)
NYS000557 NYS-38/RK-TC-5 NRC Weekly Information Report (May 15, 2015) 6/9/2015 (ML15138A267)
NYS000558 NYS-38/RK-TC-5 Indian Point Nuclear Generating Unit Nos. 2 and 3- 6/9/2015 License Renewal Application Pages 2. 3-36 -39 (EXCERPT)
NYS000559 NYS-38/RK-TC-5 Indian Point Nuclear Generating Unit Nos. 2 and 3- 6/9/2015 License Renewal Application Pages 4. 3-14 -15 (EXCERPT) 6
Submitted: June 9, 2015 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Exhibit Name Exhibit
- Addressed by Submission /
Exhibit Revision Date NYS000560 NYS-38/RK-TC-5 Indian Point Steam Generator Materials Summary Table 6/9/2015 NYS000561 NYS-38/RK-TC-5 Indian Point Nuclear Generating Unit 3 Event 51060 6/9/2015 Unusual Event Declared Due To Main Transformer Fire (May 9, 2015)
NYS000562 NYS-38/RK-TC-5 Revised Pre-filed Testimony of Dr. Richard T. Lahey, 6/9/2015 Jr. in Support of Joint Contention NYS-38/Rk-TC-5 (June 9, 2015) (Non-public, Non-redacted)
NYS000562 NYS-38/RK-TC-5 Revised Pre-filed Testimony of Dr. Richard T. Lahey, 6/9/2015 Jr. in Support of Joint Contention NYS-38/Rk-TC-5 (June 9, 2015) (Public, Redacted) 7