UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of )

)

FIRSTENERGY NUCLEAR OPERATING CO. ) Docket No. 50-346-LR

)

(Davis-Besse Nuclear Power Station, Unit 1) )

NRC STAFF ANSWER TO BEYOND NUCLEARS HEARING REQUEST AND PETITION TO INTERVENE AND MOTION TO REOPEN THE RECORD IN THE LICENSE RENEWAL PROCEEDING FOR DAVIS-BESSE NUCLEAR POWER PLANT Brian G. Harris Jeremy Wachutka Counsel for NRC Staff May 1, 2015

-i-TABLE OF CONTENTS PAGE INTRODUCTION .......................................................................................................................... 1 BACKGROUND ............................................................................................................................ 3 DISCUSSION ................................................................................................................................ 9 I. Legal Standards ................................................................................................................ 9 A. Legal Standards for Admission of Contentions ............................................................ 9 B. Legal Standards for Reopening of the Record .......................................................... 12 II. The Petition Should Be Denied for Failing to Timely Proffer an Admissible Contention . 13 A. The Proposed Contention Challenges a Rulemaking that Is Beyond the Scope of this Proceeding ...................................................................................................................... 14 B. The Proposed Contention Fails to Raise a Genuine Material Issue .......................... 16 C. The Proposed Contention Is Untimely ....................................................................... 17 III. The Motion to Reopen Should Be Denied for Failing to Meet the Reopening Standards18 A. Beyond Nuclears Motion Is Untimely and Does Not Raise an Exceptionally Grave Issue................................................................................................................................ 19 B. Beyond Nuclears Motion Does Not Address a Significant Environmental Issue....... 19 C. Beyond Nuclears Motion Does Not Show that a Materially Different Result Would Be Likely .............................................................................................................................. 21 CONCLUSION ............................................................................................................................ 22

- ii -

TABLE OF AUTHORITIES Page ADMINISTRATIVE DECISIONS Commission:

AmerGen Energy Co., LLC (Oyster Creek Nuclear Generating Station),

CLI-09-7, 69 NRC 235 (2009) ............................................................................................. 12, 13 Calvert Cliffs 3 Nuclear Project, LLC & UniStar Nuclear Operating Services, LLC (Calvert Cliffs Nuclear Power Plant, Unit 3), CLI-12-16, 76 NRC 63 (2012) ............................... 6 Calvert Cliffs 3 Nuclear Project, LLC, & UniStar Nuclear Operating Services, LLC (Calvert Cliffs Nuclear Power Plant, Unit 3), CLI-14-08, 80 NRC 71 (2014) ......................... 6, 15 Dominion Nuclear Connecticut, Inc. (Millstone Nuclear Power Station, Units 2 and 3),

CLI-01-24, 54 NRC 349 (2001), petition for reconsidn denied, CLI-02-01, 55 NRC 1 (2002) ... 9 Dominion Nuclear Connecticut, Inc. (Millstone Nuclear Power Station, Unit 3),

CLI-09-5, 69 NRC 115 (2009) ................................................................................................... 12 DTE Elec. Co. (Fermi Nuclear Power Plant, Unit 3),

CLI-15-10, 81 NRC __ (Apr. 23, 2015) (slip op.) ...................................................................... 17 DTE Electric Co. (Fermi Nuclear Power Plant, Unit 3),

CLI-15-12, 81 NRC __ (Apr. 23, 2015) (slip op.) .............................................................. passim DTE Elec. Co. (Fermi Nuclear Power Plant, Unit 3),

CLI-15-4, 81 NRC __ (Feb. 26, 2015) (slip op.) .......................................................................... 8 Entergy Nuclear Vermont Yankee, LLC & Entergy Nuclear Operations, Inc.

(Vermont Yankee Nuclear Power Station), CLI-07-03, 65 NRC 13 (2007) ............................... 15 Entergy Nuclear Generation Co. & Entergy Nuclear Operations, Inc.

(Pilgrim Nuclear Power Station), CLI-12-10, 75 NRC 479 (2012) ............................................. 21 Entergy Nuclear Generation Co. & Entergy Nuclear Operations, Inc.

(Pilgrim Nuclear Power Station), CLI-12-15, 75 NRC 704 (2012) ............................................. 16 Entergy Nuclear Generation Co. & Entergy Nuclear Operations, Inc.

(Pilgrim Nuclear Power Station), CLI-12-21, 76 NRC 491 (2012) ............................................. 19 Exelon Generation Co., LLC (Limerick Generating Station, Units 1 and 2),

CLI-12-19, 76 NRC 377 (2012), remanding, LBP-13-1, 77 NRC 57 (2013),

affg on other grounds, CLI-13-7, 78 NRC 199 (2013) ........................................................ 15, 16 FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1), CLI-12-08, 75

- iii -

NRC 393, 409 (2012) .................................................................................................................. 4 Florida Power & Light Co. (Turkey Point Nuclear Generating Plant, Units 3 and 4),

CLI-01-17, 54 NRC 3 (2001) ..................................................................................................... 15 Northern States Power Co. (Prairie Island Nuclear Generating Plant, Units 1 and 2),

CLI-10-27, 72 NRC 481 (2010) ................................................................................................. 12 Private Fuel Storage, L.L.C. (Independent Spent Fuel Storage Installation),

CLI-05-12, 61 NRC 345 (2005) ................................................................................................. 13 Private Fuel Storage, L.L.C. (Independent Spent Fuel Storage Installation),

CLI-06-03, 63 NRC 19 (2006) ................................................................................................... 20 Private Fuel Storage, L.L.C. (Independent Spent Fuel Storage Installation),

CLI-99-10, 49 NRC 318 (1999) ..............................................................................................9-10 Southern Nuclear Operating Co. (Vogtle Electric Generating Plant, Units 3 and 4),

CLI-11-8, 74 NRC 214 (2011) ............................................................................................. 12, 20 Union Elec. Co. (Callaway Nuclear Power Plant, Unit 1),

CLI-15-11, 81 NRC __ (Apr. 23, 2015) (slip op.) .............................................................. passim Atomic Safety and Licensing Appeal Board:

Philadelphia Elec. Co. (Peach Bottom Atomic Power Station, Units 2 and 3),

ALAB-216, 8 AEC 13 (1974) ............................................................................................... 10, 14 Atomic Safety and Licensing Board:

Arizona Pub. Serv. Co. (Palo Verde Nuclear Station, Units No. 1, 2, and 3),

LBP-91-19, 33 NRC 397 (1991), appeal granted in part, CLI-91-12, 34 NRC 149 (1991).. 10, 14 Entergy Nuclear Generation Co. & Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), LBP-06-23, 64 NRC 257 (2006) ................................................................................. 11 Entergy Nuclear Vermont Yankee, LLC & Entergy Nuclear Operations, Inc.

(Vermont Yankee Nuclear Power Station), LBP-10-19, 72 NRC 529 (2010) ............................ 21 Exelon Generation Co., LLC (Limerick Generating Station, Units 1 and 2),

LBP-12-8, 75 NRC 539 (2012), revd in part, CLI-12-19, 76 NRC 377 (2012) .............. 11, 16, 17 FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1),

LBP-11-13, 73 NRC 534, 565, 577 (2011) .................................................................................. 4 FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1),

LBP-12-26, 76 NRC 559, 561 (2012) .......................................................................................... 4

- iv -

FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1),

LBP-12-27, 76 NRC 583, 587 (2012) .......................................................................................... 5 FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1),

LBP-15-1, 81 NRC __, __ (Jan. 15, 2015) (slip op. at 2) ............................................................ 5 FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1),

LBP-15-9, 81 NRC __, __ (Mar. 10, 2015) (slip op. at 2-3) ........................................................ 8 Nextera Energy Seabrook, LLC (Seabrook Station, Unit 1),

LBP-11-28, 74 NRC 604 (2011) ................................................................................................ 11 REGULATIONS 10 C.F.R. § 2.309(a) ..................................................................................................................... 9 10 C.F.R. § 2.309(b) ..................................................................................................................... 9 10 C.F.R. § 2.309(c) ................................................................................................................... 11 10 C.F.R. § 2.309(c)(1) ............................................................................................................... 17 10 C.F.R. § 2.309(f)(1) .................................................................................................................. 9 10 C.F.R. § 2.309(f)(1)(iii) ........................................................................................................... 14 10 C.F.R. § 2.309(f)(1)(vi) ........................................................................................................... 10 10 C.F.R. § 2.309(i) ...................................................................................................................... 1 10 C.F.R. § 2.326(a) ................................................................................................................... 12 10 C.F.R. § 2.326(b) ................................................................................................................... 12 10 C.F.R. § 2.335(a) ................................................................................................................... 14 10 C.F.R. § 2.335(b) ............................................................................................................. 10, 15 10 C.F.R. § 2.335(c) ................................................................................................................... 10 10 C.F.R. § 2.335(d) ................................................................................................................... 10 10 C.F.R. § 2.335(e) ................................................................................................................... 10 10 C.F.R. § 51.23(b) ..............................................................................................................16-17 10 C.F.R. § 51.92(a) ................................................................................................................... 20 MISCELLANEOUS SECY-14-0072, Final Rule: Continued Storage of Spent Nuclear Fuel (RIN 3150-AJ20)

(July 21, 2014) ............................................................................................................................ 6 SRM-SECY-14-0072, Final Rule: Continued Storage of Spent Nuclear Fuel (RIN 3150-AJ20)

(Aug. 26, 2014) .......................................................................................................................... 6 Criteria for Reopening Records in Formal Licensing Proceedings, 51 Fed. Reg. 19,535 (May 30, 1986) ........................................................................................ 19

-v-Notice of Acceptance for Docketing of the Application, Notice of Opportunity for Hearing for Facility Operating License No. NPF-003 for an Additional 20-Year Period; FirstEnergy Nuclear Operating Company, Davis-Besse Nuclear Power Station, Unit 1, 75 Fed. Reg. 65,528 (Oct.

25, 2010) ............................................................................................................................... 3, 17 License Renewal Application for Davis-Besse Nuclear Power Station, Unit 1, 79 Fed. Reg.

13,079 (Mar. 7, 2014) ................................................................................................................. 6 Continued Storage of Spent Nuclear Fuel, 79 Fed. Reg. 56,238 (Sept. 19, 2014) ................. 7, 18 Order (Initial Scheduling Order), at 12 (Jun. 15, 2011) (unpublished) (ADAMS Accession No.

ML111662021) (ISO) .................................................................................................................. 3 Memorandum and Order (Denying Intervenors Motion for Admission of Contention No. 6 on Shield Building Concrete Void, Cracking and Broken Rebar Problems) (Jul. 25, 2014)

(unpublished) (ADAMS Accession No. ML14206A719) .............................................................. 5 Order (Denying Motion to File a New Contention Concerning Temporary Storage of Nuclear Waste), at 1 (Oct. 8, 2014) (unpublished) (ADAMS Accession No. ML14281A448) .................. 7 NUREG-1437, Supplement 52, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Davis-Besse Nuclear Power Station, Draft Report for Comment (Feb. 2014) (ADAMS Accession No. ML14050A290) ................................................................. 6

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of )

)

FIRSTENERGY NUCLEAR OPERATING CO. ) Docket No. 50-346-LR

)

(Davis-Besse Nuclear Power Station, Unit 1) )

NRC STAFF ANSWER TO BEYOND NUCLEARS HEARING REQUEST AND PETITION TO INTERVENE AND MOTION TO REOPEN THE RECORD IN THE LICENSE RENEWAL PROCEEDING FOR DAVIS-BESSE NUCLEAR POWER PLANT INTRODUCTION In accordance with 10 C.F.R. §§ 2.309(i) and 2.323(c), the U.S. Nuclear Regulatory Commission (NRC) staff (Staff) respectfully submits its combined answer to the Petition to Intervene1 and Motion to Reopen the Record2 filed by Beyond Nuclear on April 22, 2015 in the Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse) license renewal (LR) proceeding.

Beyond Nuclear asserts that the Davis-Besse draft supplemental environmental impact statement is inadequate because its evaluation of the environmental impacts of spent fuel storage and disposal relies on the NRCs Continued Storage Rule and Continued Storage generic environmental impact statement (GEIS).3 Beyond Nuclears Petition and Motion to Reopen are substantively similar to petitions and motions to reopen filed previously in the Callaway Nuclear Power Plant, Unit 1 (Callaway) license renewal proceeding and the Fermi Nuclear Power Plant, Unit 3 (Fermi 3) combined 1

Beyond Nuclears Hearing Request and Petition to Intervene in License Renewal Proceeding for Davis-Besse Nuclear Power Plant (Apr. 22, 2015) (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15112B201) (Petition).

2 Beyond Nuclears Motion to Reopen the Record of License Renewal Proceeding For Davis-Besse Nuclear Power Plant (Apr. 22, 2015) (ADAMS Accession No. ML15112B199) (Motion to Reopen).

3 Id. at 1.

license proceeding, which also argued that the NRCs environmental documents in those proceedings were inadequate due to their reliance on the NRCs Continued Storage Rule and Continued Storage GEIS.4 In its rulings on those filings, CLI-15-11 and CLI-15-12, the Commission denied the petitions to intervene because they impermissibly challenged an agency regulation without a waiver of that regulation and were therefore outside the scope of their individual licensing proceedings and because, by challenging a regulation instead of the associated application, they did not provide sufficient information to demonstrate a genuine dispute with the applicant on a material issue.5 The Commission also held that, because the petitions to intervene had not included an admissible contention, the accompanying motions to reopen necessarily did not satisfy the Commissions reopening standards because they did not raise a significant environmental issue and did not demonstrate that a materially different result would be likely if the contentions had been considered initially.6 Just as it did in Callaway and Fermi 3, the Commission should (1) deny Beyond Nuclears Petition because it challenges a Commission rule without requesting a waiver and 4

Compare Petition and Motion to Reopen with Missouri [Coalition] for the Environments Hearing Request and Petition to Intervene in License Renewal Proceeding for Callaway Nuclear Power Plant (Dec. 8, 2014) (ADAMS Accession No. ML14342B010) and Missouri [Coalition] for the Environments Motion to Reopen the Record of License Renewal Proceeding for Callaway Unit 1 Nuclear Power Plant (Dec. 8, 2014) (ADAMS Accession No. ML14342B011) (the only substantive difference between these pleadings is that the Missouri Coalition for the Environments pleadings include timeliness arguments based on the alleged availability of the final NUREG-1437, Supplement 51, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Callaway Plant, Unit 1 whereas Beyond Nuclears pleadings state, without legal support, that they are timely because they depend on a future ruling on a case pending before the U.S. Court of Appeals for the District of Columbia Circuit);

compare Petition and Motion to Reopen with Beyond Nuclears Hearing Request and Petition to Intervene in Combined License Proceeding for Fermi Unit 3 Nuclear Power Plant (Feb. 12, 2015) (ADAMS Accession No. ML15043A567) and Beyond Nuclears Motion to Reopen the Record of Combined License Proceeding for Fermi Unit 3 Nuclear Power Plant (Feb. 12, 2015) (ADAMS Accession No.

ML15043A566).

5 Union Elec. Co. (Callaway Nuclear Power Plant, Unit 1), CLI-15-11, 81 NRC __, __ (Apr. 23, 2015) (slip op. at 4); DTE Electric Co. (Fermi Nuclear Power Plant, Unit 3), CLI-15-12, 81 NRC __, __

(Apr. 23, 2015) (slip op. at 4).

6 Callaway, CLI-15-11, 81 NRC at __ (slip op. at 4 n.17); Fermi, CLI-15-12, 81 NRC at __ (slip op.

at 4 n.17).

because it fails to raise a genuine issue of fact or law material to the Davis-Besse LR proceeding and (2) deny Beyond Nuclears Motion to Reopen because it does not address a significant environmental issue and because it does not demonstrate that a materially different result would be likely if the proposed new contention had been raised at the beginning of the proceeding. Moreover, the Commission should also deny the Petition and Motion because they are untimely.

BACKGROUND This proceeding concerns FirstEnergy Nuclear Operating Companys (FENOCs) August 27, 2010 license renewal application (LRA) seeking to renew for twenty years the operating license for Davis-Besse from its current expiration date of April 22, 2017.7 The Staff accepted the LRA for review, and published a Federal Register Notice on October 25, 2010, providing a Notice of Opportunity for Hearing.8 The deadline for requesting a hearing was set at 60 days after the publication of this Federal Register Notice.9 New or amended contentions filed after this deadline were required to be filed within sixty days of the date when the material information on which they were based first became available to the moving party.10 Beyond Nuclear, along with Citizens Environmental Alliance of Southwestern Ontario, Dont Waste Michigan, and Green Party of Ohio (collectively, the Intervenors), initially filed a 7

See Letter from Barry S. Allen, Vice President - Nuclear, FENOC, to NRC, License Renewal Application and Ohio Coastal Management Program Consistency Certification (Aug. 27, 2010) (ADAMS Accession No. ML102450565) (transmitting the LRA). The LRA itself is available at http://www.nrc.gov/reactors/operating/licensing/renewal/applications/davis-besse/davis-besse-lra.pdf (LRA).

8 Notice of Acceptance for Docketing of the Application, Notice of Opportunity for Hearing for Facility Operating License No. NPF-003 for an Additional 20-Year Period; FirstEnergy Nuclear Operating Company, Davis-Besse Nuclear Power Station, Unit 1, 75 Fed. Reg. 65,528 (Oct. 25, 2010).

9 Id. at 65,529.

10 Order (Initial Scheduling Order), at 12 (Jun. 15, 2011) (unpublished) (ADAMS Accession No.

ML111662021) (ISO).

hearing request on December 27, 2010 proposing four contentions.11 In LBP-11-13, the Board narrowed the Intervenors proposed Contentions 1, 2, and 3 and admitted them as a single Contention 1 and also admitted, as narrowed, Contention 4 regarding severe accident mitigation alternatives (SAMA) analysis.12 FENOC appealed this ruling and, in CLI-12-08, the Commission reversed the Boards admission of these contentions, with the exception of the portion of Contention 4 in which the Intervenors challenged FENOCs use of the Modular Accident Analysis Program (MAAP) computer code.13 FENOC subsequently moved for summary disposition of this remaining area of contention14 and the Board granted its motion in LBP 26.15 On October 10, 2011, workers identified indications of cracking below the surface of the Davis-Besse shield building.16 In response to the discovery of the shield building concrete cracking, FENOC revised its LRA to include a new, plant-specific aging management program (AMP) entitled the Shield Building Monitoring AMP.17 The purpose of the Shield Building 11 Request for a Public Hearing and Petition for Leave to Intervene in the Matter of FirstEnergys Application to Relicense the Davis-Besse Nuclear Power Plant (Facility Operating License No-NFP-003, Docket No. 50-346, NRC-2010-0299) for 20 Additional Years of Extended Operation (Dec. 27, 2010)

(ADAMS Accession No. ML103610406).

12 FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1), LBP-11-13, 73 NRC 534, 565, 577 (2011).

13 FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1), CLI-12-08, 75 NRC 393, 409 (2012).

14 FirstEnergys Motion for Summary Disposition of Contention 4 (SAMA Analysis Source Terms)

(Jul. 26, 2012) (ADAMS Accession No. ML12208A431).

15 FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1), LBP-12-26, 76 NRC 559, 561 (2012).

16 See FENOCs Answer Opposing Intervenors Motion for Admission of Contention No. 5 on Shield Building Cracking, at 4 (Feb. 6, 2012) (ADAMS Accession No. ML12037A245).

17 See Letter from David M. Imlay, FENOC, to NRC, Reply to Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station, Unit No. 1, License Renewal Application (TAC No. ME4640) and License Renewal Application Amendment No. 25, at Enclosure (Apr. 5, 2012) (ADAMS Accession No. ML12097A520) (LRA Amendment 25); Letter from Thomas J. Summers, FENOC, to NRC, Reply to Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station, Unit No. 1, License Renewal Application (TAC No. ME4640) and License Renewal Application

Monitoring AMP was to supplement the LRAs pre-existing Structures Monitoring AMP with respect to the Davis-Besse shield building.18 The Intervenors filed motions to admit proposed new Contentions 5,19 6,20 and 721 concerning cracking in the Davis-Besse shield building and the Shield Building Monitoring AMP. The Board denied the Intervenors motions to admit proposed new Contentions 5,22 6,23 and 7.24 On July 9, 2012, following the D.C. Circuits Decision in New York v. NRC, 681 F.3d 471 (D.C. Cir. 2012), the Intervenors filed a motion for leave to file a new contention concerning the Amendment No. 51, at Enclosure (Jul. 3, 2014) (ADAMS Accession No. ML14184B184) (LRA Amendment 51).

18 See LRA Amendment 25 at 6, 7.

19 Motion for Admission of Contention No. 5 on Shield Building Cracking (Jan. 10, 2012) (ADAMS Accession No. ML12010A172). The motion for admission of proposed Contention 5 was followed by five separate motions to amend. See Intervenors Motion to Amend Motion for Admission of Contention No.

5' (Feb. 27, 2012) (ADAMS Accession No. ML12058A249); Intervenors Motion to Amend and Supplement Proposed Contention No. 5 (Shield Building Cracking) (Jun. 4, 2012) (ADAMS Accession No.

ML12156A411); Intervenors Third Motion to Amend and/or Supplement Proposed Contention No. 5 (Shield Building Cracking) (Jul. 16, 2012) (ADAMS Accession No. ML12198A561); Intervenors Fourth Motion to Amend and/or Supplement Proposed Contention No. 5 (Shield Building Cracking) (Jul. 23, 2012) (ADAMS Accession No. ML12205A507); Intervenors Fifth Motion to Amend and/or Supplement Proposed Contention No. 5 (Shield Building Cracking) (Aug. 16, 2012) (ADAMS Accession Nos.

ML12229A584, ML12229A585, ML12229A586, ML12229A587, ML12229A588, ML12230A000, ML12230A001, ML12230A002, ML12230A003, and ML12230A004).

20 Motion for Admission of Contention No. 6 on Shield Building Concrete Void, Cracking and Broken Rebar Problems (Apr. 21, 2014) (ADAMS Accession No. ML14112A007).

21 Intervenors Motion for Admission of Contention No. 7 on Worsening Shield Building Cracking and Inadequate AMPs in Shield Building Monitoring Program (Sept. 2, 2014) (ADAMS Accession No.

ML14245A656). The motion for admission of proposed Contention 7 was followed by two separate motions to amend. See Intervenors Motion to Amend and Supplement Contention No. 7 on Worsening Shield Building Cracking and Inadequate AMPs in Shield Building Monitoring Program (Sept. 8, 2014)

(ADAMS Accession No. ML14251A609); Intervenors Second Motion to Supplement Contention No. 7 on Worsening Shield Building Cracking and Inadequate AMPs in Shield Building Monitoring Program (Dec.

30, 2014) (ADAMS Accession No. ML14364A405).

22 FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1), LBP-12-27, 76 NRC 583, 587 (2012).

23 Memorandum and Order (Denying Intervenors Motion for Admission of Contention No. 6 on Shield Building Concrete Void, Cracking and Broken Rebar Problems) (Jul. 25, 2014) (unpublished)

(ADAMS Accession No. ML14206A719).

24 FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1), LBP-15-1, 81 NRC __, __ (Jan. 15, 2015) (slip op. at 2).

temporary storage and ultimate disposal of spent reactor fuel at Davis-Besse.25 The Commission exercised its inherent supervisory authority and held the contention in abeyance.26 On March 7, 2014, the Staff issued for public comment a draft Davis-Besse plant-specific Supplement 52 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants, NUREG-1437 (Davis-Besse DSEIS).27 On August 26, 2014, the Commission approved a final rule and GEIS regarding the environmental impacts of the continued storage of spent fuel (the Continued Storage Rule and Continued Storage GEIS, respectively).28 At the same time, the Commission issued CLI-14-08.

In CLI-14-08, the Commission stated that in the Continued Storage GEIS, it had determined that the environmental impacts of continued storage would not vary significantly from site to site and could, therefore, be analyzed generically.29 The Commission explained that, because the generic impacts of continued storage had been the subject of extensive public participation in the Continued Storage rulemaking process, those generic determinations are excluded from 25 Intervenors Motion for Leave to File a New Contention Concerning Temporary Storage and Ultimate Disposal of Nuclear Waste at Davis-Besse Nuclear Power Station (July 9, 2012) (ADAMS Accession No. ML12191A421).

26 Calvert Cliffs 3 Nuclear Project, LLC & UniStar Nuclear Operating Services, LLC (Calvert Cliffs Nuclear Power Plant, Unit 3), CLI-12-16, 76 NRC 63, 68-69 (2012) (In view of the special circumstances of this case, as an exercise of our inherent supervisory authority over adjudications, we direct that these contentions - and any related contentions that may be filed in the near term - be held in abeyance pending our further order.).

27 See License Renewal Application for Davis-Besse Nuclear Power Station, Unit 1, 79 Fed. Reg.

13,079 (Mar. 7, 2014); NUREG-1437, Supplement 52, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Davis-Besse Nuclear Power Station, Draft Report for Comment (Feb. 2014) (ADAMS Accession No. ML14050A290).

28 See SRM-SECY-14-0072, Final Rule: Continued Storage of Spent Nuclear Fuel (RIN 3150-AJ20) at 2, Attachment 5 (Aug. 26, 2014) (ADAMS Accession No. ML14237A092); SECY-14-0072, Final Rule: Continued Storage of Spent Nuclear Fuel (RIN 3150-AJ20) (July 21, 2014) (attaching the GEIS and the draft Continued Storage Rule). The Commission paper and its attachments may be found at ADAMS Accession No. ML14177A482 (package).

29 Calvert Cliffs 3 Nuclear Project, LLC, & UniStar Nuclear Operating Services, LLC (Calvert Cliffs Nuclear Power Plant, Unit 3), CLI-14-08, 80 NRC 71, 78-79 (2014) (CLI-14-08).

litigation in individual proceedings.30 Citing longstanding precedent, the Commission reiterated that [c]ontentions that are the subject of general rulemaking by the Commission may not be litigated in individual license proceedings.31 The Commission observed that the Staff could make decisions on the issuance of final licenses once it has completed its review of the affected applications and has implemented the Continued Storage Rule . . . .32 The Commission then directed the Davis-Besse LR Board, among others, to dismiss the spent fuel contention before it consistent with the Commissions reasoning.33 Accordingly, on October 8, 2014, the Board denied the Intervenors motion for leave to file a new contention concerning the temporary storage and ultimate disposal of spent reactor fuel at Davis-Besse.34 On September 19, 2014, the Commission published its new Continued Storage Rule in the Federal Register with an effective date of October 20, 2014.35 On September 29, 2014, the Intervenors submitted a motion for leave to file a new contention in which they asserted that the NRC had failed to make safety findings regarding the feasibility and capacity for spent fuel disposal in connection with the Davis-Besse LR proceeding.36 This motion was accompanied by a petition to suspend licensing actions.37 On 30 Id. at 79.

31 Id. at n.27, citing Duke Energy Corp. (Oconee Nuclear Power Station, Units 1, 2, and 3), CLI-99-11, 49 NRC 328, 345 (1999).

32 Id. at 77.

33 Id. at 79.

34 Order (Denying Motion to File a New Contention Concerning Temporary Storage of Nuclear Waste), at 1 (Oct. 8, 2014) (unpublished) (ADAMS Accession No. ML14281A448).

35 See Continued Storage of Spent Nuclear Fuel, 79 Fed. Reg. 56,238, 56,238 (Sept. 19, 2014)

(Final Rule).

36 Intervenors Motion for Leave to File a New Contention Concerning the Absence of Required Waste Confidence Safety Findings in the Relicensing Proceeding for Davis-Besse Nuclear Power Station, at 1 (Sept. 29, 2014) (ADAMS Accession No. ML14272A313).

37 Petition to Suspend Final Decisions in All Pending Reactor Licensing Proceedings Pending Issuance of Waste Confidence Safety Findings (Sept. 29, 2014) (ADAMS Accession No. ML14272A339).

February 26, 2015, the Commission denied the suspension petition and denied the associated motions for leave to file a new contention.38 Subsequently, the Board stated that, with the issuance of this Commission ruling, there were no proffered or admitted contentions remaining in the Davis-Besse LR proceeding and, therefore, its jurisdiction had terminated.39 The Board also stated that a petition for review could be filed within 25 days, which time period has since passed.40 On April 22, 2015, Beyond Nuclear filed the instant Petition to Intervene and Motion to Reopen the Record alleging that the Davis-Besse DSEIS is inadequate because its evaluation of the environmental impacts of spent fuel storage and disposal relies on the Continued Storage Rule and Continued Storage GEIS.41 Beyond Nuclear does not seek to litigate the substantive content of this filing in an adjudicatory hearing.42 At its core, Beyond Nuclears contention challenges 10 C.F.R. § 51.23(b).43 38 See DTE Elec. Co. (Fermi Nuclear Power Plant, Unit 3), CLI-15-4, 81 NRC __ (slip op.) (Feb.

26, 2015) (ADAMS Accession No. ML15057A279).

39 FirstEnergy Nuclear Operating Co. (Davis-Besse Nuclear Power Station, Unit 1), LBP-15-9, 81 NRC __, __ (Mar. 10, 2015) (slip op. at 2-3).

40 Id. at 3.

41 Motion to Reopen at 1.

42 Motion to Reopen at 1-2; Petition at 1-2.

43 See Petition at 4-5.

DISCUSSION I. Legal Standards A. Legal Standards for Admission of Contentions For a hearing request to be granted, the requestor must propose at least one admissible contention that meets all of the requirements of 10 C.F.R. § 2.309(f)44 and must submit that contention in a timely filing.45 The requirements for an admissible contention are set out in 10 C.F.R. § 2.309(f)(1), which provides that a contention is admissible if it:

(i) Provide[s] a specific statement of the issue of law or fact to be raised or controverted . . .;

(ii) Provide[s] a brief explanation of the basis for the contention; (iii) Demonstrate[s] that the issue raised in the contention is within the scope of the proceeding; (iv) Demonstrate[s] that the issue raised in the contention is material to the findings the NRC must make to support the action that is involved in the proceeding; (v) Provide[s] a concise statement of the alleged facts or expert opinions which support the requestor's/petitioner's position on the issue and on which the petitioner intends to rely at hearing, together with references to the specific sources and documents on which the requestor/petitioner intends to rely to support its position on the issue; [and]

(vi) . . . provide[s] sufficient information to show that a genuine dispute exists with the applicant/licensee on a material issue of law or fact. This information must include references to specific portions of the application . . . .

The Commission has emphasized that the 10 C.F.R. § 2.309(f)(1) contention admissibility requirements are strict by design.46 Failure to comply with any one of the 10 C.F.R. § 2.309(f)(1) requirements is grounds for dismissing the proposed contention.47 44 10 C.F.R. § 2.309(a).

45 10 C.F.R. § 2.309(b).

46 Dominion Nuclear Connecticut, Inc. (Millstone Nuclear Power Station, Units 2 and 3), CLI 24, 54 NRC 349, 358 (2001), petition for reconsidn denied, CLI-02-01, 55 NRC 1 (2002).

Subsection (iii) of 10 C.F.R. § 2.309(f)(1) explicitly provides that a contention must raise an issue that is within the scope of the proceeding. Challenges to the Commissions regulations and generic determinations are beyond the scope of NRC adjudications.48 A proposed contention otherwise inadmissible as an out-of-scope collateral attack on a Commission rule may, however, be entertained if (1) the proponent of the contention petitions for the waiver of the rule in the particular proceeding, (2) the presiding officer determines that the waiver petition has made a prima facie showing that the application of the specific rule would not serve the purposes for which the rule was adopted and then certifies the matter directly to the Commission, and (3) the Commission makes a determination on the matter.49 If the presiding officer determines that the petitioner has not made the required prima facie showing, no evidence may be received on [the] matter and no discovery, cross examination, or argument directed to the matter will be permitted, and the presiding officer may not further consider the matter.50 Instead, the participant may challenge the rule by filing a petition for rulemaking under 10 C.F.R. § 2.802.51 Contentions must also raise a genuine material issue of law or fact with the specific application at bar.52 In other words, the proponent on the contention must show how resolution 47 Private Fuel Storage, L.L.C. (Independent Spent Fuel Storage Installation), CLI-99-10, 49 NRC 318, 325 (1999), citing Arizona Pub. Serv. Co. (Palo Verde Nuclear Generating Station, Units 1, 2, and 3),

CLI-91-12, 34 NRC 149, 155-56 (1991).

48 See Arizona Pub. Serv. Co. (Palo Verde Nuclear Station, Units No. 1, 2, and 3), LBP-91-19, 33 NRC 397, 410 (1991), appeal granted in part, CLI-91-12, 34 NRC 149 (1991); Philadelphia Elec. Co.

(Peach Bottom Atomic Power Station, Units 2 and 3), ALAB-216, 8 AEC 13, 20 (1974), citing Florida Power & Light Co. (Turkey Point Units No. 3 and 4), 4 AEC 787, 788 (1972) ([A] licensing proceeding before this agency is plainly not the proper forum for an attack on applicable statutory requirements or for challenges to the basic structure of the Commission's regulatory process.).

49 10 C.F.R. §§ 2.335(b) and (d).

50 10 C.F.R. § 2.335(c).

51 10 C.F.R. § 2.335(e).

52 10 C.F.R. § 2.309(f)(1)(vi).

of the dispute would make a difference in the outcome of the licensing proceeding.53 A contention that raises only a generic issue and fails to link that issue to any specific aspect of the pertinent application is inadmissible for failure to raise a genuine material issue.54 While a disagreement as to the interpretation of the language of a rule may raise a genuine issue of law, a challenge to the rule itself does not.55 Such a challenge fails because it does not raise a material issue of law as contemplated by the regulation.

Where the original date for the filing of contentions has passed, the provisions of 10 C.F.R. § 2.309(c) apply. Section 2.309(c) provides that contentions filed after the deadline will not be entertained absent a determination by the presiding officer that the proponent of the contentions has demonstrated good cause by showing that:

(i) The information upon which the filing is based was not previously available; (ii) The information upon which the filing is based is materially different from information previously available; and (iii)The filing has been submitted in a timely fashion based on the availability of the subsequent information.

Whether a contention is timely filed depends in large part on when the new information became available. The Commission generally considers a contention based on new information to be filed in a timely fashion if the contention is filed within 30 days of the availability of the new information. When information is later repeated in a Staff document, however, the date that controls for timeliness purposes is the date that the information first became available, not the 53 Entergy Nuclear Generation Co. & Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), LBP-06-23, 64 NRC 257, 354 (2006), citing Rules of Practice for Domestic Licensing Proceedings - Procedural Changes in the Hearing Process, 54 Fed. Reg. 33,168, 33,172 (Aug. 11, 1989)

(Final Rule).

54 Nextera Energy Seabrook, LLC (Seabrook Station, Unit 1), LBP-11-28, 74 NRC 604, 609 (2011).

55 Exelon Generation Co., LLC (Limerick Generating Station, Units 1 and 2), LBP-12-8, 75 NRC 539, 566 (2012), revd in part, CLI-12-19, 76 NRC 377 (2012), remanding LBP-13-1, 77 NRC 57 (2013),

affd on other grounds, CLI-13-7, 78 NRC 199 (2013).

later date when the Staff collect[ed], summarize[d] and place[d] into context the facts supporting the contention.56 B. Legal Standards for Reopening of the Record The Commission has stated that a petitioner seeking to introduce a new contention after the record has been closed should address the reopening standards contemporaneously with a late-filed intervention petition, which must satisfy the standards for both contention admissibility and late filing.57 Section 2.326(a) of the Commissions regulations states that a motion to reopen will not be granted unless the following criteria are satisfied:

(1) The motion must be timely. However, an exceptionally grave issue may be considered in the discretion of the presiding officer even if untimely presented; (2) The motion must address a significant safety or environmental issue; and (3) The motion must demonstrate that a materially different result would be or would have been likely had the newly proffered evidence been considered initially.

Additionally, one or more affidavits showing that the motion to reopen meets the above three criteria must accompany the motion.58 Each affidavit must contain statements from competent individuals with knowledge of the facts alleged or experts in disciplines appropriate to the issues raised.59 Moreover, the motion to reopen and its supporting documentation must be strong 56 Northern States Power Co. (Prairie Island Nuclear Generating Plant, Units 1 and 2), CLI-10-27, 72 NRC 481, 496 (2010). See also Southern Nuclear Operating Co. (Vogtle Electric Generating Plant, Units 3 and 4), CLI-11-8, 74 NRC 214, 224-225 (2011).

57 Dominion Nuclear Connecticut, Inc. (Millstone Nuclear Power Station, Unit 3), CLI-09-5, 69 NRC 115, 124 (2009).

58 10 C.F.R. § 2.326(b).

59 Id. See also AmerGen Energy Co., LLC (Oyster Creek Nuclear Generating Station), CLl-09-7, 69 NRC 235, 291-93 (2009).

enough, in the light of any opposing filings, to avoid summary disposition.60 The Commission has held that [t]he burden of satisfying the reopening requirements is a heavy one [and that]

proponents of a reopening motion bear the burden of meeting all of [these] requirements.61 Section 2.326(d) further provides that a motion to reopen that relates to a contention not previously in controversy among the parties must also satisfy the requirements in 10 C.F.R.

§ 2.309(c) (discussed above) for contentions submitted after the original deadline for filing.

II. The Petition Should Be Denied for Failing to Timely Proffer an Admissible Contention Beyond Nuclears proposed contention asserts that, the Continued . . . Storage Rule and GEIS fail to provide the NRC with a lawful basis under [the National Environmental Policy Act of 1969, as amended, (NEPA)] for licensing Davis-Besse.62 The Petition goes on to identify seven specific alleged failures in the Continued Storage Rule and GEIS.63 Simply stated, Beyond Nuclears proposed contention is an impermissible challenge to the Commissions Continued Storage Rule and GEIS. As the Commission just recently held in Callaway and Fermi 3 with respect to a substantively identical proposed contention, a placeholder contention such as the instant contention is not admissible under the Commissions rules of practice because it impermissibly challenges an agency regulation and is therefore outside the scope of an individual licensing proceeding.64 Additionally, Beyond Nuclear does not raise any site-specific environmental issues with respect to the Davis-Besse LR application and, thus, does not show that a genuine dispute exists with the applicant on a 60 Private Fuel Storage, L.L.C. (Independent Spent Fuel Storage Installation), CLI-05-12, 61 NRC 345, 350 (2005) (PFS), citing Vermont Yankee Nuclear Power Corp. (Vermont Yankee Nuclear Power Station), ALAB-138, 6 AEC 520, 523-4 (1973).

61 Oyster Creek, CLI-09-7, 69 NRC at 287 (internal quotations omitted, alteration in original).

62 Petition at 4.

63 Id. at 4-5.

64 Callaway, CLI-15-11, 81 NRC at __ (slip op. at 3-4); Fermi, CLI-15-12, 81 NRC at __ (slip op.

at 4).

material issue of law or fact. Finally, Beyond Nuclears Petition is untimely. For all of these reasons, Beyond Nuclears Petition should be denied.

A. The Proposed Contention Challenges a Rulemaking that Is Beyond the Scope of this Proceeding Beyond Nuclears proposed contention is a challenge to the Continued Storage Rule and GEIS and, as a challenge to a Commission rule, it is a challenge that is beyond the scope of this proceeding.65 Every alleged failure and violation of NEPA that Beyond Nuclear asserts is an alleged failure or violation by virtue of the Continued Storage Rule or GEIS.66 Beyond Nuclears only complaint with the Davis-Besse DSEIS is the fact that the Continued Storage Rule adopted the environmental impacts described in the Continued Storage GEIS and deemed them incorporated into the DSEIS.67 Commission regulations bar such challenges to its rules: 10 C.F.R. § 2.335(a) provides that no rule or regulation of the Commission, or any provision thereof, . . . is subject to attack by way of discovery, proof, argument, or other means in any adjudicatory proceeding subject to this part. Contentions that challenge Commission regulations or its regulatory processes are beyond the scope of adjudicatory proceedings and have been regularly dismissed as such.68 Most recently and to the point, in ruling on a substantively identical proposed contention in Callaway and Fermi 3, the Commission held that such a contention was not admissible because it impermissibly challenges an agency regulation and is therefore outside the scope of an 65 See 10 C.F.R. § 2.309(f)(1)(iii).

66 See Petition at 4-5.

67 Id. at 4.

68 See, e.g., Callaway, CLI-15-11, 81 NRC at __ (slip op. at 3-4); Fermi, CLI-15-12, 81 NRC at __

(slip op. at 4); Palo Verde, LBP-91-19, 33 NRC at 400, 410, appeal granted in part, CLI-91-12, 34 NRC 149 (1991); Peach Bottom, ALAB-216, 8 AEC at 20, citing Florida Power & Light Co. (Turkey Point Units No. 3 and 4), 4 AEC 787, 788 (1972) ([A] licensing proceeding before this agency is plainly not the proper forum for an attack on applicable statutory requirements or for challenges to the basic structure of the Commission's regulatory process.).

individual licensing proceeding.69 Further, in its Continued Storage decision in CLI-14-08, the Commission also wrote: Contentions that are the subject of general rulemaking by the Commission may not be litigated in individual license proceedings.70 For this same reason, contentions that challenge the NRCs generic environmental impact statement for license renewal have been rejected in case after case.71 In CLI-14-08, the Commission explained,

[b]ecause these generic impact determinations have been the subject of extensive public participation in the rulemaking process, they are excluded from litigation in individual proceedings.72 Consistent with the recent Callaway and Fermi 3 decisions, as well as CLI 08 and longstanding case law, the Commission should deny Beyond Nuclears challenge to the Continued Storage Rule and GEIS.

Nevertheless, in accordance with the provisions of 10 C.F.R. § 2.335, Beyond Nuclear could still have challenged the Continued Storage Rule and GEIS in this adjudicatory proceeding had it sought and obtained a waiver of the prohibition against such challenges. In order to obtain such a waiver, 10 C.F.R. § 2.335(b) requires that a petitioner provide an affidavit demonstrating that special circumstances with respect to the subject matter of the particular proceeding are such that the application of the regulation would not serve the purposes for which the regulation was adopted. But Beyond Nuclear has not done this; instead, Beyond Nuclear states that its contention is not accompanied by a petition for a waiver and explains 69 Callaway, CLI-15-11, 81 NRC at __ (slip op. at 3-4); Fermi, CLI-15-12, 81 NRC at __ (slip op.

at 4).

70 Calvert Cliffs, CLI-14-08, 80 NRC at 79 n.27, citing Duke Energy Corp. (Oconee Nuclear Station, Units 1, 2, and 3), CLI-99-11, 49 NRC 328, 345 (1999).

71 See, e.g., Exelon Generation Co., LLC (Limerick Generating Station, Units 1 and 2), CLI-12-19, 76 NRC 377, 386 (2012), remanding, LBP-13-1, 77 NRC 57 (2013), affg on other grounds, CLI-13-7, 78 NRC 199 (2013); Entergy Nuclear Vermont Yankee, LLC & Entergy Nuclear Operations, Inc. (Vermont Yankee Nuclear Power Station), CLI-07-03, 65 NRC 13, 20 (2007); Florida Power & Light Co. (Turkey Point Nuclear Generating Plant, Units 3 and 4), CLI-01-17, 54 NRC 3, 11-12 (2001).

72 Calvert Cliffs, CLI-14-08, 80 NRC at 79.

that this is because [n]o purpose would be served by such a waiver, because Beyond Nuclear does not seek an adjudicatory hearing on the NRCs generic environmental findings.73 Given that Beyond Nuclears proposed contention challenges the NRCs Continued Storage Rule and GEIS and that Beyond Nuclear has affirmatively decided to forego petitioning for a waiver, the Commission should deny Beyond Nuclears Petition.74 B. The Proposed Contention Fails to Raise a Genuine Material Issue Beyond Nuclear asserts, without referencing to any specific portions of the Davis-Besse LR application, that its contention raises a genuine dispute with both the applicant and the NRC regarding whether the NRC has satisfied NEPA for the purpose of renewing the operating license for Davis-Besse.75 As explained above, Beyond Nuclears contention is an inadmissible attack on the Commissions Continued Storage Rule and GEIS and, as such, it cannot raise a genuine issue for dispute as required by 10 C.F.R. § 2.309(f)(1)(vi); the dispute is, per se, not a genuine one.76 Additionally, it is well established that an admissible contention must raise a genuine dispute with the license application in order to demonstrate that a material issue for hearing exists.77 All Beyond Nuclear disputes is the incorporation of the Continued Storage Rule and GEIS into the Davis-Besse DSEIS. This incorporation was, however, mandated by the Commission. The Continued Storage Rule itself provides that:

The environmental reports described in . . . [§] 51.53 [Postconstruction environmental reports] . . . are not required to discuss the environmental 73 Petition at 3 n.3.

74 See Limerick, CLI-12-19, 76 NRC at 386-87; Callaway, CLI-15-11, 81 NRC at __ (slip op. at 3-4).

75 Petition at 5.

76 See Limerick, LBP-12-8, 75 NRC at 566, 566 n.188, revd on other grounds, CLI-12-16, 76 NRC 377 (2012); Callaway, CLI-15-11, 81 NRC at __ (slip op. at 3-4).

77 Entergy Nuclear Generation Co. & Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-12-15, 75 NRC 704, 709 (2012).

impacts of spent nuclear fuel storage in a reactor facility storage pool or an [Independent Spent Fuel Storage Installation (ISFSI)] for the period following the term of the reactor operating license . . . . The impact determinations in [the Continued Storage GEIS] regarding continued storage shall be deemed incorporated into the environmental impact statements described in . . . [§] 51.95 [Postconstruction environmental impact statements] . . . .[78]

As the Limerick board observed, while a disagreement over the proper interpretation of NRC regulations may give rise to an admissible contention, an interpretation that is in direct conflict with the plain meaning of a regulation and the agencys Statements of Consideration fails to present a genuine dispute of fact or law . . . as required by NRC regulations.79 Beyond Nuclears proposed contention, which is in direct conflict with the Continued Storage Rule, thus fails to present a genuine dispute as required by 10 C.F.R. § 2.309(f)(1)(vi) and should be rejected.

C. The Proposed Contention Is Untimely The initial deadline for filing contentions in the Davis-Besse LR proceeding was December 27, 2010.80 A petition to intervene filed after this deadline will not be entertained absent a determination that the petition was timely filed based on the availability of previously unavailable and materially different information.81 However, instead of identifying previously unavailable and materially different information as providing good cause for its late filing of its Petition, Beyond Nuclear states that the Petition does not depend at all on past information.82 This assertion, though, is incorrect. The entirety of Beyond Nuclears statement of its proposed 78 10 C.F.R. § 51.23(b) (emphasis added). See DTE Electric Co. (Fermi Nuclear Power Plant, Unit 3), CLI-15-10, 81 NRC __, __ (Apr. 23, 2015) (slip op. at 5) (holding that, by the terms of the plain language of 10 C.F.R. § 51.23(b), the environmental impacts in the Continued Storage GEIS have already been incorporated into the NRCs environmental evaluations in individual licensing proceedings by operation of law).

79 Limerick, LBP-12-8, 75 NRC at 566.

80 See 75 Fed. Reg. at 65,529.

81 10 C.F.R. § 2.309(c)(1).

82 Petition at 5.

new contention is an argument against the Continued Storage Rule and GEIS83 and this argument does indeed depend on past information, that is, on the Continued Storage Rule and GEIS themselves, which were published in the Federal Register on September 19, 2014.84 The Continued Storage Rule went into effect on October 20, 2014, and Beyond Nuclear had an obligation to raise its contention in a timely manner based on the effective date of the rule, at the latest.85 The Petition should therefore be denied as untimely.

Beyond Nuclear attempts to cure this pleading deficiency by asserting that its Petition is timely because it depends on an event that will occur in the future . . . .86 However, Beyond Nuclear cites no authority supporting this assertion that filing timeliness before the Commission can be measured from an event that has not yet occurred, and the Staff has not identified any cases that support such a theory. Moreover, such a theory could be used to support the endless filing of late contentions based on claims that some event in the future may eventually provide a basis for the filings.

By filing a petition based on documents published many months earlier and by not identifying any other potentially new and materially different documents, but instead relying on an unsupported theory of future new and materially different information, Beyond Nuclear has not filed its Petition in a timely fashion and, thus, the Petition should be denied.

III. The Motion to Reopen Should Be Denied for Failing to Meet the Reopening Standards Beyond Nuclear does not meet the Commissions reopening standards provided in 10 C.F.R. § 2.326(a)(1)-(3) because its Motion to Reopen is untimely without raising an 83 Id. at 4-5.

84 See Continued Storage of Spent Nuclear Fuel, 79 Fed. Reg. 56,238 (Sept. 19, 2014) (Final Rule).

85 Additionally, Beyond Nuclear notes that its contention is similar to one filed in Callaway in December 2014. Petition at 1 n.1. The fact that Beyond Nuclear subsequently took more than four months to file a substantively identical contention only reinforces its untimeliness.

86 Petition at 5.

exceptionally grave issue, it does not address a significant environmental issue, and it does not demonstrate that a materially different result would be likely if the proposed new contention had been raised at the beginning of the proceeding. Accordingly, Beyond Nuclears Motion to Reopen should be denied.

A. Beyond Nuclears Motion Is Untimely and Does Not Raise an Exceptionally Grave Issue Under 10 C.F.R. § 2.326(a)(1), a motion to reopen must be timely. As discussed above, the issues raised in Beyond Nuclears Motion to Reopen are not timely because they are based on the analyses contained in the Continued Storage Rule and GEIS that were published on September 19, 2014.87 Nonetheless, 10 C.F.R. § 2.326(a)(1) provides an exception to its timeliness requirement for when the motion to reopen raises an exceptionally grave issue.

The Commission anticipates that this exception will be granted rarely and only in truly extraordinary circumstances.88 The Commission has stated that an untimely raised environmental issue could be exceptionally grave, depending on the circumstances of the case and the facts presented.89 However, Beyond Nuclear has not made any arguments or presented any facts in support of the existence of an exceptionally grave issue. Therefore, Beyond Nuclears Motion to Reopen is untimely and this untimeliness cannot be excused.

B. Beyond Nuclears Motion Does Not Address a Significant Environmental Issue Under 10 C.F.R. § 2.326(a)(2), a motion to reopen must address a significant safety or environmental issue. When a motion to reopen is untimely, the 10 C.F.R. § 2.326(a)(1) exceptionally grave issue test supplants the 10 C.F.R. § 2.326(a)(2) significant safety or 87 See Motion to Reopen at 1-2.

88 Criteria for Reopening Records in Formal Licensing Proceedings, 51 Fed. Reg. 19,535, 19,536 (May 30, 1986) (Final Rule).

89 Entergy Nuclear Generation Co. & Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-12-21, 76 NRC 491, 500-501 (2012).

environmental issue test.90 As discussed above, the claims in Beyond Nuclears Motion to Reopen are untimely and do not raise an exceptionally grave issue; therefore, Beyond Nuclears Motion to Reopen also does not meet the requirements of 10 C.F.R. § 2.326(a)(2).

Moreover, even if Beyond Nuclear had filed its Motion to Reopen in a timely fashion, the motion still does not raise a significant environmental issue under 10 C.F.R. § 2.326(a)(2). For environmental issues, the Commission has found that the standard for showing significance to reopen a closed record is analogous to the standard for supplementing an environmental impact statement.91 This standard is that the Staff must prepare a supplement to a final environmental impact statement if: (1) [t]here are substantial changes in the proposed action that are relevant to environmental concerns; or (2) [t]here are new and significant circumstances or information relevant to environmental concerns and bearing on the proposed action or its impacts.92 Any such new information must paint a seriously different picture of the environmental landscape.93 Beyond Nuclear asserts that its Motion to Reopen raises the significant environmental issue that the Davis-Besse DSEIS, because of its dependence on the Continued Storage Rule and GEIS, lacks an adequate analysis of the environmental impacts of spent fuel storage and disposal such that it fails to provide sufficient support for the proposed licensing action.94 Beyond Nuclear does not explain how there is new and significant information relevant to its environmental concerns and how that information bears on the Davis-Besse LR application 90 Vogtle, CLI-11-8, 74 NRC at 225 n.44 (citing Pub. Serv. Co. of New Hampshire (Seabrook Station, Units 1 and 2), ALAB-886, 27 NRC 74, 78 (1988)).

91 Private Fuel Storage, L.L.C. (Independent Spent Fuel Storage Installation), CLI-06-03, 63 NRC 19, 28-29 (2006).

92 10 C.F.R. § 51.92(a).

93 PFS, CLI-06-3, 63 NRC at 28 (quoting Natl Comm. for the New River, Inc. v. FERC, 373 F.3d 1323, 1330 (D.C. Cir. 2004) (emphasis in original)).

94 Motion to Reopen at 4.

such that it paints a seriously different picture of the environmental landscape. Instead, Beyond Nuclear relies solely on its comments on the draft Continued Storage Rule and GEIS,95 but fails to explain how these comments paint a new and seriously different picture of the environment.

Accordingly, Beyond Nuclears claims do not constitute a significant environmental issue under 10 C.F.R. § 2.326(a)(2) and its Motion to Reopen should be denied.

C. Beyond Nuclears Motion Does Not Show that a Materially Different Result Would Be Likely Under 10 C.F.R. § 2.326(a)(3), a motion to reopen must demonstrate that a materially different result would be or would have been likely had the newly proffered evidence been considered initially. One Board has explained that, under this standard, [t]he movant must show that it is likely that the result would have been materially different, i.e., that it is more probable than not that [the movant] would have prevailed on the merits of the proposed new contention.96 The Commission has made clear that the evidence provided in support of a motion to reopen must be sufficiently compelling to suggest a likelihood of materially affecting the ultimate results in the proceeding. 97 Beyond Nuclear has not demonstrated that a materially different result would be likely in this proceeding had its proposed new contention been considered initially. In its Motion to Reopen, Beyond Nuclear claims that the purpose of its new contention is to ensure that the NRC will withdraw the Davis-Besse DSEIS as a basis for re-licensing Davis-Besse and, therefore, withdraw the Davis-Besse license renewal permit, if the U.S. Court of Appeals for the District of Columbia Circuit vacates the Continued Storage Rule and GEIS.98 Although Beyond 95 See id.

96 Entergy Nuclear Vermont Yankee, LLC & Entergy Nuclear Operations, Inc. (Vermont Yankee Nuclear Power Station), LBP-10-19, 72 NRC 529, 549 (2010) (emphasis in original).

97 Entergy Nuclear Generation Co. & Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-12-10, 75 NRC 479, 498 (2012).

98 Motion to Reopen at 4.

Nuclear does assert that the admission of its proposed new contention would likely produce a materially different result in this proceeding, Beyond Nuclears logic is flawed. First, Beyond Nuclear appears to contradict itself in asserting that admission of its contention would produce a materially different result because it also concedes that it is submitting its new contention with the reasonable expectation that it will be denied, because the subject matter of the contention is generic.99 Second, Beyond Nuclear provides no evidence to establish the likelihood that its challenge to the Continued Storage Rule and GEIS would prevail especially given the fact that the very same comments on which it is based were available to the Commission at the time of its approval of the Continued Storage Rule and GEIS. Finally, Beyond Nuclear has not shown that a materially different result would be likely because, as explained above, Beyond Nuclear has failed to proffer an admissible contention under 10 C.F.R. §§ 2.309(f)(1) and 2.309(c).

Beyond Nuclear also describes its contention as a placeholder that it does not intend to litigate before the NRC but, instead, only intends to appeal upon its denial.100 However, as the Commission held in Callaway and Fermi 3, such placeholder contentions are not necessary to ensure that a petitioners challenge to a Commission rule receives a full and fair airing.101 CONCLUSION Beyond Nuclears Petition to Intervene is inadmissible because it raises an issue that is beyond the scope of this proceeding by challenging a Commission rule without requesting a waiver of the rule, it fails to raise a genuine issue of material fact or law, and it was filed late without good cause. Beyond Nuclears Motion to Reopen is inadmissible because it is untimely without addressing an extremely grave issue, it does not address a significant environmental 99 Petition at 2.

100 Motion to Reopen at 1-2.

101 See Callaway, CLI-15-11, 81 NRC at __ (slip op. at 5); Fermi, CLI-15-12, 81 NRC at __ (slip op. at 5). Instead, the Commission stated that, [s]hould the D.C. Circuit find any infirmities in the Continued Storage Rule or GEIS, we would take appropriate action consistent with the courts direction.

Callaway, CLI-15-11, 81 NRC at __ (slip op. at 5).

issue, and it does not demonstrate that a materially different result would be likely if its proposed new contention had been raised at the beginning of the proceeding. Accordingly, consistent with the Commissions denial of a substantively identical proposed contention in Callaway and Fermi 3, the Commission should deny both Beyond Nuclears Petition to Intervene and Motion to Reopen.

Respectfully submitted,

/Signed (electronically) by/

Jeremy Wachutka Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop O15-D21 Washington, DC 20555 Telephone: (301) 415-1571 E-mail: Jeremy.Wachutka@nrc.gov Executed in Accord with 10 CFR 2.304(d)

Brian G. Harris Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop O-15 D21 Washington, DC 20555 Telephone: (301) 415-1392 E-mail: Brian.Harris@nrc.gov Dated at Rockville, Maryland this 1st day of May, 2015

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of )

)

FIRSTENERGY NUCLEAR OPERATING CO. ) Docket No. 50-346-LR

)

(Davis-Besse Nuclear Power Station, Unit 1) )

CERTIFICATE OF SERVICE Pursuant to 10 C.F.R. § 2.305, I hereby certify that copies of the foregoing NRC STAFF ANSWER TO BEYOND NUCLEARS HEARING REQUEST AND PETITION TO INTERVENE AND MOTION TO REOPEN THE RECORD IN THE LICENSE RENEWAL PROCEEDING FOR DAVIS-BESSE NUCLEAR POWER PLANT, dated May 1, 2015 have been served upon the Electronic Information Exchange, the NRCs E-Filing System, in the above-captioned proceeding, this 1st day of May, 2015.

/Signed (electronically) by/

Jeremy Wachutka Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop O15-D21 Washington, DC 20555 Telephone: (301) 415-1571 E-mail: Jeremy.Wachutka@nrc.gov Dated at Rockville, Maryland this 1st day of May, 2015