ML15118A143

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/95-25,50-270/95-25 & 50-287/95-25 on 951204-08 & 11-15.No Violations Noted.Major Areas Inspected: Implementation & Completion of Commitments Made in Response to GL 89-10
ML15118A143
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 01/11/1996
From: Fredrickson P, Whitener H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML15118A142 List:
References
50-269-95-25, 50-270-95-25, 50-287-95-25, GL-89-10, NUDOCS 9611140002
Download: ML15118A143 (15)


See also: IR 05000269/1995025

Text

pjk REGLI.

UNITED STATES

REa

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

Report Nos. 50-269/95-25, 50-270/95-25, and 50-287/95-25

Licensee:

Duke Power Company

422 South Church Street

Charlotte, NC 28242

Docket Nos.:

50-269, 50-270, and 50-287

License Nos.: DPR-38, DRP-47

and DRP-55

Facility Name: Oconee Nuclear Station Units 1, 2, and 3

Inspection Conducted:

December 4-8 and 11-15, 1995

Lead Inspector: /1

,

/

7//

H. Whitener, Reactor Inspector

Date Signed

Accompanying Personnel: M. Miller, Reactor Inspector RII

T. Scarbrough, NRR

Holbrook, ,Contr ctor INEL

Approved by.-, ,--.

-i'

/

Paul Fredrickson, Chief

tate Signed

Special Inspection Branch

Division of Reactor Safety

SUMMARY

Scope:

This special, announced inspection was performed at the Oconee Nuclear Station

to assess the licensee's implementation and completion of commitments made in

response to Generic Letter (GL) 89-10, "Safety-Related Motor-Operated Valve

Testing and Surveillance."

Results:

The inspectors concluded that the licensee's implementation of the recommenda

tions of GL 89-10 had been completed in a satisfactory manner. Therefore, the

NRC staff is closing its review of the Oconee GL 89-10 program. However, the

licensee is still expected to maintain the GL 89-10 valves in accordance with

the recommendations in the generic letter. In addition, two inspector

followup items (IFIs) and several other concerns and commitments remain to be

completed. The first IFI concerns the licensee's need to respond to the

Vectra Report on butterfly valves. The second IFI addresses hard seat contact

for the "Anchor/Darling" Double Disc Gate valves. One violation identified

during the GL 89-10 Part 2 inspection was closed. There are no operability

concerns with any of the followup items and remaining items. These items are

listed below:

9611140002 960111

PDR ADOCK 05000269

G

PDR

2

Inspector Followup Items

(Closed) VIO 50-269/94-13-01, Inadequate Procedure Preparation For IST

Testing.

[Section 3.0]

(Open) IFI 50-269,270,287/95-25-01, "Response To Vectra Report

Butterfly Valves". The licensee needs to address and respond to three

areas in the report, 1) flow resistance, 2) procedure improvement, and

3) shaft orientation. [Section 2.5]

(Open) IFI 50-269,270,287/95-25-02, "Anchor/Darling Double Disc Gate

Flow Cutoff".

The licensee needs to address hard seat contact. The

licensee determined that the MOVs meet theoretical flow isolation of the

EPRI model but not hard seat contact. .[Section 2.5]

Remaining Items

Thirteen commitments which were stated in Attachment 1 of the licensee's

letter to the NRC, "Request for Closure of Generic Letter 89-10" dated

March 31, 1995, remain to be completed. All the other commitment items

addressed in the Request for Closure Letter have been satisfactorily

addressed by the licensee and were closed during this inspection.

[Section 2.0 and 2.5]

Strengths

1)

The licensee implemented "flow loop testing".

[Section 2.5]

2)

The licensee used innovative technology such as "bench testing"

and the Motor Power Monitor. [Section 2.10]

3)

Licensee personnel, including both engineering and maintenance,

were very knowledgeable of the issues related to GL 89-10.

[Section 2.0]

4)

The licensee personnel were pro-active in the MOV industry.

[Section 2.5]

S

REPORT DETAILS

1.0

Persons Contacted

1.1

Licensee Employees

  • E. Burchfield, Manager, Regulatory Compliance
  • T. Cline, Valve Engineering Support, General Office
  • J. Davis, Manager, Engineering
  • J. Hampton, Site Vice President
  • T. Ledford, Engineer
  • D. King, Valve Engineering
  • K. Matthews, Valve Engineering
  • B. Millsaps, Mechanical/Civil Engineering Manager
  • D. Nix, Regulatory Compliance
  • B. Peele, Station Manager
  • B. Sealy, Engineer
  • J. Smith, Regulatory Compliance
  • C. Tompkins, Valve Engineering Supervisor
  • L. Underwood, Engineer

1.2

U. S. Nuclear Regulatory Commission

  • P. Harmon, Senior Resident Inspector

Acronyms and initialisms used throughout this report are listed in the

last paragraph.

2.0

GENERIC LETTER (GL) 89-10 "SAFETY-RELATED MOTOR-OPERATED VALVE (MOV)

TESTING AND SURVEILLANCE"

(TI 2515/109)

On June 28, 1989, the NRC issued GL 89-10, which requested licensees and

construction permit holders to establish a program to ensure that switch

settings for safety-related MOVs were selected, set, and maintained

properly. Subsequently, six supplements to the GL have been issued.

NRC inspections of licensee actions implementing commitments to GL 89-10

and its supplements have been conducted based on guidance provided in

Temporary Instruction (TI) 2515/109, "Inspection Requirements for

Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and

Surveillance." Temporary Instruction 2515/109 is divided into Part 1,

"Program Review," and Part 2, "Verification of Program Implementation".

In a letter to the NRC dated December 12, 1994, the licensee provided

notification and requested closure of the Generic Letter 89-10 Program.

On January 23, 1995, a phone conversation was held between Duke and NRC

representatives concerning GL 89-10 closure. In that phone

conversation, Oconee stated they would provide the NRC a "Generic Letter 89-10 Closure Audit Package". In a letter to the NRC dated March 31,

1995, the licensee provided the "Supplemental Information for Closure

Audit". The supplemental information listed the licensee's commitments

in Attachment 1 of the letter. The inspectors verified that all

licensee commitments

2

listed in the March 31, 1995, Duke letter have been satisfactorily

addressed and are closed except for 11 Unit 1 and two Unit 2 items.

These remaining commitments are as follows:

Valves

Document

Modification or Work

1)

2-BS-001

W095067563

Replace motor

2)

2-HP-024

W095067625

Change motor gear set

3)

2-HP-025

W095067629

Change motor gear set

4)

2-HP-409

W095067535

Replace valve

5)

2-HP-409

W095064580

Replace operator

6)

2-HP-410

W095064581

Replace valve

7)

2-HP-410

W095067858

Replace operator

8)

2-CCW-10

W095067575

Change gear ratio

9)

2-CCW-11

W095067577

Change gear ratio

10)

2-CCW-12

W095067579

Change gear ratio

11)

2-CCW-13

W095067583

Change gear ratio

12)

3-LP-001

Replace actuator and (possibly) valve

13)

3-LP-002

Replace actuator and (possibly) valve

The Unit 2 items are scheduled for implementation during the next

refueling outage 2EOC15 in late Spring 1996. The Unit 3 items are

scheduled for implementation by the end of 1996. The inspectors

verified there were no operability concerns and the work order (WO)

schedule for implementation was satisfactory.

The current inspection assessed the completion of the licensee's

GL 89-10 program as stated in the closure letter. The assessment was

conducted utilizing guidance described in an NRC memorandum of July 12,

1994, "Guidance on Closure of Staff Review of Generic Letter 89-10

Programs" and in TI 2515/109, "Inspection Requirements for Generic

Letter 89-10, Safety-Related Motor-Operated Valve Testing and

Surveillance." The licensee's GL 89-10 program and its implementation

were previously examined and documented in NRC Inspection Reports

50-269, 270, 287/91-13 (Part 1 program) and 94-15 (Part 2

implementation).

Details of this inspection and findings are described

below.

SII

3

2.1

Design-Basis Reviews

During the Part 2 inspection, the inspectors examined the licensee's

design-basis documentation used in the implementation of the GL 89-10

Motor Operated Valve Plant Program for diagnostic testing of MOVs. That

examination included review of mechanical flow diagrams (piping and

instrumentation); design-basis calculation results of the expected

differential pressures; the sizing and switch setting calculations; and

diagnostic test data. The inspectors also conducted a walkdown of

selected MOVs. The inspectors reviewed the licensee's design-basis

documentation (DBD) to determine and verify its adequacy in general for

all MOVs in the program. In addition, the recommended action "a" of

GL 89-10 that requested licensees to determine the maximum differential

pressure and flow expected for both normal and abnormal (accident)

conditions was examined to verify that maximum parameters were used.

During this inspection, the inspectors examined the design-basis

calculations and the torque/thrust calculations to verify their adequacy

for all the GL 89-10 valves. The calculations were reviewed to ensure

all the GL 89-10 recommendations were included.

The design-basis calculations for differential pressure were reviewed to

verify electrical degraded grid voltage, flow, and temperature were used

in the design calculations for thrust and torque. The calculations were

reviewed to determine if the worst case design-basis differential

pressure and flow conditions, design temperature, and other design

parameters for each MOV selected met the recommendations of GL 89-10.

The inspectors verified that degraded grid calculations were included to

ensure that the lowest motor terminal voltage commensurate with design

basis conditions was factored into the determination of maximum thrust

ratings. The inspectors also verified that the licensee satisfactorily

addressed the Limitorque Part 21 high temperature motor concern.

The "design-basis" differential pressure calculations reviewed are as

follows:

CALCULATION

SYSTEM -

MOTOR OPERATED VALVES

1)

OSC-4374, R4 -----------

Main Steam (MS), MS

17,26,82,84

2)

OSC-4363, R5 -----------

MS-24,33,35,36,47,76,79

3)

OSC-4412, RO -----------

Purg (PR), PR-15, 19

4)

OSC-4416, R6 -----------

Low Pressure Service Water

(LPSW), LPSW-4, 5

5)

OSC-4564, RO -----------

LPSW-6, 15

6)

OSC-4502, RI -----------

LPSW-18, 21, 24

7)

OSC-4551, R3 -----------

LPSW-45

8)

OSC-4560, RO -----------

LPSW-137

9)

OSC-4553, R3 -----------

LPSW-139 (Unit 1)

10)

OSC-4536, R1 -----------

LPSW-565, 566

4

9CALCULATION

SYSTEM-MOTOR OPERATED VALVES

11)

OSC-4697, R2 -------------

High Pressure Injection (HP),

HP-3, 4, 20, 24, 25, 26, 27,

409, 410

12)

OSC-4676, R4 -------------

HP-398, 417, 426, 428

13)

OSC-4281, R4 -------------- Low Pressure Injection (LP),

LP-1, 2, 3, 14, 15, 16, 17,

18, 19, 20, 21, 22, 103, 104

14)

OSC-4542, R3 -------------- Building Spray (BS), BS-1, 2

15)

OSC-4784, RI------------

Component Cooling (CC), CC-3,

4, 5, 6, and 7

16)

OSC-4494, R2------------

Condensate Circulating Water

(CCW), CCW-1, 2, 3, 4, 5, 6,

7, 8, 10, 11, 12, 13, 90, 91,

93

17)

OSC-5628, RI -------------- CCW-268, 287

18)

OSC-4692, R2 -------------

CCW-269, 347

19)

OSC-4479, R3 -------------- Condensate (C), C-124, 152,

153, 156, 158, 391

20)

OSC-5692, RO------------

Core Flood (CF), CF-i, 2, 3,

4, 5, 6

21)

OSC-4385, R2 -------------- Feedwater (FDW), FDW-103, 104,

105, 107

022)

OSC-4431, R2 -------------- FDW-33, 36, 38, 42, 45, 47

23)

OSC-4643, R2 -------------

Reactor Coolant (RC), RC-3, 4,

5, 6

24)

OSC-4555, Ri -----------

igSpent Fuel (SF), SF-82, 97

During the Part 2 inspection, MOV LPSW-139 was identified as having a

small thrust margin. At that time the licensee indicated the actuator

would be replaced. The inspectors verified that the licensee had

replaced LPSW-139 using work order WO 95014138. In addition, the

inspectors reviewed the completed modification package, ID No.

TN/5/A/2972/AL1/01, "Replace Valve LPSW-139" dated December 3, 1995.

The inspectors concluded the licensee implemented appropriate corrective

action to increase the thrust (torque) margin of LPSW-139.

Concl usion

The inspectors concluded the licensee's satisfactory implementation of

the GL 89-10 recommendations for addressing the design-basis was

adequate for closure.

2.2

Motor Brakes

During the Part 2 inspection, the inspectors verified that Units 1 & 3

had been walked down and no motor brakes were installed on GL 89-10

MOVs.

The licensee indicated that a motor brake walkdown inspection was

planned during the October 1994 Unit 2 refueling outage. During this

16

inspection, the inspectors reviewed work order Nos. 94010077 and

5

94020444 to determine the results of the Unit 2 motor brake walkdown

inspection. No GL 89-10 MOVs in Unit 2 had motor brakes installed.

Conclusion

The inspectors concluded that no motor brakes are installed on GL 89-10

MOVs.

2.3

Scope Change

The inspectors examined the scope change since the Part 1 inspection.

The licensee reduced by 15 the number of valves in the scope of the

GL 89-10 Program.

VALVES REMOVED

JUSTIFICATION

1(2,3)-CS-5

Diaphragm Type

1(2,3)-AS-40

Converted to Manual

1(2,3)-MS-47

Converted to Manual

1(3)-CCW-90, 91

Removed Valves

1(3)-LPSW-137

Ball Type

Conclusion

The inspectors concluded the removal of 15 MOVs from the GL 89-10 scope

was justified.

2.4

Establishing MOV Settings

The inspectors reviewed the following thrust calculations to determine

and assess the licensee's general requirements for switch settings. The

following thrust calculations were reviewed:

1)

OSC-5675, Revision 0

GL 89-10 MOV Calculation For Unit 2

Gate And Globe Valves At Oconee

2)

OSC-5761, Revision 0

GL 89-10 MOV Calculation For Unit 2

Butterfly Valves

3)

OSC-5859, Revision 1

GL 89-10 MOV Calculation For

Butterfly Valves On The ECCW System

4)

OSC-5760, Revision 0

GL 89-10 MOV Calculation For Unit 1

Butterfly Valves At Oconee

5)

OSC-5599, Revision 1

GL 89-10 MOV Calculation For Unit 3

Gate And Globe Valves At Oconee

  • 6

6)

OSC-5762, Revision 0

GL 89-10 MOV Calculation For Unit 3

Butterfly Valves At Oconee

7)

OSC-5674, Revision 1

GL 89-10 MOV Calculation For Unit 1

Gate And Globe Valves At Oconee

The inspectors reviewed the thrust calculations and test packages for

each program MOV to verify the licensee had implemented the

recommendations in GL 89-10. In addition, the inspectors verified that

several findings identified during the Part 2 inspection were

satisfactorily resolved by the licensee. A fixed 15 percent thrust

margin was previously used to account for diagnostic equipment

uncertainty and torque switch repeatability. The current MOV setup and

calculations now properly account for VOTES diagnostic equipment

inaccuracies and incorporates Limitorque's published values for torque

switch repeatability. A fixed 15 percent margin was previously used for

load sensitive behavior (rate of loading). The method to determine this

margin has been revised to add 5.6 percent as a bias error and 26.4

percent as a random error. The random margin is combined with

diagnostic equipment uncertainty and torque switch repeatability using

the square root of the sum of the squares method. The approach using

this method was consistent with the load sensitive behavior measured on

the MOVs tested.

Conclusion

The inspectors concluded the licensee's satisfactory implementation of

GL 89-10 recommendations for addressing switch settings was adequate for

closure.

2.5

Design-Basis Capabilities

Conclusions

The licensee determined that several MOVs were marginal and established

plans to upgrade or replace those MOVs. The modifications to these

valves were commitments in Attachment 1 of licensee's letter, "Generic

Letter 89-10 Closure Audit Package" to the NRC. The licensee's closure

letter is discussed in Section 2.0 and the remaining MOV commitments are

also listed in Section 2.0.

The licensee typically assumed valve factors of 0.6 for gate valves and

1.1 for globe valves. The licensee supported these valve factors with

actual plant data, grouping of test data, or the application of the EPRI

MOV Performance Prediction Methodology. The licensee verified the

proper guide or seat area in predicting the thrust required to operate

globe valves.

For the 8-inch Posi-Seal butterfly valves, a licensee contractor

(Vectra) performed a similarity study to apply prototype test data from

Utah State University. Vectra provided several recommendations for

establishing the applicability of the prototype data to the Oconee

7

valves. The licensee had not documented its response to these

recommendations. This issue is categorized as an IFI 50-269,270,287/

95-25-01, "Response To Vectra Report-Butterfly Valves".

The licensee

evaluation of flow resistance, procedure improvement, and shaft

orientation will require further NRC review. Because the licensee's

response to inspector questions in this area revealed that the licensee

had considered the Vectra recommendations, the inspectors determined

that the staff's review of the licensee's GL 89-10 program can be closed

with this followup item.

For the Anchor/Darling double disk gate valves, the licensee set these

MOVs to accommodate a 0.6 valve factor. The licensee applied the EPRI

methodology for these valves and determined that they could meet the

thrust prediction for theoretical flow isolation but not for hard seat

contact. The licensee believed that its contractor (MPR Associates) had

assumed the more severe orientation of the valve disk than applicable at

Oconee. The inspectors determined that the licensee needs to resolve

the orientation question or determination whether these valves can meet

their performance requirements with possible leakage. This issue is

categorized as an Inspector Followup Item (IFI) 50-269,270,287/95-25-02,

"Anchor Darling Double Disc Gate Flow Cutoff".

Because the MOVs are set

to accommodate a reasonable valve factor for these type of valves, the

inspectors determined that the staff's review of the licensee's GL 89-10

program can be closed with this followup item.

The inspectors reviewed the licensee's application of similarity studies

conducted by Siemens for a group of Anchor/Darling double-disk gate

valves (approximately 1-inch in size) and a group of Borg-Warner

flexible wedge gate valves (4-inch and 6-inch) at Oconee. Because the

sizes of the grouped valves were similar, the inspectors did not

identify any concerns regarding the application of the similarity study

at Oconee.

For Kerotest globe valves, the licensee applied information from flow

loop testing of these valves in verifying the design-basis capability of

its similar valves. The inspectors did not identify any concerns

regarding the applicability of the flow loop data to the particular

valves at Oconee.

The licensee relied on an EPRI method to obtain a bounding rate-of

loading assumption (5.6 percent bias and 26.4 percent random).

The

inspectors consider the licensee's assumption to be supported by its

plant data.

The licensee had committed to perform certain MOV modifications in a

letter dated March 31, 1995. However, during this inspection the

licensee justified not replacing valve 1/2/3 CCW-287 based on its open

safety function (its close function had been eliminated) and not

replacing valves 2CCW-7 and 3CCW-93 based on a revised lower design

differential pressure. The inspectors considered these adjustments to

the licensee's commitments to be acceptable. The licensee stated its

8

S

intent to perform the remaining MOV modifications specified in the

March 31 letter.

The licensee determined that the diagnostic test data for 52 MOVs had

been outside the calibration range in the opening direction. The

licensee reevaluated these MOVs to verify their capability. The

inspectors considered 2LP-21 to be marginal.

However, there is no

safety concern since the licensee enters a "limiting condition of

operation" (LCO) whenever the valve is closed. Further, the licensee

plans to retest the MOV in April 1996 to verify margin.

The licensee is active in applying new technologies to improve the

performance of its MOVs. The licensee has conducted flow-loop testing

to provide information on MOV performance. The licensee has been

applying the EPRI methodology in some cases where plant test data was

not available. The licensee has been bench testing its motor actuators

to obtain detailed information on their performance capability. The

licensee has demonstrated strong technical expertise in providing

information to other licensees on MOV performance.

During the inspection the inspectors provided additional information for

consideration by the licensee. The licensee stated that this

information, discussed below, would be evaluated.

1)

-

The licensee applies linear extrapolation to its dynamic

test data. The licensee requires the test differential

pressure to be at least 50 percent of the design to perform

linear extrapolation.

-

Review of the EPRI guidance on extrapolation of test data

and the NRC safety evaluation for any adjustments to its

extrapolation technique.

2)

-

The licensee applied the EPRI methodology to verify the

design-basis capability of several MOVs in its GL 89-10

program. Review of the NRC safety evaluation (when issued)

on the EPRI methodology to determine whether any adjustments

to its capability determination are necessary.

3)

-

The licensee currently relies on a stem friction coefficient

of 0.2 in the justification for the design-basis capability

of its MOVs.

-

Justify use if a 0.15 stem friction coefficient is to be

assumed in its program in the future.

4)

-

For gate valves manufactured by Powell with inverted-guide.

design, the licensee applied the EPRI methodology in a best

possible effort to predict thrust requirements for these

valves. The inspectors considered the licensee's

determination of thrust requirements for these valves to

99

be adequate for closure of its review of the licensee's GL 89-10 program.

As part of the periodic verification program, confirm the

assumptions regarding these valves.

5)

-

For gate valves manufactured by Crane with non-stellite

seating material, the licensee applied the EPRI methodology

with an assumed friction coefficient for their seating

material.

The inspectors considered the licensee's

determination of thrust requirements for these valves to be

adequate for closure of its review of the licensee's GL 89

10 program.

As part of the periodic verification program, confirm the

assumptions regarding these valves.

6)

-

The licensee used a run efficiency in determining the output

capability of certain Limitorque MOVs when operating in the

closed direction.

-

Evaluate recent industry and research test information

concerning Limitorque actuator efficiency.

Conclusion

The inspectors concluded that the licensee's satisfactory implementation

of GL 89-10 recommendations for addressing design-basis capability was

adequate for closure.

2.6

Periodic Verification of MOV Capability

Recommended action "d" of Generic Letter (GL) 89-10 requested the

preparation or revision of procedures to ensure that adequate MOV switch

settings are determined and maintained throughout the life of the plant.

Section "j" of GL 89-10 recommends surveillance to confirm the adequacy

of the settings. The interval of the surveillance is to be based on the

safety importance of the MOV as well as its maintenance and performance

history, but was recommended not to exceed five years or three refueling

outages. Further, GL 89-10 recommended that the capability of the MOV

be verified if the MOV was replaced, modified, or overhauled to an

extent that the existing test results are not representative of the MOV.

Conclusion

The inspectors concluded that the licensee has an adequate program for

closure of the NRC staff review of GL 89-10 with respect to periodic

verification to ensure MOV capability. However, the NRC is preparing a

generic letter on the periodic verification of MOV design-basis

capability. Consequently, the inspectors did not evaluate the

4

licensee's long-term periodic verification plans. The NRC.will review

10

the licensee's MOV periodic verification program following issuance of

the new generic letter.

2.7

Post-Maintenance and Post-Modification Testing

The inspectors identified that the post-maintenance and post

modification test requirements for GL 89-10 MOVs were specified in Duke

Power NRC Generic Letter 89-10 Program Document, Section 5.10 and Figure

4, Post Maintenance Test Matrix. These documents listed the test

requirements and guidelines for maintenance and modification activities.

These activities were placed in three categories, Minor, Intermediate,

and Major. The "Minor" activities category include actuator PMs, motor

control center PMs, limit switch adjustment, limit stop adjustment for

gears, and replacement of certain seals and gaskets. Post-maintenance

testing for "Minor" activities required electrically stroking the MOV

twice. The "Intermediate" activities category included stem packing

replacement/adjustment. Post-maintenance testing for this activity

involves verification that the MOV running load has not increased beyond

acceptable limits, or engineering justification. The current practice

is to perform a new baseline test measuring stem thrust or torque to

quantify packing load changes. Engineering justification can be used

only in situations where available margin conservatively bounds packing

load changes due to adjustment. The "Major" category included

activities such as actuator removal and installation, actuator/gearbox

rebuild, torque switch adjustment, valve disassembly, stem/nut

replacement, spring pack adjustment, motor replacement, and upper

housing cover bolt tightening or gasket replacement. Post-maintenance

testing for major maintenance activities involves performing a new test

equivalent to the baseline diagnostic test.

Conclusion

The inspectors concluded that the licensee's satisfactory implementation

of the GL 89-10 recommendations for addressing post maintenance and post

modification testing was adequate for closure.

2.8

MOV Failures, Corrective Actions, and Trending

Recommended action "h" of GL 89-10 requested that licensees analyze and

justify each MOV failure and corrective action. The documentation

should include the results and history of each as-found deteriorated

condition, malfunction, test, inspection, analysis, repair, or

alteration. All documentation should be retained and reported in

accordance with plant requirements. GL 89-10 also recommended that the

material be periodically examined (every two years or after each

refueling outage after program implementation) as part of the monitoring

and feedback effort to.establish trends of MOV operability.

Equipment failure trending and analysis is specified in the Oconee

Nuclear Station Engineering Manual.

For MOVs the licensee combines the

information obtained from a number of sources. For instance, reports

11

generated quarterly which look at the equipment trends over a 12 month

period include:

-

Average Failure Frequency Report (AFFR)

-

Repeat Work Order Report

-

Unit Trip Report

-

Component Failure Analysis Report (CFAR)

The data base for these reports are the Nuclear Plant Reliability Data

System (NPRDS) and the Work Management System (WMS) which includes

equipment history and corrective maintenance work orders.

Two additional data bases important for MOV trending are:

-

Votes "Sensor" Test Report Analysis Guideline

(Trends diagnostic test results with previous test data)

-

Problem Investigation Process (PIP) reports

(Documents all MOV problems and associated corrective actions)

Since the Part 2 inspection, the licensee had generated a number of PIPs

related to valves in the GL 89-10 program. Of these, 31 PIPs were open

including 5 PIPs related to a potential for pressure locking and/or

thermal binding. The inspectors reviewed the issues identified in the

open PIPs and discussed with licensee engineers the determination of

operability and proposed corrective actions.

Conclusion

The inspectors concluded that the licensee has an adequate program for

identifying, tracking and reporting MOV problems. Review of the issues

identified in PIP reports indicated a thorough analysis, accurate

determination of operability and appropriate short term corrective

actions. Long term corrective actions were identified and considered

adequate for program closure.

2.9

Pressure Locking and Thermal Binding

The inspectors reviewed the licensee's actions taken to evaluate thermal

binding and pressure locking in accordance with recommendations of

GL 89-10 and the recently issued GL 95-07, "Pressure Locking and Thermal

Binding of Safety-Related Power-Operated Gates Valves". The inspectors

determined that the licensee was in the process of reviewing systems and

valves for pressure locking and thermal binding in accordance GL 95-07.

The inspectors reviewed seven problem investigation process (PIP)

reports in which the licensee had identified and documented short term

corrective actions for valves susceptible to pressure locking or thermal

binding. The inspectors did not identify any concerns with the PIPs.

12

In regards to GL 95-07, the licensee had completed its 90-day review.

The licensee stated that valves 2/3 LP103 and 104 had been declared

inoperable as a result of its review and that alternate paths were being

relied on to meet their safety function. The licensee had drilled holes

in the disk of these valves in Unit 1. The staff will evaluate the

licensee's response to GL 95-07 when the 180-day review package is

submitted.

Conclusions

The inspectors concluded that the licensee's satisfactory implementation

of the GL 89-10 recommendations for addressing pressure locking and

thermal binding was adequate for closure.

2.10 Quality Assurance Program Implementation

During the Part 2 inspection, the inspectors concluded that the licensee

had satisfactorily implemented the GL 89-10 recommendations for quality

assurance.

2.11 Walkdown

The inspectors conducted a walkdown of MOV Bench Testing Facility to

observe the use of the motor power monitor. The licensee demonstrated

all the functions and capabilities of the motor power monitor in

conjunction with the use of a torque test stand developed by Kalsi

Engineering. The inspector considered the licensee's bench testing of

actuators and use of the motor power monitor as an innovative approach

using advance technology. Several of the licensee's valve engineers are

pro-active in this testing area. The inspectors concluded the use of

this test facility and the advanced equipment was a strength in the

GL 89-10 program.

3.0

Followup of Previous Items (92701)

(Closed) Violation 50-269/94-15-01, Inadequate Procedure Preparation For

IST Testing. On June 21, 1994, during plant heat up, the 10 year IST

Pressure Test No. 11HN-169 was performed on a section of piping between

valves 1-LP-103 and 1-LP-104 using Work Request No. 94013014. Test

Procedure MP/0/A/1720/016 was used. Valve 1-LP-103 was damaged because

the test pressure and temperature exceeded valve set-up requirements.

The inspectors concluded the IST Test procedure was inadequate since it

did not address all parameters for conducting the test.

The inspector verified that the licensee revised IST Test Procedures

MP/O/A/1720/016 Revision 13 and MP/0/A/1720/010 Revision 26 to address

system parameters such as pressure to prevent damaging MOVs. In,

addition, the MOVs were listed to be reviewed prior to testing. The

inspectors concluded the licensee implemented appropriate corrective

action to prevent future occurrences. This violation was closed.

13

4.0

Exit Interview

The inspection scope and results were summarized on December 14, 1995,

with those persons indicated in paragraph 1. Although proprietary

information was reviewed, none is contained in this report. Dissenting

comments were not received from the licensee.

5.0

Acronyms and Intialisms

DBD

-

Design Basis Document

DP

-

Differential Pressure

EPRI

-

Electric Power Research Institute

GL

-

Generic Letter

IFI

-

Inspector Followup Item

INEL -

Idaho National Engineering Labratory

IST

-

Inservice Test

LSB

-

Load Sensitive Behavior

MOV

-

Motor Operated Valve

NRC

-

Nuclear Regulatory Commission

NRR

-

NRC Office of Nuclear Reactor Regulation

PIP

-

Problem Investigation Process Report

QA

-

Quality Assurance

TI

-

Temporary Instruction

WO

-

Work Order