ML15118A074

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/96-02,50-270/96-02 & 50-287/96-02 on 960108-25.No Violations Noted.Insp Conducted to Review Circumstances Re Spent Fuel Assembly Being Left Withdrawn from Unit 1/2 Fuel Rack from 951214-960108
ML15118A074
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 02/01/1996
From: Crlenjak R, Harmon P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML15118A073 List:
References
50-269-96-02, 50-269-96-2, 50-270-96-02, 50-270-96-2, NUDOCS 9602120130
Download: ML15118A074 (9)


See also: IR 05000269/1996002

Text

0

0

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

Report Nos.: 50-269/96-02, 50-270/96-02 and 50-287/96-02

Licensee:

Duke Power Company

422 South Church Street

Charlotte, NC 28242-0001

Docket Nos.:

50-269, 50-270 and 50-287

License Nos.: DPR-38, DPR-47 and DPR-55

Facility Name: Oconee Units 1, 2 and 3

Inspection Conducted: January 8-25, 1996

Inspectors:

i

F

/ , (

/y,

-fo P. E. Harmon, Senior Resident Inspector

Date Signed

P. G. H

rey, Resident Inspector

A p p r o v e d b y :

_

.1Crln_

_Dt

eS

e

VV

CrlenjAk, Chief0'Daeigd

Reactor Projects Branch 1

SUMMARY

Scope:

This special inspection was conducted to review the circumstances

surrounding a spent fuel assembly being inadvertently left

withdrawn from the Unit 1/2 spent fuel pool rack from December 14,

1995, until January 8, 1996.

Results:

An apparent violation was identified involving the inadequate

control over fuel assembly movement on December 14, 1995, which

resulted in a fuel assembly being left in the fuel handling mast

for over three weeks.

Enclosure 1

9602120130 960202

PDR ADOCK 05000269

PDR

REPORT DETAILS

Acronyms used in this report are defined in paragraph 4.0.

1.0

Persons Contacted

Licensee Employees

B. Peele, Station Manager

  • E. Burchfield, Regulatory Compliance Manager

D. Coyle, Systems Engineering Manager

  • J. Davis, Engineering Manager

T. Coutu, Operations Support Manager

  • W. Foster, Safety Assurance Manager
  • J. Hampton, Vice President, Oconee Site
  • D. Hubbard, Maintenance Superintendent

C. Little, Electrical Systems/Equipment Manager

J. Smith, Regulatory Compliance

G. Rothenberger, Operations Superintendent

  • R. Sweigart, Work Control Superintendent

Other licensee employees contacted included technicians,

operators, mechanics, security force members, and staff engineers.

2.0

December 14, 1995, Fuel Handling Event (71707, 62703 and 93702)

2.1

Background

Oconee Units 1 and 2 have a common SFP and Unit 3 has its own separate

SFP. Each SFP is a reinforced concrete pool located in its respective

Auxiliary Building. New and spent fuel assemblies are stored inside

individual storage cells within the pool storage racks. The fuel

storage racks rest on the bottom of the SFP. Spent fuel assemblies are

manipulated within the SFP via a fuel handling bridge equipped with a

fuel handling mechanism and fuel grapple. This bridge spans the SFP and

permits access to any one of the storage rack positions. A description

of the SFPs, the SFP Cooling Systems, and the Fuel Handling System is

described in Chapter 9 of the Oconee FSAR.

A SSF exists at ONS as a standby system for use under extreme emergency

conditions. It is provided as an alternate means to achieve and

maintain hot shutdown conditions for up to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> on all three units

following postulated fire, sabotage, or flooding events. Loss of all

other station power is assumed for each event. The SSF is designed in

part to maintain a minimum water level above the reactor core and

maintain RCP seal cooling. RCS inventory and seal cooling is provided

by the SSF RCMU pumps (one per unit). The Unit 1 and 2 RCMU pumps take

suction from the shared Unit 1/2 SFP. The Unit 3 RCMU pump takes

suction from the Unit 3 SFP. Each affected unit's RCMU pump draws 29

gpm from its corresponding SFP.

Enclosure 1

  • II2

SFP cooling is assumed to be lost at the start of an SSF event. Since

SFP cooling is not available, the temperature of the pool begins to

increase due to decay heat generated by the fuel contained in the pool.

The initial temperature of the pool, the mass of water contained in the

pool, and the rate of decay heat generation will determine how fast the

temperature of the water in the pool increases. The rate of decay heat

generation depends on the amount of fuel burn up that occurred prior to

removing the.fuel from the core, the amount of time the spent fuel has

been subcritical, and the amount of spent fuel contained in the pool.

In any case, SFP temperature will reach the boiling point well before 72

hours elapse. This boiling, in conjunction with the water being removed

by the RCMU pumps, decreases the SFP level.

The licensee does not take

any credit for water which might be returned to the SFP via the RCMU.

system recirculation line, the SSF letdown line, or condensation of

steam in the SFP room.

Based on the thermal hydraulic analysis of the SFP racks and NPSH

requirements of the RCMU pumps, the licensee has determined that the

water level in the SFP should not drop below one foot above the top of

the fuel assemblies in 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (reference preliminary calculation

OSC-619). NRC Inspection Report 50-269,270,287/94-31 identified

concerns with the failure of the licensee to fully account for the high

radiation levels (approximately 2,000,000 Roentgens per hour) near the

SFP when the water level drops to one foot above the top of the spent

fuel.

This issue is still under NRC review and is being tracked under

URI 50-269,270,287/94-31-06.

2.2

Fuel Handling Event and Related Issues

On the morning of December 14, 1995, a Reactor Engineer contacted the

Fuel Handling Supervisor to request support in an inspection of a fuel

assembly in the SFP. This inspection was part of an ongoing root cause

investigation into minor damage of a fuel assembly grid strap which had

occurred during the Unit 1 EOC 16 defueling evolution. The request was

initially denied due to the scheduled work load of the Maintenance fuel

handlers. Later that morning, due to a work delay, the fuel handling

supervisor informed the Reactor Engineer that Maintenance could support

the fuel inspection after all.

The Maintenance fuel handler and the

Reactor Engineer briefly discussed the fuel inspection, but no formal

pre-job brief was conducted. The fuel assembly inspection was

essentially viewed and treated as filler or non-scheduled work.

At approximately 1:00 p.m., on December 14, 1995, the fuel handler

raised fuel assembly-NJ05T8 into the refuel bridge mast while the

Reactor Engineer video taped it. At the Reactor Engineer's direction,

the fuel handler moved the fuel assembly to an area in the pool where

the video camera could more effectively view the assembly. This fuel

assembly was then returned to its proper location and lowered back into

the rack. The Reactor Engineer then decided to inspect another assembly

S-

for further comparison of minor scratches on the lower assembly plenum.

Enclosure 1

3

Assembly NJ06E7 was selected. The fuel handler traversed the bridge and

trolley to the SFP rack location for assembly NJ06E7, grappled the

assembly and raised it to within one foot of the top o- The mast. After

raising the assembly into the mast, the fuel handler turned off the

hydraulic pump, which mechanically locks the grapple in the engaged

position. Fuel handlers routinely turn off the hydraulic pump because

of previous experiences with hydraulic line leaks and failures. The

Reactor Engineer informed the fuel handler that his inspection was

complete. The fuel handler then left the bridge to assist the Reactor

Engineer in removing the video camera. The fuel handler and the Reactor

Engineer then reviewed the video tape of the fuel assembly. After

confirming that the video was adequate, the fuel handler returned to the

bridge and secured power to the bridge. Neither individual recognized

that the fuel assembly was still withdrawn in the mast. The activity

was performed without the use of a procedure and at the direction of the

Reactor Engineer, who was performing the video taping and acting as the

independent verifier and spotter.

At approximately 11:00 a.m., on January 8, 1996, the same individual

that had operated the SFP fuel handling bridge on December 14, 1995, was

preparing to use bridge again. The individual turned the power on and

noticed on the bridge control panel that the indicated weight on the

fuel lifting hook was what would be expected when a fuel assembly was

being lifted. He determined that a fuel assembly had been left in the

mast. At that time, he and another fuel handler decided that the bundle

should not be in the mast and lowered it into its position in the rack,

and then notified the fuel handling manager.

On January 8, 1996, at approximately 3:00 p.m., the resident inspectors

were notified of the event. The inspectors reviewed the circumstances

of the two separate fuel handling evolutions. Procedures

OP/O/A/1506/01, Fuel And Component Handling, and OP/O/A/1503/09,

Documentation Of Fuel Assemblies And/Or Component Shuffle Within A Spent

Fuel Pool, were inadequate in that specific steps were not defined to

accomplish raising, repositioning, inspection, and lowering the assembly

back into its proper location in the SFP during the evolution on

December 14, 1995. Therefore, this is being identified as Apparent

Violation 269,270,287/96-02-01, Inadequate Control Over Fuel Assembly

Movement.

At approximately 6:00 a.m., on January 9, the inspectors reviewed the

SPOC manager's log and noted that the event had not been documented and

the SPOC manager was not aware of the incident. The inspectors then

reviewed the control room operator's log and learned that the event had

not been logged, and the control room operators (ROs and SROs) were not

aware of the event.

On the evening of January 8, 1996, the licensee initiated a SEIT to

review the incident. The team exited on January 12, 1996, with several

Enclosure 1

4

preliminary findings and concerns. The SEIT concluded that there were

two principal root causes for the event:

  • The fuel bridge operator did not apply appropriate self-checking

measures during the December 14, 1995, fuel manipulation

  • Management had not clearly defined expectations for formality in

all aspects of the fuel handling process

Other SEIT findings included:

  • The event was improperly scheduled and planned
  • Clear lines of responsibility were not defined
  • Procedures were inadequate and were not followed
  • The pre-job briefing was inadequate
  • There was no written guidance for the evolution.

In addition, the team identified that the plant response to the event

was inadequate in that the assembly was lowered back into the fuel

storage rack without notification to supervision, plant management, or

the control room; notification to the NRC residents was not timely, and

the 10CFR 50.72 notification made on January 9, 1996, should have been

made earlier.

2.3

Corrective Actions

The licensee suspended all fuel handling activities until the evaluation

and recommendations from the SEIT have been formalized and corrective

actions implemented.

2.4

Recent History of Fuel Handling Errors

Under Enforcement Action 94-104 (dated August 4, 1994) the licensee was

cited for fuel handling activities when a fuel bundle was placed in the

wrong position in the reactor vessel on May 25, 1994. That citation

resulted in a civil penalty in the amount of $15,000.00 (fifteen

thousand dollars). It was the fourth citation in four years for failure

to maintain adequate control of fuel assemblies in the SFP and the

Reactor Vessel during core offload and reload activities. Also cited in

Enforcement Action 94-104 was a second violation involving the movement

of fuel assemblies to different locations within the reactor core

without a procedure.

The licensee's response to the second violation recognized that the

cause for that violation was in part due to an insufficient awareness

Enclosure 1

5

that ANY fuel movement required detailed instructions. However, the

corrective actions were limited to requiring procedures for the

placement of fuel irn the core.

2.5

Significance of the Event

The licensee evaluated an accident scenario involving the SSF where

water was supplied from the SFP. The evaluation concluded that pool

inventory could be depleted to where the thrice burned assembly

suspended in the mast, could be uncovered. The licensee evaluation also

concluded that after the assembly was uncovered, the 10 CFR, Part 100

limits could be exceeded at the site boundary. Due to this evaluation,

the licensee made a 10 CFR 50.72, 1-hour notification on January 9,

1996.

Subsequently, the licensee performed a more detailed evaluation and

determined that the 10 CFR, Part 100 limits would not have been

exceeded. The design basis event assumes that water in the SFP could be

lowered to within 1 foot above the top of the stored spent fuel.

Rough

calculations concluded that radiation levels in the SFP could reach

approximately 900,000 Roentgens per hour during the event. The licensee

has calculated that an increase of 4 percent in radiation levels above

the design basis would occur as a result of the suspended assembly being

out of the water when the borated water level was dropped to one foot

above the stored fuel.

The most recent licensee analysis also indicated

that the fuel clad of the specific fuel assembly involved in the event

would not be breached upon being uncovered. However, a different

assembly might in fact have experienced clad failure, which would result

in release of the fuel assembly gap activity.

3.0

Exit Interview

The inspection scope and findings were summarized on January 25, 1996,

with those persons indicated by an asterisk in paragraph 1. The

inspectors described the areas inspected and discussed in detail the

inspection results. A listing of inspection findings is provided.

Proprietary information is not contained in this report. Dissenting

comments were not received from the licensee.

Item Number

Status

Description and Reference

Apparent Violation

OPEN

Inadequate Control Over Fuel

269,270,287/96-02-01

Assembly Movement (paragraph 2.2).

4.0

Acronyms

EOC

End-Of-Cycle

FA

Fuel Assembly

FSAR

Final Safety Analysis Report

GPM

Gallons Per Minute

Enclosure 1

6

NPSH

Net Positive Suction Head

NI

Nuclear Instrument

OSC

Oconee Site Calculation

RCMU

Reactor Coolant Makeup

RCP

Reactor Coolant Pump

RCS

Reactor Coolant System

RO

Reactor Operator

SEIT

Significant Event Investigation Team

SPOC

Single Point Of Contact

SRO

Senior Reactor Operator

SFP

Spent Fuel Pool

SSF

Standby Shutdown Facility

URI

Unresolved Item

Enclosure 1

34386

Federal Register / Vol. 60. No. 126 / Friday, June 30, 1995 / Notices

factors in arriving at the appropriate

isnothold,thelicenseewillnormally

isamatterof publicrecordsuchasan

severity level will be dependent on the

be requested to provide a written

adjudicatory decision by the

circumstances of the violation.

r

an inspection report, if

Department of Labor. in addition. with

However, if a licensee refuses to correct

issued, as to the licensee's views on the

the approval of the Executive Director

a minor violation within a reasonable

apparent violations and their root

for Operations, conferences will not be

time such that it willfully continues, the causes and a description of planned or

open to the public wher good cause has

violation should be categorized at least

implemented corrective action.

been shown after balancing the benefit

at a Severity Level IV.

During the predecisional enforcement

of the public observation against the

D. ioltins

f Rpotin Reuiemul-conference, the licensee, vendor, or

potential impact on the agency's

D. Violations of Reporting Requirementsbe

given an

in a particular case.

The NRC expects licensees to provide

opportunity to provide information

As soon as it is determined that a

complete, accurate, and timely

consistent with the purpose of the

conference will be opento public

information and reports. Accordingly,

conference, including an explanation to

observation, the NRC will notify the

unless otherwise categorized in the

the NRC of the immediate corrective

licensee that the conference will be

Supplements, the severity level of a

actions (if any) that wer taken

open to public observation as part of the

violation involving the failure to make

following identification of the potential

agency's trial program Consistent with

a required report to the NRC will be

violation or nonconformance and the

the agency's policy on open meetings

based upon the significance of and the

longterm comprehensive actions that

"Staff Meetings Open to Public."

circumstances surrounding the matter

were taken or will be taken to prevent

published September 20,1994(59 FR

that should have been reported.

rerence. Licensees, vendors, or other

48340). the NRC intends to announce

However, the severity level of an

persos will be told when a meeting is

open conferences normally at least 10

untimely report, in contrast to no report, a predsional enforcement conference.

working days in advance of conferences

may be reduced depending on the

A predecisional enforcement

through (1) notices posted in the Public

circumstances surrounding the matter.

conference is a meeting between the

Document Room. (2) a toil-free

A licensee will not normally be cited for

NRC and the licensee. Conferences are

telephone recording at 800-952-674.

a failure to report a condition or event

normally held in the regional offices

and (3) a toll-free electronic bulletin

unless the licensee was actually aware

and ar not normally open to public

board at 800-452-0678. In addition, the

of the condition or event that it failed

observation. However, a trial program is

NRC will also issue a press relse and

to report. A licensee will, on the other

being conducted to opn approximately

notify appropriate State liaison officers

hand, normally be cited for a failure to

25 percent of all eligible conferences for

that a predecisional enforcement

report a condition or event if the

public observation. i.e., every fourth

conference has been scheduled end that

licensee knew of the information to be

eligible conference involving one of

It is open to public observation.

reported, but did not recognize that it

three categories of licensees (reactor,

The public attending open

was required to make a report.

hospital, and other materials licensees)

conferences under the trial

may

V. pedeisnnalEnfrceentwill be open to the public. Confernces

observe but not participate inth

V. Predecisional Enforcement

cneec.i

sntdta

h

ups

Coferenes

will not normally be open to the public

cneec.I

sntdta

h ups

f te fr

action being

of conducting open conferces under

Whenever the NRC has learned of the

contemplated:

the trial program is not to maximi

existence of a potential violation for

which escalated enforcement action

(1) Would be taken against an

public attendance, but rather to

whih ecaltedenorcmen acio

individual, or if the action, though not

determine whether providing the public

appears to be warranted, or r

ng

taken against an individual. turns

with opportunities to be informed of

nonconformance on the part of a

whether an individual has cmmitted

NRC activities is compatible with the

vendor, the NRC may provide an

doig

NRC's ability to exercise its regulatory

opotniyfor a predecisional

2

op -ortiuty

confe renc ithna

(2

fInves

inificant personnel

and safety responsibilities. Therefore.

enforcement conferencethe

NRC has requested

brs of the public will be allowed

licensee, vendor. or other person before

that the individual(s) involved be

access to the NRC regional offices to

taking enforcement action. The purpos

present at the conference

attend open enforcement confrencs In

of the conference is to obtain

(3) Is based on the findings of an NRC

ordance with the "Standard

information that will assist the NRC la

Office of Investi

reprt- or

operating Procedures For Providing

determining the appropriate -

-

(4) Involves

formation.

Security Support For NRC Hearings And

enforcement acon, such s: (1) A-

Privacy Act information, or information

Meetings, published November 1,1991

commn ndrsanin of facts. rookt

rceue

~monundrstadin of act. r t,1

whichb couldi be considered proprietarr'

(58 FR 55). Thesepodus

Baisses and

sed opportunities

addion con

es

not.

provide th visitors may

associated withiheapparent violations.

ormaly beN

'

lic 1f:

i

that sign

(2) a common

Of

(

-

n

i

ub

, etc., not larger than 8"

corrective action taken or planned, and

mlsdmlnistrations or

permitted. and that disruptive persons

(3) a common understanding of the

and the conference cannot be conducted

may be removed.

significance of issues and the need for

without disclosing the exposed

Members of the public at

g

lasting comprehensive corrective action.

individual's name; or

coferences will be reminded that (1

If the NRC concludes that it has

(6) The conference will be conducted

the apparent violations discussed at

sufficient information to make an

by telephone or the conference will be

predecisional enforcement conferences

informed enforcement decision, a

conducted at a relatively small

are subject to further review and may be

conference will not normally be held

licensee's facility.

subject to change prior to any resulting

unless the licensee requests it. However,

Notwithstanding meeting any of these

enforcement action and (2) the

an opportunity for a conference will

criteria, a conference may still be open

statements of views Or expressions Of

normally be provided before issuing an

if the conference involves issues related

opinion made by NRC employees at

order based on a violation of the rule on

to an ongoing adjudiatory proceeding

predecisional enforcement conferenceS,

Deliberate Misconduct or a civil penalty

with one or more intervenors or where

or the lac thereof, are not intended to

to an unlicensed person. If a conference

the evidentiary ba s for the conference

represent final eteriations or belie

NUREG-1600

8

Enclosure 2

Federal Register / Vol. 60, No. 126 / Friday, June 30, 1995 / Notices

34387

Persons attending open conferences will to be under oath. Normally, responses

management involvement in licensed

be provided an opportunity to submit

under oath will be required only in

activities and a decrease in protection of

written comments concerning the trial

connection with Severity Level I. U. or

the public health and safety.

program anonymously to the regional

III violations or orders.

office. These comments will be

The NRC uses the Notice of Violation

subsequeatly forwarded to the Director

as the usual method for formalizing the

The NRC imposes different levels of

of the Office of Enforcement for review

existence of a violation. Issuance of a

penalties for different severity level

and consideration.

Notice of Violation is normally the only

violations and different classes of

When needed to protect the public

enforcement action taken, except in

liconsees vendors and other persons.

health and safety or common defense

cases where the criteriafor issuance of

Tables IA and lB show the base civil

and security, escalated enforcement

civil penalties and orders, as set forth in

penalties for various reactor, fuel cycle.

action, such as the issuance of an

Sections VLB and VI.C. respectively, are materials and vendor programs. (Cvil

immediately effective order, will be

met. However, special circumstances

penalties issued to individuals ar

taken before the conference. In these

regarding the violation findings may

determined on a case-by-cas basi

The

cases, a conference may be held after the warrant discretion being exercised such

ructure of these tables generally takes

escalated enforcement action is taken.

that the NRC refrains from issuing a

into account the gravity of the violation

Notice of Violation. (See Section VI.B

consideration and the

VI. Efoment Actions

  • litigation of Enforcement Sanctions.") abattoayv

This section describes the

In addtion, licensees are not ordinarily

c

pi as a

oa

enforcement sanctions available to the

cited for violations resulting frmgreaternucea

material

NRC and specifies the conditions under

matters not within their control, such as

inventories and greter potential

which each may be used. The basic

equipment failures that were not

conences to the public and licensee

enforcement sanctions are Notices of

avoidable by reasonable licensee quality

empoees receive higher civil

Violation, civil penalties. and orders of

assurance measures or management

penalties. Regarding the secondary

various types. As discussed further in

controls. Generally, however, licensees

factor of ability of various classes of

Section VLD. related administrative

are held responsible for the acts of their

licensees to pay the civil penalties. it is

actions such as Notices of

employees. Accordingly, this policy

not the NRCs intention that the

Nonconformance. Notices of Deviation,

should not be construed to excuse

economic impact of a civil penalty be so

Confirmatory Action Letters. Letters of

personnel errors.

severe that It puts a licensee out of

Reprimand,' and Demands for

B

ii

eat

uies(res

ahrta ii

Infomation e used to supplement the

B. Civil Penaltybis

d rhe thn

i

enforcement program. In selecting the

A civil penalty is a monetary penalty

pente mise whene

ites

enforcement sanctions or administrative

that may be imposed for violation of (1)

or

termnate licensed aiviti

actions, the NRC will consider

certain specified licensing provisions of

o adely affct licensee aiity

enforcement actions taken by other

the Atomic Energy Act or

tely condct ofcensed activties

Federal or State regulatory bodies

supplementary NRC rules or orders; (2)

Te deterent ffect

of

tie

having concurrent jurisdiction, such as

any requirement for which a license

best

e wnth amnt

o he

in transportation matters. Usually.

may be revoked: or (3) reporting

penlti to

aaon iene

whenever a violation of NRC

requirements under section 206 of the

amilit o

p

ntiin

the

requirements of more than a minor

Energy Reorganization Act. Civil

aou of cii pales

relcnsee

concern is identified, enforcement

penalties are designed to deter future

fo

hom

the

ables

o

f the

action is taken. The nature and extent of

violations both by the involved licensee

ailiy t

he rvity of th

the enforcement action is intended to

as well as by other licensees conducting violan h

e

NR

der

a

reflect the seriousness of the violation

similar activities and to emphasize the

cay

ase

as

a

involved. For the vast majority of

need for licensees to identify violationsdbs

ray

fia

violations, a Notice of Violation or a

and take prompt comprehensivehli

ee

n m

onse

Notice of Nonconformance is the normal corrective action, .ship,

te

ill

ner

action.

Civil penalties em considered for

Paetan r

aotie o

f volationSeverity

Level m violations. In addition.

A. Notice of V1olatfoa

civil penalties will normally be assessed

civil penalty. Howeve, where a licensee

A Notice of Violation is a written

for Severity Ievel I and U violations and

notice setting forth one or more

knowing and conscious violations of the will normally be required to address

violations of a legally binding

reporting requirements of section 206 of

why it has

rescuos to safely

requirement. The Notice of Violation

the Energy Reorganization Act.

licensed

ctiie a

p

normally requires the recipient to

Civil penalties are used to encourage

provide a written statement describing

prompt identification and prompt and

2 Civil Pealty

ummt

(1) the reasons for the violation or, if

comprehensive correction of violations.

contested, the basis for disputing the

to emphasize compliance in a manner

Inan effort to

violation: (2) corrective steps that have

that deters future violations, and to

ia

been taken and the results achieved; (3) serve to focus licensees' attention on

requirmentsand(2)

prm

corrective steps that will be taken to

violations of significant regulatory

self-Identification of problems and root

prevent recurrence: and (4) the date

concern.

causes and prompt and comprehensive

when full compliance will be achieved.

Although management involvement,

correction ofviolatios, the NRC

The NRC may waive all or portions of

direct or indirect. in a violation may

reviews each proposed civil penalty on

a written response to the extent relevant

lead to an increase in the civil penalty,

itsownmeritsand.after

informaton as aldy been provided

the lack of management involvement

relevant circumstances,

ad

to the NRC in writing or documented in

may not be used to mitigate a civil

basecivl penalties

an NRC inspection report. The NRC may palty. Allowing mitigation in the

and lB for severity Level!. U, and M

require responses to Notices of Violation

lrcae

could encourage the l

of

violations as described below.

9

NUREG-1600

Enclosure 2