Correction to Amendment Nos 293 and 180 Regarding Extension of Containment Leakage Test Frequency
ML15112B087
Person / Time
Site: Beaver Valley
Issue date: 04/30/2015
From: Taylor Lamb
Plant Licensing Branch 1
To: Emily Larson
FirstEnergy Nuclear Operating Co
Lamb T, NRR/DORL/LPLI-2, 415-7128
References
TAC MF3985, TAC MF3986
Download: ML15112B087 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 30, 2015 Mr. Eric A. Larson, Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077

SUBJECT:

BEAVER VALLEY POWER STATION, UNIT NOS. 1AND2-CORRECTION TO AMENDMENT NOS. 293 AND 180 REGARDING EXTENSION OF CONTAINMENT LEAKAGE TEST FREQUENCY {TAC NOS. MF3985 AND MF3986)

Dear Mr. Larson:

On April 8, 2015, the U.S. Nuclear Regulatory Commission (NRG) issued Amendment Nos. 293 and 1801 to Renewed Facility Operating License Nos. DPR-66 and NPF-73 for the Beaver Valley Power Station (BVPS), Unit Nos. 1 and 2, in response to your application dated April 16, 2014, as supplemented by letters dated November 4, 2014, and March 23, 2015. The amendments modified the Technical Specification requirements for containment leakage test frequency.

On April 15, 2015, the FirstEnergy Nuclear Operating Company staff notified the NRG staff that one of the safety evaluation pages for BVPS Amendment Nos. 293 and 180 contained typographical errors. Specifically, on page 7 of the safety evaluation, two blocks within Table 4 contain repeated data. The corrected page is enclosed.

Please replace page 7 of the safety evaluation with the enclosed page. The NRG staff regrets any inconvenience this may have caused.

If you have any questions, please contact me at (301) 415-7128.

Sincerely, Taylf;(~oject Plant Licensing Branch 1-2 Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosure:

Safety Evaluation page 7 cc w/encls: Distribution via ListServ

' Agencywide Documents Access and Management System Accession No. ML15078A058.

Table 3: BVPS-1 Historical Type Band Type C Leak Rate Results Refueling As-Found Min Percentage of As-Left Max Percentage of Outage Path 0.6 La Path 0.6 La 1R15 Spring 454.47 SCFD 11.6% 1,409.58 SCFD 35.9%

2003 1R16 Fall 2004 543.81 SCFD 13.8% 1,074.90 SCFD 27.4%

1R17 Spring 1,305. 76 SCFD 33.2% 1,560.95 SCFD 37.7%

2006 1R18 Fall 2007 853.52 SCFD 20.7% 2, 180.47 SCFD 52.8%

1R19 Spring 581.92 SCFD 14.1% 1,330.50 SCFD 32.2%

2009 1R20 Fall 2010 858.60 SCFD 21.0% 1,563.58 SCFD 38.2%

1R21 Spring 818.46 SCFD 20.0% 1,879.23 SCFD 45.9%

2012 1R22 Fall 2013 1,007.97 SCFD 24.6% 1,680.68 SCFD 41.0%

SCFD = Standard Cubic Feet per Day The limit for leakage is 0.6 La for both the as-found minimum pathway leak rate and the as-left maximum pathway leak rate. For BVPS-1, the average as-found minimum pathway leak rate is 19.9 percent of 0.6 La and high of 33.2 percent. Similarly, the average and high as-left maximum pathway leak rate was 38.9 percent and 52.8 percent, respectively.

Table 4: BVPS-2 Historical Type B and Type C Leak Rate Results Refueling As-Found Min Percentage of As-Left Max Percentage of Outage Path 0.6 La Path 0.6 La 2R10 Fall 2003 689.08 SCFD 16.6% 1,318.30 SCFD 31.7%

2R11 Spring 2,706.1 SCFD 65.0% 1,374.06 SCFD 33.0%

2005 2R12 Fall 2006 966.01 SCFD 23.2% 1,742.53 SCFD 41.0%

2R13 Spring 664.99 SCFD 15.8% 1,308.06 SCFD 31.0%

2008 2R14 Fall 2009 814.81 SCFD 19.3% 1,173.47 SCFD 27.8%

2R15 Spring 522.17 SCFD 12.4% 1,046.45 SCFD 24.8%

2011 2R16 Fall 2012 620.00 SCFD 14.7% 1,264.61 SCFD 30.0%

SCFD = Standard Cubic Feet per Day The limit for leakage is 0.6 La for both the as-found minimum pathway leak rate and the as-left maximum pathway leak rate. For BVPS-2 the average as-found minimum pathway leak rate is 23.9 percent of 0.6 La and high of 65.0 percent. Similarly, the average and high as-left maximum pathway leak rate was 31.3 percent and 41.0 percent, respectively.

ML15112B087 *via e-mail OFFICE LPL 1-2/PM LPL 1-2/LA LPL 1-2BC LPL 1-2/PM NAME TLamb ABaxter* DBroaddus TLamb DATE 4/29/15 04/29/15 4/30/15 4/30/15