|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML15113A7671999-10-27027 October 1999 Informs That NRC Will Not Be Able to Issue Final Safety Evaluation for BAW-2248 Until mid-Nov Because of Scheduler Conflicts & Workload Priorities ML15261A2421999-10-13013 October 1999 Informs That on 990930,staff Completed mid-cycle PPR of Oconee Nuclear Station.No New Areas That Warranted More than Core Insp Program Over Next Five Months Identified. Historical Listing of Plant Issues Encl ML15112A7851999-10-0808 October 1999 Provides NRC Staff Plan for Resolving Open Item 2.1.3.1-1 of SER Re License Renewal of Plant,Units 1,2 & 3 ML15112A7741999-10-0505 October 1999 Requests Addl Info Re Aging Effects of Insulated Cables & Connections for Plant,Based on Insp Findings Noted in Insp Repts 50-269/99-12,50-270/99-12 & 50-287/99-12 and License Renewal Application ML15113A7511999-09-23023 September 1999 Concludes That All Info Requested by GL 98-01 & Suppl 1 Re Y2K Readiness of Computers at NPPs Provided by Util & GL 98-01 Considered Closed for Ons,Units 1,2 & 3 ML15261A4221999-09-21021 September 1999 Forwards Insp Repts 50-269/99-12,50-270/99-12 & 50-287/99-12 on 990602-0730.No Violations Noted.Insp Revealed That,In Most Cases,Existing Aging Mgt Programs,Implemented as Described in Licensee Application ML15113A7521999-09-21021 September 1999 Informs That Util 980326 Response to GL 97-06, Degradation of Steam Generator Internals Acceptable ML15112A7661999-09-20020 September 1999 Forwards SE Accepting Relief Request for Revision 25 of Pump & Valve Inservice Testing Program,Third 10-yr Interval for Plant ML15261A2411999-09-17017 September 1999 Confirms 990916 Telcon Between L Nicholson of Licensee Staff & R Carroll of NRC Re Mgt Meeting to Be Conducted on 991006 in Atlanta,Ga to Discuss Licensee Status of Ongoing Improvement Initiatives at Oconee Nuclear Station ML15112A7521999-09-10010 September 1999 Forwards SE Accepting Licensee 990806 Request for Relief to Use Alternative Rules of ASME B&PV Code on Certain Weld Matls in Replacement SGs Being Manufactured for Plant ML15261A4181999-09-10010 September 1999 Forwards Insp Repts 50-269/99-05,50-270/99-05 & 50-287/99-05 on 990704-0814.Ten Violations of NRC Requirements Identified & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML15113A7481999-09-10010 September 1999 Informs That Postponing Implementation of New Conditions Imposed by RG 1.147,Rev 12,acceptable Since Evaluation on Original Relief Based on Implementing Code Case for Duration of Insp Interval & That 990522 Request Valid ML15112A7611999-09-0909 September 1999 Forwards Safety Evaluation of Unresolved Safety Issue A-46 Program Implementation,Including Plant Hydro Station & Switchyard ML15261A2391999-09-0707 September 1999 Discusses 990825 Meeting in Atlanta,Ga Re Results of Recent Duke Power Co Fire Endurance Testing of Penetration Seals. List of Attendees & Presentation Handouts Encl ML15261A2371999-09-0101 September 1999 Submits Traning Manager Conference Meeting Summary of Meeting Conducted on 990812-13 on Recent Changes to Operator Licensing Program.List of Attendees & Matl Used in Presentation Enclosed ML15113A7471999-08-31031 August 1999 Responds to Providing Info on EOP Licensing Basis for Plant Requested by NRC to Base Planned NRC EOP Insp on This Info.Research Completed Into Licensing Basis of EOP & Synopsis of Basis for NRC Position Re Matter Encl ML15112A7411999-08-30030 August 1999 Forwards Request for Addl Info Re Util 990727 Requested Amend to Oconee Nuclear Station,Units 1,2 & 3 Tss.Amend Would Incorporate Keowee Hydro Unit Voltage & Frequency Protection Mod Surveillance Requirements ML15261A2711999-08-11011 August 1999 Discusses 990730 Open Meeting Conducted at Region II Request Re Continuing & Planned Engineering Activites.List of Meeting Attendees & Copy of Presentation Handout Encl ML20211B7881999-08-10010 August 1999 Transmits Summary of Two Meetings with Risk-Informed TS Task Force in Rockville,Md on 990514 & 0714 ML15261A2721999-08-0909 August 1999 Confirms 990803 Telcon Re Mgt Meeting to Be Conducted on 990825 to Discuss Results of Recent DPC Fire Endurance Testing of Penetration Seals ML16134A5591999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 ML15113A7311999-08-0202 August 1999 Forwards SE Accepting Licensee 60-day Responses to GL 96-05, Periodic Verification of Design-Bases Capability of Safety-Related Movs, Issued on 960918 ML15261A4151999-07-30030 July 1999 Forwards Insp Repts 50-269/99-04,05-270/99-04 & 50-287/99-04 on 990523-0703.Four Violations of NRC Requirements Occurred & Being Treated as Ncvs,Consistent with App C of Enforcement Policy ML20209H6921999-07-15015 July 1999 Forwards Comments on Preliminary Accident Sequence Precursor Analysis Provided in NRC Re Operational Condition Reported in LER 269/1998-04 ML15261A2701999-07-14014 July 1999 Confirms Telcon Between Je Burchfield & Re Carroll on 990708 Re Mgt Meeting Scheduled 990730 in Atlanta Ga.Purpose of Meeting to Discuss Status of Open EFW Insp Items & Engineering Initiatives ML15113A7151999-07-13013 July 1999 Forwards Audit Rept on Y2K Contingency Planning Program for Plant Conducted on 990608-09,as follow-up to GL 98-01 ML15261A2681999-07-0202 July 1999 Confirms 990701 Telcon with L Nicholson Concerning Emergency Operating Procedures Meeting.Informs That Meeting Has Been Scheduled for 990722 ML15113A7101999-07-0101 July 1999 Forwards SE Granting Third 10-yr Interval ISI Program Plan Request for Relief 98-03.Relief Would Allow Credit to Be Taken by Plant for Limited Ultrasonic Exams on Specific Pressurizer Sensing nozzle-to-vessel Welds ML15254A1711999-06-30030 June 1999 Forwards Biological Assessment to Evaluate Whether Proposed Renewal of Oconee Nuclear Station,Units 1,2 & 3 Operating Licenses for Period of Addl 20 Years Would Have Adverse Effects on Listed Species ML15261A2671999-06-28028 June 1999 Discusses 990621 Meeting at Oconee Facility Re Results of Most Recent Periodic Plant Ppr.List of Attendees Encl ML15113A7071999-06-24024 June 1999 Discusses GL 92-001,Rev 1, Suppl 1, Reactor Vessel Structural Integrity ML15112A5111999-06-23023 June 1999 Refers to Oconee License Renewal SER Sent on 990616.Informs That Number of Copies Were Missing Pages 3-173 & 3-185. Forwards New Pages 3-173 Through 3-186 That Should Replace Existing Pages 3-174 Through 3-186 IR 05000269/19990031999-06-17017 June 1999 Forwards Insp Repts 50-269/99-03,50-270/99-03 & 50-287/99-03.Violations Being Treated as Noncited Violations ML15112A5001999-06-16016 June 1999 Forwards SER Re Licensee 980706 Application to NRC for Renewal of Oconee Nuclear Station,Units 1,2 & 3 Operating License for Addl 20 Years.Open Items Must Be Resolved Before NRC Can Make Final Determination on Application ML15261A2651999-06-15015 June 1999 Discusses 990526 Meeting Re Results of 1st Oconee License Renewal Insp.Forwards List of Attendees & Presentation Slide ML20195H1681999-06-10010 June 1999 Forwards Copy of Preliminary ASP Analysis of Operational Condition Discovered at Ons,Units 1,2 & 3 on 980212 & Reported in LER 269/98-004,for Review & Comment ML15112A4961999-06-0808 June 1999 Forwards SE of TR DPC-NE-2005P, Use of BWU-Z Critical Heat Flux Correlation for Mark-B11 Fuel. Rept Acceptable ML15261A2631999-06-0202 June 1999 Provides NRC Decision on Licensee 980604 Request for Reconsideration of Violation B of NOV Issued on 980504 Re Timeliness in Reporting Design Basis Events or Conditions at Plant Facility ML15261A2641999-06-0202 June 1999 Informs That Meeting Re Performance of Oconee Nuclear Station Will Be Held on 990621 ML15112A4861999-05-25025 May 1999 Forwards SER Accepting Rev 1 to Topical Rept DPC-NE-3005-P, UFSAR Chapter 15 Transient Analysis Methodology Submitted by Ltr ML15261A4061999-05-24024 May 1999 Forwards Insp Repts 50-269/99-11,50-270/99-11 & 50-287/99-11 on 990426-30.No Violations Noted.Scoping & Screening Portion of License Renewal Activities Were Conducted as Described in License Renewal Application ML15112A4821999-05-21021 May 1999 Discusses Request That Topical Rept DPC-NE-3005-P,Rev 1, UFSAR Chapter 15 Transient Analysis Methodology, Be Withheld from Public Disclosure.Determined Info to Be Proprietary & Will Be Withheld from Public Disclosure ML20207C0321999-05-18018 May 1999 Forwards Fifth Rept Which Covers Month of Apr 1999. Commission Approved Transfer of TMI-1 Operating License from Gpu to Amergen & Transfer of Operating License for Pilgrim Station from Beco to Entergy Nuclear Generating Co ML15253A5091999-05-18018 May 1999 Submits NRR mgt-approved Survey Re Hydrogen Storage at Operating Nuclear Plants.Requests That Project Managers Contact Licensees to Conduct Listed Survey & That Rept Be Submitted by Close of Business on 990528 ML15261A2601999-05-17017 May 1999 Confirms 990510 Telcon with E Burchfield Concerning Public Meeting Scheduled for 990629.Purpose of Meeting to Discuss Results of NRC Most Recent PPR of Plant ML15261A2591999-05-12012 May 1999 Discusses 990421 Meeting Conducted by NRC to Discuss Analysis Methodology Supporting Plant License Renewal Application.List of Meeting Attendees & Presentation Handouts Encl ML15113A6811999-05-11011 May 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization, Div of Licensing Project Mgt Created.Rl Emch Section Chief for Oconee.Reorganization Chart Encl ML15261A2611999-05-10010 May 1999 Responds to from Util to NRC Re Upcoming NRC Insp of Emergency Operating Procedures at Oconee Nuclear Station & Util Request That NRC Concur That Planned Insp Will Be Based on Oconee Licensing Basis ML15261A2551999-05-10010 May 1999 Confirms Telcon Between Je Burchfield & C Julian Re Meeting to Be Conducted on 990526 for NRC to Present Results of NRC First Inspection of Oconee License Renewal Program Conducted 990426 ML15217A2091999-05-10010 May 1999 Discusses Determination of Scope of Transmission Lines Impact Assessment for License Renewal.Impacts Resulting from Maint Activities Associated with 330 Miles of Transmission Lines Cited in Original Fes in Suppls to GEIS 1999-09-09
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML15113A7671999-10-27027 October 1999 Informs That NRC Will Not Be Able to Issue Final Safety Evaluation for BAW-2248 Until mid-Nov Because of Scheduler Conflicts & Workload Priorities ML15261A2421999-10-13013 October 1999 Informs That on 990930,staff Completed mid-cycle PPR of Oconee Nuclear Station.No New Areas That Warranted More than Core Insp Program Over Next Five Months Identified. Historical Listing of Plant Issues Encl ML15112A7851999-10-0808 October 1999 Provides NRC Staff Plan for Resolving Open Item 2.1.3.1-1 of SER Re License Renewal of Plant,Units 1,2 & 3 ML15112A7741999-10-0505 October 1999 Requests Addl Info Re Aging Effects of Insulated Cables & Connections for Plant,Based on Insp Findings Noted in Insp Repts 50-269/99-12,50-270/99-12 & 50-287/99-12 and License Renewal Application ML15113A7511999-09-23023 September 1999 Concludes That All Info Requested by GL 98-01 & Suppl 1 Re Y2K Readiness of Computers at NPPs Provided by Util & GL 98-01 Considered Closed for Ons,Units 1,2 & 3 ML15261A4221999-09-21021 September 1999 Forwards Insp Repts 50-269/99-12,50-270/99-12 & 50-287/99-12 on 990602-0730.No Violations Noted.Insp Revealed That,In Most Cases,Existing Aging Mgt Programs,Implemented as Described in Licensee Application ML15113A7521999-09-21021 September 1999 Informs That Util 980326 Response to GL 97-06, Degradation of Steam Generator Internals Acceptable ML15112A7661999-09-20020 September 1999 Forwards SE Accepting Relief Request for Revision 25 of Pump & Valve Inservice Testing Program,Third 10-yr Interval for Plant ML15261A2411999-09-17017 September 1999 Confirms 990916 Telcon Between L Nicholson of Licensee Staff & R Carroll of NRC Re Mgt Meeting to Be Conducted on 991006 in Atlanta,Ga to Discuss Licensee Status of Ongoing Improvement Initiatives at Oconee Nuclear Station ML15261A4181999-09-10010 September 1999 Forwards Insp Repts 50-269/99-05,50-270/99-05 & 50-287/99-05 on 990704-0814.Ten Violations of NRC Requirements Identified & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML15113A7481999-09-10010 September 1999 Informs That Postponing Implementation of New Conditions Imposed by RG 1.147,Rev 12,acceptable Since Evaluation on Original Relief Based on Implementing Code Case for Duration of Insp Interval & That 990522 Request Valid ML15112A7521999-09-10010 September 1999 Forwards SE Accepting Licensee 990806 Request for Relief to Use Alternative Rules of ASME B&PV Code on Certain Weld Matls in Replacement SGs Being Manufactured for Plant ML15112A7611999-09-0909 September 1999 Forwards Safety Evaluation of Unresolved Safety Issue A-46 Program Implementation,Including Plant Hydro Station & Switchyard ML15261A2391999-09-0707 September 1999 Discusses 990825 Meeting in Atlanta,Ga Re Results of Recent Duke Power Co Fire Endurance Testing of Penetration Seals. List of Attendees & Presentation Handouts Encl ML15261A2371999-09-0101 September 1999 Submits Traning Manager Conference Meeting Summary of Meeting Conducted on 990812-13 on Recent Changes to Operator Licensing Program.List of Attendees & Matl Used in Presentation Enclosed ML15113A7471999-08-31031 August 1999 Responds to Providing Info on EOP Licensing Basis for Plant Requested by NRC to Base Planned NRC EOP Insp on This Info.Research Completed Into Licensing Basis of EOP & Synopsis of Basis for NRC Position Re Matter Encl ML15112A7411999-08-30030 August 1999 Forwards Request for Addl Info Re Util 990727 Requested Amend to Oconee Nuclear Station,Units 1,2 & 3 Tss.Amend Would Incorporate Keowee Hydro Unit Voltage & Frequency Protection Mod Surveillance Requirements ML15261A2711999-08-11011 August 1999 Discusses 990730 Open Meeting Conducted at Region II Request Re Continuing & Planned Engineering Activites.List of Meeting Attendees & Copy of Presentation Handout Encl ML20211B7881999-08-10010 August 1999 Transmits Summary of Two Meetings with Risk-Informed TS Task Force in Rockville,Md on 990514 & 0714 ML15261A2721999-08-0909 August 1999 Confirms 990803 Telcon Re Mgt Meeting to Be Conducted on 990825 to Discuss Results of Recent DPC Fire Endurance Testing of Penetration Seals ML16134A5591999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 ML15113A7311999-08-0202 August 1999 Forwards SE Accepting Licensee 60-day Responses to GL 96-05, Periodic Verification of Design-Bases Capability of Safety-Related Movs, Issued on 960918 ML15261A4151999-07-30030 July 1999 Forwards Insp Repts 50-269/99-04,05-270/99-04 & 50-287/99-04 on 990523-0703.Four Violations of NRC Requirements Occurred & Being Treated as Ncvs,Consistent with App C of Enforcement Policy ML15261A2701999-07-14014 July 1999 Confirms Telcon Between Je Burchfield & Re Carroll on 990708 Re Mgt Meeting Scheduled 990730 in Atlanta Ga.Purpose of Meeting to Discuss Status of Open EFW Insp Items & Engineering Initiatives ML15113A7151999-07-13013 July 1999 Forwards Audit Rept on Y2K Contingency Planning Program for Plant Conducted on 990608-09,as follow-up to GL 98-01 ML15261A2681999-07-0202 July 1999 Confirms 990701 Telcon with L Nicholson Concerning Emergency Operating Procedures Meeting.Informs That Meeting Has Been Scheduled for 990722 ML15113A7101999-07-0101 July 1999 Forwards SE Granting Third 10-yr Interval ISI Program Plan Request for Relief 98-03.Relief Would Allow Credit to Be Taken by Plant for Limited Ultrasonic Exams on Specific Pressurizer Sensing nozzle-to-vessel Welds ML15254A1711999-06-30030 June 1999 Forwards Biological Assessment to Evaluate Whether Proposed Renewal of Oconee Nuclear Station,Units 1,2 & 3 Operating Licenses for Period of Addl 20 Years Would Have Adverse Effects on Listed Species ML15261A2671999-06-28028 June 1999 Discusses 990621 Meeting at Oconee Facility Re Results of Most Recent Periodic Plant Ppr.List of Attendees Encl ML15113A7071999-06-24024 June 1999 Discusses GL 92-001,Rev 1, Suppl 1, Reactor Vessel Structural Integrity ML15112A5111999-06-23023 June 1999 Refers to Oconee License Renewal SER Sent on 990616.Informs That Number of Copies Were Missing Pages 3-173 & 3-185. Forwards New Pages 3-173 Through 3-186 That Should Replace Existing Pages 3-174 Through 3-186 IR 05000269/19990031999-06-17017 June 1999 Forwards Insp Repts 50-269/99-03,50-270/99-03 & 50-287/99-03.Violations Being Treated as Noncited Violations ML15112A5001999-06-16016 June 1999 Forwards SER Re Licensee 980706 Application to NRC for Renewal of Oconee Nuclear Station,Units 1,2 & 3 Operating License for Addl 20 Years.Open Items Must Be Resolved Before NRC Can Make Final Determination on Application ML15261A2651999-06-15015 June 1999 Discusses 990526 Meeting Re Results of 1st Oconee License Renewal Insp.Forwards List of Attendees & Presentation Slide ML20195H1681999-06-10010 June 1999 Forwards Copy of Preliminary ASP Analysis of Operational Condition Discovered at Ons,Units 1,2 & 3 on 980212 & Reported in LER 269/98-004,for Review & Comment ML15112A4961999-06-0808 June 1999 Forwards SE of TR DPC-NE-2005P, Use of BWU-Z Critical Heat Flux Correlation for Mark-B11 Fuel. Rept Acceptable ML15261A2641999-06-0202 June 1999 Informs That Meeting Re Performance of Oconee Nuclear Station Will Be Held on 990621 ML15261A2631999-06-0202 June 1999 Provides NRC Decision on Licensee 980604 Request for Reconsideration of Violation B of NOV Issued on 980504 Re Timeliness in Reporting Design Basis Events or Conditions at Plant Facility ML15112A4861999-05-25025 May 1999 Forwards SER Accepting Rev 1 to Topical Rept DPC-NE-3005-P, UFSAR Chapter 15 Transient Analysis Methodology Submitted by Ltr ML15261A4061999-05-24024 May 1999 Forwards Insp Repts 50-269/99-11,50-270/99-11 & 50-287/99-11 on 990426-30.No Violations Noted.Scoping & Screening Portion of License Renewal Activities Were Conducted as Described in License Renewal Application ML15112A4821999-05-21021 May 1999 Discusses Request That Topical Rept DPC-NE-3005-P,Rev 1, UFSAR Chapter 15 Transient Analysis Methodology, Be Withheld from Public Disclosure.Determined Info to Be Proprietary & Will Be Withheld from Public Disclosure ML20207C0321999-05-18018 May 1999 Forwards Fifth Rept Which Covers Month of Apr 1999. Commission Approved Transfer of TMI-1 Operating License from Gpu to Amergen & Transfer of Operating License for Pilgrim Station from Beco to Entergy Nuclear Generating Co ML15253A5091999-05-18018 May 1999 Submits NRR mgt-approved Survey Re Hydrogen Storage at Operating Nuclear Plants.Requests That Project Managers Contact Licensees to Conduct Listed Survey & That Rept Be Submitted by Close of Business on 990528 ML15261A2601999-05-17017 May 1999 Confirms 990510 Telcon with E Burchfield Concerning Public Meeting Scheduled for 990629.Purpose of Meeting to Discuss Results of NRC Most Recent PPR of Plant ML15261A2591999-05-12012 May 1999 Discusses 990421 Meeting Conducted by NRC to Discuss Analysis Methodology Supporting Plant License Renewal Application.List of Meeting Attendees & Presentation Handouts Encl ML15113A6811999-05-11011 May 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization, Div of Licensing Project Mgt Created.Rl Emch Section Chief for Oconee.Reorganization Chart Encl ML15261A2611999-05-10010 May 1999 Responds to from Util to NRC Re Upcoming NRC Insp of Emergency Operating Procedures at Oconee Nuclear Station & Util Request That NRC Concur That Planned Insp Will Be Based on Oconee Licensing Basis ML15217A2091999-05-10010 May 1999 Discusses Determination of Scope of Transmission Lines Impact Assessment for License Renewal.Impacts Resulting from Maint Activities Associated with 330 Miles of Transmission Lines Cited in Original Fes in Suppls to GEIS ML15261A2551999-05-10010 May 1999 Confirms Telcon Between Je Burchfield & C Julian Re Meeting to Be Conducted on 990526 for NRC to Present Results of NRC First Inspection of Oconee License Renewal Program Conducted 990426 ML15261A4031999-05-0505 May 1999 Forwards Insp Repts 50-269/99-02,50-270/99-02 & 50-287/99-02 on 990228-0410.Five Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy 1999-09-09
[Table view] |
See also: IR 05000269/1999012
Text
oA
UNITED STATES
0
NUCLEAR REGULATORY COMMISSION
WASHINGTON, D.C. 20555-0001
October 5, 1999
Mr. William R. McCollum, Jr.
Vice President, Oconee Nuclear Site
Duke Energy Corporation (Duke)
P. 0. Box 1439
Seneca, SC 29679
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION RELATED TO AGING EFFECTS
OF INSULATED CABLES AND CONNECTIONS FOR THE OCONEE
NUCLEAR STATION, UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION
(LRA)
Dear Mr. McCollum:
The Nuclear Regulatory Commission issued inspection report 50-269/99-12, 50-270/99-12, and
50-287/99-12 on September 21, 1999. The purpose of that inspection was to determine whether
your aging management programs adequately support your application for renewed operating
licenses for Oconee. One of the inspection findings identifies an issue related to applicable
aging effects for insulated cables and electrical connections that conflicts with the staffs findings
in the safety evaluation report (SER) that was issued by the staff on June 16, 1999, regarding
the Oconee license renewal application.
The staff concludes that the results of the inspection need to be reflected in a change to the SER
sections related to insulated cables and connections. Furthermore, the staff will need
additional information in order to resolve this issue. The Oconee license renewal application
(Section 3.6.3) identified the service environments in which insulated cables and connections
operate in as 'thermal', 'radiation', and 'moisture'. The application concluded that based on the
review of industry information, NRC generic communications, and Oconee operating experience,
no aging effects are applicable for insulated cables and connections. Therefore, no aging
management program is necessary. The NRC inspection team conducted walkdowns inside and
outside of containment to assess the material condition, reviewed a sample of the results of
previous Duke electrical inspections and problem investigation process reports and, found that
there is evidence of aging of insulated cables and electrical connectors, that appear to warrant
an aging management program. Therefore, Duke is requested to provide the technical basis for
the conclusion that no aging management program is needed or, provide a description of the
J
aging management program that will be utilized for insulated cables and connections at Oconee.
/
This issue is designated as Open Item 3.9.3-1 for tracking purposes.
As you are aware, the staff is currently scheduled to issue an update to the Oconee license
renewal application SER by February 12, 2000. The schedule also shows that you will respond
to all SER open items by October 15, 1999. Although the staff does not expect you to respond
to the above request for additional information by October 15, 1999, we would appreciate a
schedule for when you intend to respond to the issue.
9910070216 99105GO
PDR
ADOCK 05000269
P
PDR_
William R. McCollum
-2-
October 5, 1999
Currently the staff has not identified any other items in the inspection report that fundamentally
call into question the findings in the Oconee license renewal application SER. However, the
regional and headquarters staff will work with you to identify and develop a closure plan for all
the issues in the inspection report. If during the course of this activity the staff identifies other
issues where it needs additional information in order to update the SER we will inform you in a
separate letter.
If you have any questions regarding this issue please contact me at 301-415-1183, or the project
manager for the Oconee license renewal application, Mr. Sebrosky, at 301-415-1132.
Sincerely,
original signed by:
Christopher 1. Grimes, Chief
License Renewal and Standardization Branch
Division of Regulatory Improvement Programs
Office of Nuclear Reactor Regulation
Docket Nos. 50-269, 50-270,
and 50-287
cc w/encl: See next page
DISTRIBUTION: See next page
DOCUMENT NAME: G:\\RLSB\\SEBROSKY\\cables-oi.wpd
OFFICE
LA
PM:RLSB
BC:EEIB
BC:RLSB
NAME
EHylton*
JSebrosky l/<'
JCalvo
%(J C~rme
DATE
9/28/99
L/
99/99
L L1499
\\O/ S/99
OFFICIAL RECORD COPY
q00
William R. McCollum
-2
If you have any questions regarding this issue please contact myself at 301-415-1183, or the
project manager for the Oconee license renewal application, Mr. Sebrosky, at 301-415-1132.
Sincerely,
Christopher 1. Grimes, Branch Chief
License Renewal and Standardization Branch
Division of Regulatory Improvement Programs
Office of Nuclear Reactor Regulation
Docket Nos. 50-269, 50-270,
and 50-287
Enclosure: As stated
cc w/encl: See next page
DISTRIBUTION: See next page
DOCUMENT NAME: G:\\RLSB\\SEBROSKY\\cables-oi.wpd
OFFICE
LA
PM:RLSB
BC:EEIB
BC:RLSB
NAME
EHyltonOVPW JSebrosky
JCalv
CGrimes
DATE
q
1P999
q/199
1/0/99_/
/99
OFFICIAL RECORD COPY
Oconee Nuclear Station (License Renewal)
cc:
Mr. Larry E. Nicholson
Ms. Lisa F. Vaughn
Compliance Manager
Duke Energy Corporation
Duke Energy Corporation
422 South Church Street
Oconee Nuclear Site
Mail Stop PB-05E
P. 0. Box 1439
Charlotte, North Carolina 28201-1006
Seneca, South Carolina 29679
Anne W. Cottingham, Esquire
Ms. Karen E. Long
Winston and Strawn
Assistant Attorney General
1400 L Street, NW.
North Carolina Department of Justice
Washington, DC 20005
P. 0. Box 629
Raleigh, North Carolina 27602
Mr. Rick N. Edwards
Framatome Technologies
L. A. Keller
Suite 525
Manager- Nuclear Regulatory Licensing
1700 Rockville Pike
Duke Energy Corporation
Rockville, Maryland 20852-1631
526 South Church Street
Charlotte, North Carolina 28201-1,006.
Manager, LIS
NUS Corporation
Mr. Richard M. Fry, Director
2650 McCormick Drive, 3rd Floor
Division of Radiation Protection
Clearwater, Florida 34619-1035
North Carolina Department of
Environment, Health, and
Senior Resident Inspector
Natural Resources
U. S. Nuclear Regulatory Commission
3825 Barrett Drive
7812B Rochester Highway
Raleigh, North Carolina 27609-7721
Seneca, South Carolina 29672
Gregory D. Robison
Regional Administrator, Region II
Duke Energy Corporation
U. S. Nuclear Regulatory Commission
Mail Stop EC-12R
Atlanta Federal Center
P. 0. Box 1006
61 Forsyth Street, SW, Suite 23T85
Charlotte, North Carolina 28201-1006
Atlanta, Georgia 30303
Robert L. Gill, Jr.
Virgil R. Autry, Director
Duke Energy Corporation
Division of Radioactive Waste Management
Mail Stop EC-12R
Bureau of Land and Waste Management
P. 0. Box 1006
Department of Health and
Charlotte, North Carolina 28201-1006
Environmental Control
RLGILL@DUKE-ENERGY.COM
2600 Bull Street
Columbia, South Carolina 29201-1708
Douglas J. Walters
Nuclear Energy Institute
1776 1 Street, NW
Suite 400
Washington, DC 20006-3708
DJW@NEI.ORG
Chattooga River Watershed Coalition
P. O. Box 2006
Clayton, GA 30525
DISTRIBUTION:
-
H~an copy
Docket File
PUBLIC
RLSB RF
N. Dudley, ACRS - T2E26
EHylton
E-mail
R. Zimmerman
D. Matthews
S. Newberry
C. Grimes
C. Carpenter
B. Zalcman
J. Strosnider
R. Wessman
E. Imbro
W. Bateman
J. Calvo
T. Hiltz
G. Holahan
T. Collins
C. Gratton
B. Boger
R. Correia
R. Latta
J. Moore
J. Rutberg
R. Weisman
M. Mayfield
S. Bahadur
N. Chokshi
J. Vora
A. Murphy
D. Martin
W. McDowell
S. Droggitis
M. Modes
RLSB Staff
R. Emch
D. LaBarge
L. Plisco
C. Ogle
R. Trojanowski
D. Billings
M. Shannon
C. Julian
J. Peralta
J. Wilson
C. Sochor