3/4/2015, Meeting Slides Regarding Public Meeting with Tennessee Valley Authority, Watts Bar, Unit 2 for Transition Plan
ML15070A209
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 03/04/2015
From:
Tennessee Valley Authority
To:
Plant Licensing Branch II
Minarik A
Shared Package
ML15069A350 List:
References
Download: ML15070A209 (8)


Text

Watts Bar Unit 2 Transition Plan Public Meeting with TVA March 04, 2015 1

Purpose of Discussion

  • Discuss revisions to the NRC transition plan

- Inspection

- Assessment

- Performance Indicators

- Path P th Forward F d 2

Construction Oversight (IMC 2517 Assessment) ROP Assessment by IMC 0305 IMC 2512 Construction Issue License Completion of IMC 2514 94302 Letter Inspections Load Fuel IMC 2514 Pre-Op Testing ORAT IMC 2514 Startup p Testingg Inspection IAW IMC 2515 Baseline Inspection Program for All Cornerstones EP, Security, and Radiation Protection Cornerstones transitioned to the ROP Valid PIs: EP01, EP02, EP03, OR01, PR01, PP01 Valid PIs: IE04, MS05, BI01, BI02, MSPI*

Initiating Events, Mitigating Systems, and Barrier Augmented Inspection Valid PIs: IE01, IE03 Integrity Cornerstones transitioned to the ROP Augmented Inspection Valid PIs: MSPI*

  • MSPI for common or Unit 1 specific components will become effective immediately after IMC 2514 is completed. MSPI for Unit 2 specific components will become active after 4 Quarters 3

Inspection Programs

  • After Operating License (OL) Issued inspections will be conducted IAW IMC 2514, Light Water Reactor Inspection Program -

Light Startup Testing Phase, and IMC 2515, Light-Water Reactor Inspection Program -

Operations Phase 4

Assessment

  • Findings and PIs in cornerstones transitioned to the ROP will be assessed under the ROP assessment process

- SDP with color designations

- Supplemental inspections for greater than green findings or PIs

- The Action Matrix will not be utilized until after the licensee is notified of full transition into the ROP

- Outstanding greater than green inputs will be considered for Action Matrix placement when all cornerstones are monitored under the ROP ROP.

5

Performance Indicators (PIs)

  • Environmental Protection Protection, Radiation Protection and Security PIs will become valid once OL is issued
  • IE04, MS05, BI01, BI02, MSPI will become valid after TVA is notified of full transition into the ROP
  • IE01, IE01 IE03, IE03 andd MSPIs MSPI specificifi to UUnit i 2 will ill become valid 4 quarters after 6

Augmented Augmented Inspection

  • While PIs are invalid the licensee is still expected to submit the data
  • Augmented Augmented inspections may be performed in the event of an unplanned scram, power change, or equipment that effects MSPI for unit 2

- Inspections IAW Baseline procedures

- Samples p mayy exceed the maximum specified p if needed

- Expected one additional sample per occurrence 7

Path Forward

  • Finish review process for Transition Plan
  • Issue Transition Plan and make public in ADAMS 8