Letter Sequence Acceptance Review |
|---|
|
|
MONTHYEAR1CAN031403, Request for Exemption from Certain 10 CFR 50.61 and 10 CFR 50, Appendix G Requirements2014-03-20020 March 2014 Request for Exemption from Certain 10 CFR 50.61 and 10 CFR 50, Appendix G Requirements Project stage: Request 1CAN111401, Arkansas Nuclear One, Unit 1, License Amendment Request Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits2014-11-21021 November 2014 Arkansas Nuclear One, Unit 1, License Amendment Request Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits Project stage: Request 1CAN111401, License Amendment Request Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits2014-11-21021 November 2014 License Amendment Request Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits Project stage: Request ML14330A2502014-11-30030 November 2014 Attachment 4 to 1CAN111401, ANP-3300, Revision 1, Pressure-Temperature Limits at 54 Efpy Project stage: Request ML14345A6442014-12-11011 December 2014 NRR E-mail Capture - Acceptance Review Results - ANO-1 License Amendment Request to Revise the P/T and LTOP Limits - MF5292 Project stage: Acceptance Review ML15021A4282015-01-21021 January 2015 NRR E-mail Capture - Requests for Additional Information - ANO-1 P/T and LTOP Limits LAR to Extend P/T Curves to 54 EFPY - TAC No. MF5292 Project stage: RAI ML15041A0742015-02-0606 February 2015 ANP-3300Q1NP, Rev. 0, Response to Request for Additional Information on Reactor Coolant System Pressure/Temperature and Low Temperature Overpressure Protection System Limits to 54 EFPY for Arkansas Nuclear One, Unit 1, Attachment 2 to 1CAN0 Project stage: Response to RAI 1CAN021502, Responses to Request for Additional Information Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits2015-02-0606 February 2015 Responses to Request for Additional Information Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits Project stage: Response to RAI ML15065A0842015-03-0404 March 2015 NRR E-mail Capture - Request for Additional Information (2nd Round) - Arkansas Nuclear One, Unit 1 - LAR to Revise Pressure-Temperature Limits to 54 EFPY - TAC No. MF5292 Project stage: RAI 1CAN031503, Responses to Request for Additional Information Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits Arkansas Nuclear One, Unit 12015-03-10010 March 2015 Responses to Request for Additional Information Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits Arkansas Nuclear One, Unit 1 Project stage: Response to RAI ML15097A0052015-03-20020 March 2015 NRR E-mail Capture - Arkansas Nuclear One, Unit No. 1, Request for Additional Information (Second Round) - License Amendment Request Project stage: RAI 1CAN031504, Arkansas Nuclear One, Unit 1 - Responses to Request for Additional Information on Update of the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits2015-03-25025 March 2015 Arkansas Nuclear One, Unit 1 - Responses to Request for Additional Information on Update of the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits Project stage: Request ML15086A0242015-03-25025 March 2015 ANP-3300Q3NP, Revision 0 to Response to Request for Additional Information on Reactor Coolant System Pressure/Temperature and Low Temperature Overpressure Protection System Limits to 54 EFPY for Arkansas Nuclear One, Unit 1 (Non-Proprietary Project stage: Response to RAI ML15072A0792015-03-26026 March 2015 Request for Withholding Information from Public Disclosure - 3/9/15 Affidavit Executed by A. Meginnis, Areva Inc. ANP-3300Q2P, March 2015 Related to RCS Pressure/Temperature License Amendment Request Project stage: Withholding Request Acceptance ML15071A0552015-03-31031 March 2015 ANP-3300Q2NP, Revision 0, Response to Request for Additional Information on Reactor Coolant System Pressure/Temperature and Low Temperature Overpressure Protection System Limits to 54 EFPY for Arkansas Nuclear One, Unit 1 Project stage: Response to RAI ML15072A0772015-04-0202 April 2015 Request for Withholding Information from Public Disclosure - 2/6/15 Affidavit Executed by G. Elliott, Areva Inc. ANP-3300Q1P, February 2015 Related to RCS Pressure/Temperature License Amendment Request Project stage: Withholding Request Acceptance ML15093A0062015-04-0202 April 2015 NRR E-mail Capture - Requests for Additional Information - 4th Round - ANO-1 P/T and LTOP Limits Update to 54 EFPY License Amendment Request - MF5292 Project stage: RAI 1CAN041502, Responses to Request for Additional Information Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits2015-04-0707 April 2015 Responses to Request for Additional Information Update the Reactor Coolant System Pressure and Temperature and the Low Temperature Overpressure Protection System Limits Project stage: Response to RAI ML15096A0142015-04-20020 April 2015 Request for Withholding Information from Public Disclosure - 3/26/15 Affidavit Executed by G. Elliott, Areva Inc.; ANP-3300Q3P and Document No. 32-9220706-002 RCS Pressure/Temperature Amendment Request Project stage: Withholding Request Acceptance ML15096A3242015-04-24024 April 2015 Issuance of Amendment No. 254, Revise Technical Specifications to Update Reactor Coolant System Pressure and Temperature and Low Temperature Overpressure Protection System Limits Project stage: Approval 2015-03-20
[Table View] |
Text
1 NRR-PMDAPEm Resource From:
George, Andrea Sent:
Thursday, December 11, 2014 11:45 AM To:
BICE, DAVID B (ANO)
Cc:
CLARK, ROBERT W; PYLE, STEPHENIE L
Subject:
Acceptance Review Results - ANO-1 License Amendment Request to Revise the P/T and LTOP Limits - MF5292 Mr. Bice, By letter dated November 21, 2014 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML14330A246), Entergy Operations, Inc. (Entergy, the licensee), submitted a license amendment request for Arkansas Nuclear One, Unit 1 (ANO-1). The proposed license amendment request would revise the ANO-1 Technical Specifications (TS) with updated Reactor Coolant System Pressure /
Temperature curves and Low Temperature Overpressure Protection Limits that reflect continued unit operations to 54 Effective Full Power Years (EFPY).
The purpose of this e-mail is to provide the results of the NRC staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the TSs) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed the application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
If you have any questions, please contact me at (301) 415-1081.
Sincerely, Andrea George Project Manager Nuclear Regulatory Commission Division of Operating Reactor Licensing andrea.george@nrc.gov 301-415-1081
Hearing Identifier:
NRR_PMDA Email Number:
1754 Mail Envelope Properties (Andrea.George@nrc.gov20141211114400)
Subject:
Acceptance Review Results - ANO-1 License Amendment Request to Revise the P/T and LTOP Limits - MF5292 Sent Date:
12/11/2014 11:44:59 AM Received Date:
12/11/2014 11:44:00 AM From:
George, Andrea Created By:
Andrea.George@nrc.gov Recipients:
"CLARK, ROBERT W" <RCLARK@entergy.com>
Tracking Status: None "PYLE, STEPHENIE L" <SPYLE@entergy.com>
Tracking Status: None "BICE, DAVID B (ANO)" <DBICE@entergy.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 2714 12/11/2014 11:44:00 AM Options Priority:
Standard Return Notification:
No Reply Requested:
Yes Sensitivity:
Normal Expiration Date:
Recipients Received: