Email, Hope Creek and Salem, Draft Safety Evaluation for Approval of Revised Cyber Security Plan Implementation Schedule
ML14330A231
Person / Time
Site: Salem, Hope Creek  PSEG icon.png
Issue date: 11/25/2014
From: Sanders-Parker C
Plant Licensing Branch 1
To: Duke P
Public Service Enterprise Group
Sanders C, NRR/DORL/LPL1-2, 415-1603
References
TAC MF3384, TAC MF3385, TAC MF3386
Download: ML14330A231 (1)


Text

Sanders-Parker, Carleen From: Sanders-Parker, Carleen Sent: Tuesday, November 25, 2014 1:57 PM To: Duke, Paul R. (Paul.Duke@pseg.com)

Cc: Khanna, Meena; Ennis, Rick

Subject:

Hope Creek and Salem Draft Safety Evaluation for Approval of Revised Cyber Security Plan Implementation Schedule (TAC Nos. MF3384, MF3385, MF3386)

Attachments: DRAFT SE for SUNSI Review.docx The Attachment May Contain Security-Related Information And Should Be Handled Accordingly

Paul, Attached is a copy of the Draft safety evaluation (SE) for the subject license amendment. The information in section 3.0 of the draft SE, as well as the Milestone 8 implementation date, was identified as security-related in your application dated December 24, 2014, and your request for information response dated August 18, 2014 (Agencywide Access and Management System (ADAMS) Accession Nos. ML14174B239 and ML14231A048, respectively). The NRC staff does not consider this information to be security-related and the information is likely to be included in the final NRC staff SE which will be publicly available.

Please review the Draft SE and confirm by e-mail that you agree with the NRC staffs determination and none of the information contained in the attached Draft SE is security related. Alternatively, If you believe that any information in the enclosure is security-related, please identify such information line-by-line.

Since the NRC review is not yet complete, this letter and the enclosure do not convey or represent an NRC staff position regarding the licensee's request. Should the amendment be approved, the NRC staff will issue a publicly available version of the SE. The final SE will be issued after making any necessary changes and will be made publicly available. The NRC staff's disposition of your comments on the draft SE will be discussed in the final SE.

If you have any questions, please contact me at 301-415-1603.

Thank you, Carleen Carleen Parker Salem and Hope Creek Project Manager 301-415-1603 1