|
---|
Category:E-Mail
MONTHYEARML24008A0022024-01-0505 January 2024 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of License Amendment Request for Application to Revise TS to Adopt TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation - EPID L-2023-LLA-0170 ML23278A0042023-10-0404 October 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling - EPID L-2023-LLA-0128 ML23275A0092023-09-29029 September 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise Tech Specs to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling - EPID: L-2023-LLA-0128 ML23150A2502023-05-26026 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - License Amendment Request to Clean-Up Operating License and Appendix a, Technical Specifications - EPID L-2023-LLA-0062 ML23124A2412023-05-0404 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise TS to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position - EPID L-2023-LLA-0063 ML23124A0062023-05-0303 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - Application to Revise Tech Specs to Adopt TSTF-541, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling - EPID L-2023-LLA-0063 ML23065A0422023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2022 Biological Monitoring Report ML22343A1802022-12-0808 December 2022 February 2023 Emergency Preparedness Program Inspection - Request for Information ML22349A2002022-12-0101 December 2022 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2022 Priority Pollutant Discharge Monitoring Report ML22312A0042022-11-0707 November 2022 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of Fourth 10 Year ISI RR 4ISI-11 - EPID L-2022-LLR-0071 ML22301A1432022-10-28028 October 2022 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Adopt TSTF-505 - EPID L-2022-LLA-0023 ML22256A2002022-09-13013 September 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22241A0182022-08-26026 August 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22235A1052022-08-22022 August 2022 August 2022 Emergency Preparedness Exercise Inspection Request for Information ML22210A0072022-07-28028 July 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22173A0682022-06-17017 June 2022 Email Concurrence on SE Input for Columbia Pltr LAR ML22166A4122022-06-15015 June 2022 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - Application to Revise TS to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling - EPID L-2022-LLA-0081 ML22144A0342022-05-18018 May 2022 NRR E-mail Capture - Draft - Request for Additional Information - Columbia Generating Station - LAR to Change TS 3.4.11 - Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML22075A3392022-03-15015 March 2022 NRR E-mail Capture - Columbia Generating Station - Audit Questions - Regulatory Audit of License Amendment Request to Adopt 50.69 - Categorization Process - EPID L-2021-LLA-0207 ML22067A0132022-03-0707 March 2022 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of License Amendment Request to Adopt TSTF-505, Revision 2, Provide RISK-INFORMED Extended Completion Times - RITSTF Initiative 4b - EPID L-2022-LLA-0023 A002515, NRR E-mail Capture - (External Sender) Energy Northwest Columbia Generating Station 2021 Priority Pollutant Discharge Monitoring Report2022-01-12012 January 2022 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2021 Priority Pollutant Discharge Monitoring Report ML21348A1852021-12-14014 December 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia - License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors - EPID L-2021-LLA-0207 ML21335A0182021-11-30030 November 2021 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of Requested Licensing Action - License Amendment Request to Change TS 3.4.11 Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML21216A0502021-08-0303 August 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia - License Amendment Request to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO EPID L-2021-LLA-0259 ML21209A9792021-07-28028 July 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) - EPID L-2021-LLA-0074 ML21162A3062021-06-11011 June 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia Generating Station - License Amendment Request to Adopt TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement - EPID L-2021-LLA-0084 ML21137A0012021-05-14014 May 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia Generating Station - License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) - EPID L-2021-LLA-0074 ML21120A1182021-04-30030 April 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - On-Site Cooling System Sediment Disposal Approval Request - EPID L-2020-LLL-0031 ML21109A2762021-04-0808 April 2021 Email Request for Information for Columbia Generating Station'S PIR Inspection_Redacted ML21068A2842021-03-0404 March 2021 2021002 Inservice Inspection (ISI) Request for Information (RFI) ML21036A2932021-02-0404 February 2021 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2020 Biological Monitoring Report ML20357B1502020-12-22022 December 2020 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia - License Amendment Request - Adoption of TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO, Rev. 2 - EPID L-2020-LLA-0259 ML20336A1852020-11-30030 November 2020 NRR E-mail Capture - Final - RAI - Columbia - One -Time Exemption from 10 CFR 73, App B, Sect VI, Subsection C.3.(l)(1) Regarding Annual Force-On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20325A0402020-11-19019 November 2020 NRR E-mail Capture - Draft - RAI - Columbia - One -Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force -On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20314A0452020-11-0606 November 2020 NMFS to Energy Northwest, Entrainment Study Results for Columbia Generating Station ML20297A3032020-10-22022 October 2020 NRR E-mail Capture - LIC-109 Acceptance Review of License Amendment Request for Columbia - Application to Revise Tech Specs to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements - EPID L-2020-LLA-0212 ML20267A5162020-09-23023 September 2020 NRR E-mail Capture - Columbia Generating Station - Final - Request for Additional Information - Fourth Ten-Year Interval Inservice Inspection (ISI) Program Relief Request 4ISI-09 - EPID L-2020-LLR-0068 ML20265A3242020-09-20020 September 2020 Email 9-20-2020 - Req_ Kick-Off Call Columbia Generating Station RFI Provided for Roll-Back EP Program Inspection (Week of Nov 2 2020) ML20245E2822020-08-31031 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20239A9702020-08-26026 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20149K4362020-05-26026 May 2020 NRR E-mail Capture - Formal RAIs for Columbia (COVID-19) QA Plan Change Surveillance, Request Response by Tuesday June 2, 2020 ML20136A0112020-05-14014 May 2020 NRR E-mail Capture - Acceptance Columbia Relief Request ISI Reactor Pressure Vessel Feedwater Nozzles, 4ISI-09 ML20112F4572020-04-21021 April 2020 NRR E-mail Capture - Official Release of NRC RAIs for Columbia Covid Exigent Due Friday April 24, 2020 ML20090F5532020-03-30030 March 2020 NRR E-mail Capture - Accepted: Columbia Relief Request, EPID: L-2020-LLR-0035 ML20063G1522020-03-0202 March 2020 NRR E-mail Capture - Columbia Generating Station - Acceptance of Requested Licensing Action TSTF-564 Amendment ML20056E3592020-02-25025 February 2020 NRR E-mail Capture - Columbia Generating Station - Acceptance of Requested Licensing Action TSTF-566 Amendment ML20034E6082020-02-0303 February 2020 NRR E-mail Capture - RAI Formal Release Columbia TSTF 563 LAR, 30 Day Response Period Due March 3, 2020 ML20013G7642020-01-10010 January 2020 Revised Questions to Support the Columbia SPRA Audit ML19305C9342019-11-0101 November 2019 50.54(f) SPRA Submittal - Completeness Review Done and Path Forward ML19291A0322019-10-17017 October 2019 NRR E-mail Capture - Subject: Columbia Generating Station - Acceptance of Requested Licensing Action TSTF-529 Amendment 2024-01-05
[Table view] |
Text
NRR-PMDAPEm Resource From: George, Andrea Sent: Tuesday, November 25, 2014 11:50 AM To: 'Williams, Lisa L.'
Subject:
Request for Additional Information - Columbia License Amendment Request to Revise UHS Level TS (MF4682)
Attachments: MF4682 RAIs.pdf Ms. Williams, By letter dated August 22, 2014 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML14251A032), Energy Northwest, the licensee, requested a change to the Technical Specifications (TSs) for Columbia Generating Station. The amendment proposes to change TS 3.7.1, "Standby Service Water (SSW) and Ultimate Heat Sink (UHS)," specifically as it relates to Surveillance Requirement (SR) 3.7.1.1, regarding UHS spray pond water level.
The staff is reviewing the subject license amendment request and has determined that further information is required in order to complete the staffs evaluation. The requests for additional information are attached to this email. These RAIs were sent in draft form to you on November 13, 2014, and a clarification call was held on November 24, 2014. During the call, it was decided that a response to these RAIs would be provided by December 26, 2014.
Thank you, Andrea George Project Manager Nuclear Regulatory Commission Division of Operating Reactor Licensing andrea.george@nrc.gov 301-415-1081 1
Hearing Identifier: NRR_PMDA Email Number: 1721 Mail Envelope Properties (Andrea.George@nrc.gov20141125115000)
Subject:
Request for Additional Information - Columbia License Amendment Request to Revise UHS Level TS (MF4682)
Sent Date: 11/25/2014 11:50:14 AM Received Date: 11/25/2014 11:50:00 AM From: George, Andrea Created By: Andrea.George@nrc.gov Recipients:
"'Williams, Lisa L.'" <llwilliams@energy-northwest.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 1161 11/25/2014 11:50:00 AM MF4682 RAIs.pdf 85070 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
REQUESTS FOR ADDITIONAL INFORMATION REVISION TO ULTIMATE HEAT SINK LEVEL SURVEILLANCE REQUIREMENT ENERGY NORTHWEST COLUMBIA GENERATING STATION DOCKET NO. 50-397 By application dated August 22, 2014, to the U.S. Nuclear Regulatory Commission (NRC)
(Agencywide Documents Access and Management System (ADAMS) Accession No. ML14237A729), Energy Northwest, the licensee, submitted a license amendment request to revise Columbia Generating Station Technical Specification (TS) Surveillance Requirement (SRs) 3.7.1.1 for the ultimate heat sink (UHS) to clarify that spray pond level is the average of the level in both ponds.
Based on its review, the NRC staff requests the following additional information to complete its safety evaluation of the application.
Background:
Energy Northwest stated in the amendment that the UHS is described in Final Safety Analysis Report (FSAR) Section 9.2.5, Ultimate Heat Sink, and consists of two concrete spray ponds.
The design basis function of the UHS is to provide a source of water for the Service Water (SW) system for 30 days and to absorb the heat transferred to it from the plant via the SW system during that time period without exceeding its design temperature.
BOP-RAI-1-1 Describe the high pressure core spray (HPCS) SW pump and any interactions with the UHS TS minimum water level or basin overflow when the HPCS SW pump is operating during testing.
BOP-RAI-1-2 Describe, given an automatic start of all three SW divisional pumps (and assuming a single failure), any interactions with the UHS TS minimum water level or basin overflow.
BOP-RAI-1-3 During operational testing of the HPCS SW pump, are there are conditions that would cause an overflow condition with the possibility of substantial loss of UHS water volume? If so, please describe.
Background:
In its LAR, Energy Northwest listed applicable NRC regulatory requirements related to the SW and UHS, including the 10 CFR 50 Appendix A, General Design Criteria (GDC), as follows:
GDC 44, GDC 45, GDC 46.
BOP-RAI-2-1 Discuss why GDC 2 and 4 are not addressed in the application, or, provide information to address the regulatory requirements in GDC 2 and 4.
BOP-RAI-2-2 GDC 44 states that suitable redundancy in components and features, and suitable interconnections, leak detection, and isolation capabilities shall be provided to assure that for onsite electric power system operation (assuming offsite power is not available) and for offsite electric power system operation (assuming onsite power is not available) the system safety function can be accomplished, assuming a single failure.
Please address the loss of the 30 diameter siphon line as it relates to GDC 44 and single failure with the potential loss of UHS water level.
Background:
The licensee states in its LAR that the existing language in TS SR 3.7.1.1 requires verification that the level in each spray pond is greater than or equal to 432 feet 9 inched MSL.
Additionally, the licensee states that due to the design of the spray ponds and SW system, it is difficult to meet this requirement in each pond when only one SW pump is in operation. Normal level in the spray ponds is maintained at less than 433.5 feet. The high level alarm is at 434.25 feet. The pond overflow is at 434.5 feet.
With one SW pump in operation, the level in the associated pond drops approximately 9-11 inches while the level in the other pond rises by an equivalent amount for a total differential level of 18-22 inches. In order to meet the minimum TS level of 432.75 feet when one SW pumps is in operation, the normal level in the ponds would need to be maintained slightly above 433.5 feet.
Based on the staffs calculation, at the beginning of any SW pump testing, SW automatic start, or EDG testing which involves one Division 1 or Division 2 pump, in order to prevent UHS overflow and loss of UHS water inventory, the initial water level cannot be any higher than 433 feet 6 inches MSL. At 433 feet 7 inches MSL, it appears the opposite basin will rise to a level of
+11 inches and start to overflow at 434 feet 6 inches MSL.
BOP-RAI-3-1 During testing as stated above, what water volume (in gallons) can be lost in the overflow?
Provide any strip-chart data that may be available.
BOP-RAI-3-2 During automatic SW pump starts, what water volume (in gallons) can be lost in the overflow?
Provide any strip-chart data that may be available.
BOP-RAI-3-3
Based on the response to questions 1 and 2, describe any TS Limiting Condition for Operations (LCOs) that are to be entered during any UHS basin overflow condition and describe any past Licensee Event Reports (LERs) that addresses degraded UHS basin level during pump starts.
BOP-RAI-3-4 Describe the controls that are in place (for example, operating procedures or alarms) to maintain the UHS TS water level requirements (in standby) knowing that an overflow condition is likely if the initial UHS water level is above 433 feet 6 inches and normal UHS water level is at 433 feet 6 inches.
BACKGROUND The licensee states in the LAR that the siphon line is American Society of Mechanical Engineers (ASME)Section III, Code Class 3 piping. The licensee stated that the buried portion of the siphon line is included in Columbia's Inservice Inspection (ISI) Program, is examined in accordance with ASME Section XI, and is classified in Code Category D-B, Item D2.10, pressure retaining components. The licensee stated that quarterly SW operability testing demonstrates that adequate flow is being produced and that the line in not impaired during operation.
In September 2007, the licensee stated that it performed a long range guided wave examination and it also performed B-Scan Ultrasonic Test (UT) to measure the pipe wall thickness of the siphon line. The licensee found minor corrosion in the pipe. In September 2008, the licensee performed UT to measure wall thickness of an elbow in the buried portion of the pipe. The minimum pipe wall thickness of the elbow is greater than the nominal wall thickness.
The Columbia FSAR, Figure 9.2-7, Composite Piping Plan, Section and Details, Spray Ponds, shows (in Section 3-3) a watertight boot attached to the siphon line which is part of the UHS basin.
BOP-RAI-4-1 Describe the purpose of the siphon line water tight boot and the consequences of its failure.
BOP-RAI-4-2 Describe if the siphon line watertight boot needs to be periodically inspected as part of the inspection plan related to a possible UHS water inventor loss.
BOP-RAI-4-3 Depending on the response to RAIs 1 and 2 of this section, describe the last inspections performed on the siphon line watertight boots.
BOP-RAI-4-4 Describe if there are other water tight boots within the UHS pond which are located below the UHS water line and if so, the consequences of the boot failure(s).