Email from M.Thadani to W.Craft Acceptance Review Determination - LAR for Administrative Changes and Request for Correction of Errors in Technical Specifications
ML14240A526
Person / Time
Site: Millstone Dominion icon.png
Issue date: 08/28/2014
From: Thadani M
Plant Licensing Branch 1
To: Craft W
Dominion Generation
Guzman R
References
TAC MF3872
Download: ML14240A526 (2)


Text

From: Thadani, Mohan Sent: Thursday, August 28, 2014 9:02 AM To: Wanda D Craft (Generation - 6) (wanda.d.craft@dom.com)

Subject:

RE: License Amendment Request for Administrative Changes and Request for correction of Errors in Technical Specifications (TAC No. MF3872)

Wanda:

Acceptance review for the application for the subject amendment request is provided below.

Thanks, Mohan Mr. David A Heacock President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NO. 3 -ACCEPTANCE REVIEW REGARDING LICENSE AMENDMENT TO FOR ADMINISTRATIVE CHANGES AND COREECTIONS TO THE TECHNICAL SPECIFICATIONS. (TAC No. MF3872)

Dear Mr. Heacock:

By letter dated March 28, 2014, Dominion Nuclear Connecticut, Inc., the licensee for Millstone Power Station, Unit 2, submitted license amendment requests (LAR) to make administrative changes and corrections to the Technical Specifications (TS). The proposed changes would delete the TS index and make other administrative changes and corrections to the TS.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.

This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your applications dated March 28, 2014, and concluded that the application does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.

If you have any questions, please contact me at (301) 415-1476 or email Mohan.Thadani@nec.gov.

Sincerely, Mohan C Thadani Senior Project Manager Millstone, Ginna, and Constellation Fleet Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476 Mohan.Thadani@nrc.gov