UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P.O. Box 236, N09 Hancocks Bridge, NJ 08038 September 3, 2014
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNIT 1-REVIEW OF THE CORE OPERATING LIMITS REPORT (COLR), CYCLE 23 (TAC NO. MF2473)
Dear Mr. Joyce:
By letter dated May 3, 2013, as supplemented by letter dated July 10, 2014 (Agencywide Documents Access and Management System Accession Nos. ML13129A284 and ML14195A469, respectively), PSEG Nuclear, LLC submitted the Salem Nuclear Generating Station, Unit 1 Cycle 23 Core Operating Limits Report (COLR) in accordance with Technical Specification (TS) Section 6.9.1.9.d.
The U.S. Nuclear Regulatory Commission (NRC) staff has completed its review of the report and concludes that the cycle-specific parameter limits were developed using NRC-approved methodologies and that PSEG has met the TS requirements.
If you have any questions, please contact me at (301) 415-1603 or via e-mail at Carleen.Sanders@nrc.gov.
Docket No. 50-272 cc: Distribution via ListServ Sincerely,
/ ;
I i
I
(~_{\\..,_~ (!
I Carleen J. Sanders, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
September 3, 2014 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P.O. Box 236, N09 Hancocks Bridge, NJ 08038
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNIT 1 -REVIEW OF THE CORE OPERATING LIMITS REPORT (COLR), CYCLE 23 (TAC NO. MF2473)
Dear Mr. Joyce:
By letter dated May 3, 2013, as supplemented by letter dated July 10, 2014 (Agencywide Documents Access and Management System Accession Nos. ML13129A284 and ML14195A469, respectively), PSEG Nuclear, LLC submitted the Salem Nuclear Generating Station, Unit 1 Cycle 23 Core Operating Limits Report (COLR) in accordance with Technical Specification (TS) Section 6.9.1.9.d.
The U.S. Nuclear Regulatory Commission (NRC) staff has completed its review of the report and concludes that the cycle-specific parameter limits were developed using NRC-approved methodologies and that PSEG has met the TS requirements.
If you have any questions, please contact me at (301) 415-1603 or via e-mail at Carleen. Sanders@nrc.gov.
Docket No. 50-272 cc: Distribution via ListServ DISTRIBUTION:
PUBLIC RidsNrrDoriDpr Resource RidsNrrDssSrxb Resource RidsNrrLAABaxter Resource THuang, NRR ADAMS A ccess1on N ML14237A404 o.:
OFFICE LPL 1-2/PM LPL 1-2/LA NAME CSanders ABaxter DATE 8/27/2014 08/27/2014 Sincerely, IRA/
Carleen J. Sanders, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation LPLI-2 R/F RidsNrrDorllpll-2 Resource RidsNrrPMSalem Resource RidsRgn1 MaiiCenter Resource
- b IY memo d t d ae SRXB/BC*
LPL 1-2/BC US hoop RSchaaf 08/18/2014 9/03/2014 OFFICIAL RECORD COPY