ML14192A539

From kanterella
Jump to navigation Jump to search
Confirms 841128 Mgt Meeting in Atlanta,Ga to Discuss Readiness of Facility to Commence Operations After Extended Steam Generator Replacement Outage,Per 841119 Telcon
ML14192A539
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 11/21/1984
From: Olshinski J
NRC/IE, NRC/RGN-II
To: Utley E
Carolina Power & Light Co
References
NUDOCS 8412280257
Download: ML14192A539 (2)


Text

NOV 2 1 1984 Carolina Power and Light Company ATTN:

Mr. E. E. Utley Executive Vice President JE FILE COPY Power Supply and Engineering and Construction 411 Fayetteville Street Raleigh, NC 27602 Gentlemen:

SUBJECT:

CONFIRMATION OF MEETING -

DOCKET NO. 50-261 This confirms the telephone conversation between myself and Mr. M. A. McDuffie, Senior Vice President, Nuclear Generation on November 19,

1984, concerning a management meeting to be conducted in Atlanta, Georgia, on November 28, 1984, at 2:00 p.m.

We requested this meeting to discuss the readiness of H. B. Robinson to commence operations after the extended steam generator replacement outage.

We specifically wish to discuss your plans to ensure that the plant staff has the proper training to begin operations safely and that operability of plant systems has been reviewed to minimize equipment failures during commencement of operations.

Should you have any questions regarding these arrangements, we will be pleased to discuss them.

Sincerely, John A. Olshinski, Director Division of Reactor Projects

Enclosure:

Notice of Significant Licensee Meeting cc w/encl:

G. P. Beatty, Jr., Manager Robinson Nuclear Project Department R. E. Morgan, Plant General Manager bcc w/encl:

NRC Resident Inspector Document Control Desk State of South Carolina RII RII RII

'Fre ickson:ht DMVerrelli 1 1/UO/84 11/ -M/84 1/

8412280257 841121 PDR ADOCK 05000261 PPDR

2 11984 NOTICE OF SIGNIFICANT LICENSEE MEETING Name of Licensee:

Carolina Power and Light Company Name of Facility:

H. B. Robinson 2 Docket No.:

50-261 Date and Time of Meeting:

November 28, 1984, at 2:00 p.m.

Location of Meeting:

NRC Region II Office, Atlanta, Georgia Purpose of Meeting:

Discuss readiness of the H. B. Robinson facility to begin operations after the extended steam generator replacement outage.

NRC Attendees:

James P. O'Reilly, Regional Administrator John A. Olshinski, Director, Division of Reactor Projects (DRP), RII P. R. Bemis, Acting Director, Division of Reactor Safety (DRS), RII D. M. Verrelli, Chief, Reactor Projects Branch 1, DRP, RII P. E. Fredrickson, Acting Chief, Projects Section 1C, DRP, RII A. K. Hardin, Project Inspector, Robinson 2 H. Krug, Senior Resident Inspector, Robinson 2 Licensee Attendees: M. A. McDuffie, Senior Vice President, Nuclear Generation G. P. Beatty, Manager, Robinson Nuclear Project R..E. Morgan, Plant General Manager NOTE:

Attendance by NRC personnel at this NRC/Licensee meeting should be made known by 4:00 p.m.,

November 26, 1984, via telephone call to P. E. Fredrickson FTS:

242-4668.

Distribution:

Victor Stello, Jr., DEDROGR J. Lieberman, Director, ROE R. DeYoung, Director, IE J. M. Taylor, Director, Division of Reactor Programs, IE G. Requa, Project Manager, NRR Region II Distribution List C

~~Recep tioqn is t______

RII RII R Ini C4Fre rickson:ht DMVerrelli P' is 3 A, n 11/

/84 11/ip /84 11/

/84