Informs That Applicant Request for Hearing on 810617 & 26 Re Environ Qualification of safety-related Equipment Reviewed. Request Held in Abeyance for 90 Days.Requests Specific Issues Applicant Intends to Raise in Proceeding
ML14192A215
Person / Time
Site: Robinson, Brunswick  
Issue date: 07/07/1981
From: Eisenhut D
Office of Nuclear Reactor Regulation
To: Rosalyn Jones
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
References
NUDOCS 8107150424
Download: ML14192A215 (3)


Text

Distributio:

JUL 0 8 1981 Docket File NRC PDR omeson Docket Nos. 50-325 Local PDR 50-324 ORB#2 Rdg.

50-261 D. Eisenhut.

\\

OELD 0I&E (3)

T. Ippolito M. Williams UUL 7

Mr. Richard E. Jones S. Norris Associate General Counsel NSIC Carolina Power and Light Company TERA P. 0. Box 1551 ACRS (10)

Raleigh, North Carolina J. Heltemes

Dear Mr. Jones:

SUBJECT:

IN THE MATTER OF CAROLINA POWER AND LIGHT COMPANY (BRUNSWICK STEAM ELECTRIC PLANT NO. 1 & 2, AND H. B. ROBINSON STEAM ELECTRIC PLANT UNIT NO. 2), DOCKET NOS. 50-325; 50-324 AND 50-261 We have reviewed the Carolina Power and Light Company's requests for a hearing dated June 17 and June 26, 1981 regarding the Environmental Qualification of Safety Related Electrical-Equipment. As you will recall, members of the NRC staff contacted you on June 30, 1981 to discuss these hearing requests. It was our understanding of that conversation that you considered it acceptable for us to ho8d your requests in abeyaoce until 90 days after the date 6f issuance of the Safety Evaluations for the facilities. This interim period would allow additional feedback from the NRC staff concerning the issues you raised in your requests. At or befote '

the end of the interim period, you will advise us, in writing, of whether you intend to pursue your hearing requests and what specific issues you intend to to raise in the proceeding.

Please confirm as soon as practicable that our understanding is correct.

Sincerely,

'Original signed by Darrell G. Eisenhut Darrell G. Eisenhut, Director Division of Licensing 8107150424 810707 PDR ADOCK 05000261 PDR OELD

  • DLORB#1
  • ORB#2*

Lieberman/Cosgrove SAVarga T. Ippolito.See Fious concurrence sheet

/ /81

/

/81

/ /81 OFFICEO DL:ORB#2 t DL:ORB#2

..DL;qR.

  • DL;QRB0l....

. L;-.DLD.

OR.

Pur D

nhu t OATE~...........................

DATE 318 10C NRc on sislo so )NRcM 240 OFFICIAL RECORD COPY ASP:90392

Distribution:

Docket File NRC PDR Docket Nos. 50-325 Local PDR 50-324 ORB #2 Rdg 50-261 D. Eisenhut OELD OI&E (3)

T. Ippolito Mr. Richard E. Jones M. Williams Associate General Counsel S. Norris Carolina Power and Light Company NSIC P. 0. Box 1551 TERA Raleigh, North Carolina ACRS (10)

J. Heltemes

Dear Mr. Jones:

SUBJECT:

IN THE MATTER OF CAROLINA POWER AND LIGHT COMPANY (BRUNSWICK STEAM ELECTRIC PLANT NO. 1 & 2, AND H. B. ROBINSON STEAM ELECTRIC PLANT UNIT NO. 2), DOCKET NOS. 50-325, 50-324 AND 50-261 We havereviewed the Carolina Power and Light Company's requests for a hearing dated June 17 and June 26, 1981 regarding the Environmental Qualification of Safety-Related.Electrical Equipment.

As you will recall, members of the NRC staff contacted you on June 30, 1981 to discuss these hearing requets.

It was our understanding of that.conversation that you considered it acceptable for us to hold your requests in abeyance until 90 days after the date of issuance of the Safety Evaluations for the facilities. This interim period would allow additional feedback from the NRC staff concerning the issues you raised in your requests.

At the end of the interim period, you will be required to advise us, in writing, of whether you intend to pursue your hearing requests.

If you do pursue a hearing, please advise me of the specific issues-you intend to raise in the proceeding.

Please respond to this letter with your formal postion-regarding our approach by July 6, 1981.

Please send a copy6f your response to us via telecopy (301-492-7371, Attn:

Mark Williams).

Thank you.

Sincerely, Darrell G. Eisenhut, Director Division of Licensing Lieberma Cosgroveg OFFICE)

DL: RB OFF2,E,, LOB

~

~

#2 DL:ORB#....2
  1. 1 DL:O DL:DD DL:D SURNAMEj SRA S~or.ia.....

W

....... iamsm VanVliet D ghbors I vak RPurple DGEisenhut T11ams :ms DATE/ 88

/8

./81

/

/81

<NRC FORM 318 (10/80 NRCM 0240 OFFICIAL RECORD COPY' USGPO: 1980-329-824

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 July 7, 1981 Docket Nos.

50-325 50-324 50-261 Mr. Richard E. Jones Associate General Counsel Carolina Power and Light Company P. 0. Box 1551 Raleigh, North Carolina

Dear Mr. Jones:

SUBJECT:

IN THE MATTER OF CAROLINA POWER AND LIGHT COMPANY (BRUNSWICK STEAM ELECTRIC PLANT NO. 1 & 2, AND H. B. ROBINSON STEAM ELECTRIC PLANT UNIT NO. 2), DOCKET NOS. 50-325, 50-324 AND 50-261 We have reviewed the Carolina Power and Light Company'.s requests for a hearing dated June 17 and June 26, 1981 regarding the Environmental Qualification of Safety-Related Electrical Equipment. As you will recall, members of the NRC staff contacted you on June 30, 1981 to discuss these hearing requests. It was our understanding of that conversation that you considered it acceptable for us to hold your requests in abeyance until 90 days after the date of issuance of the Safety Evaluations for the facilities. This interim period would allow additional feedback from the NRC staff concerning the issues you raised in your requests. At or before the end of the interim period, you will advise us, in writing, of whether you intend to pursue your hearing requests and what specific issues you intend to raise in the proceeding.

Please confirm as soon as practicable that our understanding is correct.

incerely, Darre

. Eisenhut, Director Division of Licensing