Discusses Topics for Discussion on Submittals Re Nuclear Assessment Dept Functional Changes.Meeting Scheduled for 930527 to Discuss Various Concerns
ML14184B062
Person / Time
Site: Harris, Brunswick, Robinson  
Issue date: 05/07/1993
From: Mozafari B
Office of Nuclear Reactor Regulation
To: Orser W
Carolina Power & Light Co
References
TAC-M84259, TAC-M84260, TAC-M84312, TAC-M84325 NUDOCS 9305140260
Download: ML14184B062 (4)


Text

pftRE~j 0 o UNITED STATES NUCLEAR REGULATORY COMMISSION o Z WASHINGTON, D. C. 20555 May 7, 1993 Docket Nos. 50-261 50-325 and 50-324 50-400 Mr. W. S. Orser Executive Vice President Nuclear Generation Carolina Power & Light Company Post Office Box 1551, MC: CPB12 Raleigh, North Carolina 27602

SUBJECT:

TOPICS FOR DISCUSSION CONCERNING CAROLINA POWER & LIGHT COMPANY SUBMITTALS RELATED TO THE NUCLEAR ASSESSMENT DEPARTMENT FUNCTIONAL CHANGES FOR BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2, H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2, AND SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 (TAC NOS. M84259, M84260, M84312, AND M84325)

On August 6, 1992, Carolina Power & Light Company (CP&L) submitted applications for amendments to the operating licenses for the Shearon Harris Nuclear Power Plant, Unit No. 1, (Harris), and the Brunswick Steam Electric Plant, Units No. 1 and 2, (BSEP). The requested changes are intended to implement the functional role and responsibilities of the newly established Nuclear Assessment Department (NAD). A similar amendment request was submitted on August 10, 1992, for the H. B. Robinson Steam Electric Plant, Unit No. 2, (HBR).

In addition, on August 6, 1992, submittals were made in accordance with 10 CFR 50.54(a)(3) to change the Quality Assurance (QA) programs of the same three plants. Amendments had already been approved for Harris, BSEP, and HBR on July 7, 1991, October 22, 1991, and December 20,1991, respectively, to revise numerous Technical Specifications (TS) to support the organizational structure of NAD.

The NRC has reviewed the various submittals and have some concerns that would best be addressed in a meeting between our respective staffs. A meeting has been scheduled for this purpose on May 27, 1993, at NRC headquarters. The formal meeting notice is forthcoming.

Your discussion should focus on providing assurance that the changes that have been proposed would not reduce your ability to meet NRC requirements. Of particular concern are the following topics that should be included in your presentation:

1. Provide assurance that proposed changes ensure compliance with Appendix B of 10 CFR Part 50 the in area of required, periodic assessments.
2. Discuss commitments made for assessments or periodic audits to address plant modifications, receipt inspection, training, and calibration.

9305140260 13050'7 FZ 1

%- ~

PDR' ADOC.K 05000261 P--D

May 7, 1993

-2

3. Discuss provisions that are proposed to meet the safeguards audit requirements of 10 CFR 50.54(p).
4. Likewise, discuss how CP&L plans to ensure that the emergency preparedness audit requirements of 10 CFR 50.54(t) will be met.
5. Provide assurance that changes proposed with regard to Plant Nuclear Safety Committee and independent reviews maintain CP&L's commitment to meet the requirements of ANSI N18.7.

Discuss how the proposed changes reflect accepted content as described in section 6 of the Standard Technical Specification (STS) or section 5 of the improved STS.

The reporting and/or recordkeeping requirements contained in this letter affect fewer than ten respondents; therefore, OMB clearance is not required under P. L.96-511.

Any questions concerning the schedule or agenda for the meeting can be directed to me at (301) 504-2020.

Sincerely, ORIGINAL SIGNED BY:

Brenda L. Mozafari, Project Manager Project Directorate II-1 Division of Reactor Projects -

I/II Office of Nuclear Reactor Regulation DISTRIBUTION:

Docket File j NRC/Local PDRs PD II-1 Reading File S.A. Varga G.C. Lainas J.A. Mitchell P.D. Anderson B.L. Mozafari N.B. Le P.D. Milano OGC ACRS (10)

M. Branch, R-II H. Christensen, R-II E.W. Merschoff, R-II cc:

Plant Service list OFC LA:

E PM:PD21:DRPE PM:PD21:DRPE PM:PD21:DRPE A

II:DRPE NAME PDAde'rson BLMozafari:tmw NBLe / k PDMilanf G.VL a___nas DATE 05

/9 05/

/93 05/ 6 /93 05/ 6. /93 05/, /93 OFC

p DRIL:RPEB*

NAME AMi chell GZECH DATE 05/ 1/93 5/ 6/93

cc:

Mr. W. S. OrseqP Carolina Power & Light Company Mr. H. Ray Starling Mr. C. R. Dietz Manager -

Legal Department Vice President Carolina Power & Light Company Carolina,Power & Light Company Post Office Box 1551 H. B. Robinson Steam Electric Plant Raleigh, North Carolina 27602 Post Office Box 790 Hartsville, South Carolina 29550 Mr. H. A. Cole Special Deputy Attorney General Mr. Heyward G. Shealy, Chief State of North Carolina Bureau of Radiological Health Post Office Box 629 South Carolina Department of Health Raleigh, North Carolina 27602 and Environmental Control 2600 Bull Street U. S. Nuclear Regulatory Commission Columbia, South Carolina 29201 Resident Inspector's Office H. B. Robinson Steam Electric Plant Mr. H. W. Habermeyer, Jr.

Route 5, Box 413 Vice President Hartsville, South Carolina 29550 Carolina Power & Light Company Nuclear Services Department Regional Administrator, Region II Post Office Box 1551 MC: OHS7 U. S. Nuclear Regulatory Commission Raleigh, North Carolina 27602 101 Marietta Street, NW, Ste. 2900 Atlanta, Georgia 30323 Resident Inspector/Harris NPS Shearon Harris Nuclear Power Plant Mr. Ray H. Chambers, Jr.

Nuclear Regulatory Commission General Manager Route 1, Box 315B Carolina Power & Light Company New Hill, North Carolina 27562 H. B. Robinson Steam Electric Plant Post Office Box 790 Mr. Gerald E. Vaughn Hartsville, South Carolina 29550 Vice President Carolina Power & Light Company Mr. Dayne H. Brown, Director Shearon Harris Nuclear Plant Department of Environmental, Post Office Box 165 MC: Zone 1 Health and Natural Resources New Hill, North Carolina 27562 Division of Radiation Protection Post Office Box 27687 Mr. W. R. Robinson Raleigh, North Carolina 27611-7687 Plant Manager Carolina Power & Light Company Mr. Robert P. Gruber Shearon Harris Nuclear Power Plant Executive Director Post Office Box 165 Public Staff - NCUC New Hill, North Carolina 27562 Post Office Box 29520 Raleigh, North Carolina 27626-0520 Mr. R. A. Anderson Vice President Resident Inspector Carolina Power & Light Company U. S. Nuclear Regulatory Commission Brunswick Nuclear Electric Plant Star Route 1, Post Office Box 208 Post Office Box 10429 Brunswick Steam Electric Plant Southport, North Carolina 28461 Southport, North Carolina 28461 Mr. Kelly Holden, Chairman Mr. C. C. Warren Board of Commissioners Plant Manager - Unit 2 Post Office Box 249 Carolina Power & Light Company Bolivia, North Carolina 28422 Brunswick Steam Electric Plant Post Office Box 10429 Southport, North Carolina 28461

Mr. J. M. Brown Plant Manager - Unit 1 Carolina Power & Light Company Brunswick Steam Electric Plant Post Office Box 10429 Southport, North Carolina 28461 Mr. Mark S. Calvert Associate General Counsel Carolina Power & Light Company Post Office Box 1551 Raleigh, North Carolina 27602 Public Service Commission State of South Carolina Post Office Drawer 11649 Columbia, South Carolina 29211