Forwards SER Re Response to Station Blackout Rule.Requests That Util Submit Proposed Reolution of Recommendations in SER within 30 Days of Receipt of Ltr
ML14184A793
Person / Time
Site: Robinson 
Issue date: 02/04/1991
From: Lo R
Office of Nuclear Reactor Regulation
To: Eury L
CAROLINA POWER & LIGHT CO.
Shared Package
ML14184A794 List:
References
TAC-68595, NUDOCS 9102110193
Download: ML14184A793 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 February 4, 1991 Docket No. 50-261 Mr. Lynn W. Eury Executive Vice President Power Supply Carolina Power & Light Company Post Office Box 1551 Raleigh, North Carolina 27602

Dear Mr. Eury:

SUBJECT:

STATION BLACKOUT RULE - H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 (TAC NO. 68595)

The Station Blackout (SBO) Rule requires licensees to submit information, as defined in 10 CFR Part 50.63, and to provide a plan and schedule for conformance to the S80 Rule. Your initial response to the SBO Rule regarding the H. B. Robinson Steam Electric Plant, Unit No. 2, (HBR-2) was provided by a letter from M. A. McDuffie, dated March 3, 1989, to the U.S. Nuclear Regulatory Commission (NRC). A supplemental response was submitted by a letter to the NRC from A. B. Cutter, dated March 30, 1990. This was followed by a teleconference between your representatives and the NRC staff on August 8, 1990, and a follow-up was provided by a letter from S. D. Floyd to A. S. Gill (NRC) on August 30, 1990.

Your responses were reviewed by the NRC staff and by Science Applications International Corporation (SAIC) under contract to the NRC. The results of the review are documented in the enclosed Safety Evaluation (SE) (Enclosure 1) and the SAIC Technical Evaluation Report (TER) SAIC-90/1379, "H. B. Robinson Steam Electric Plant, Unit 2, Station Blackout Evaluation," dated November 21, 1990 (Attachment 1 to Enclosure 1).

Carolina Power & Light Company (CP&L) has proposed using an existing diesel generator, presently used as the dedicated shutdown (DSD) system for 10 CFR Part 50, Appendix R, fire protection requirements, as the alternate AC (AAC) power source. The CP&L submitted the initial response to the SBO rule in the SBO generic response format. Based on our review of the initial response, and subsequent submittals,.the staff finds, subject to satisfactory resolution of the recommendations presented in the SE, that HBR-2 conforms with the SBO rule and the guidance of Regulatory Guide (RG) 1.155, NUMARC 87-00 and NUMARC 87-00 Supplemental Question/Answers and Major Assumptions dated December 27, 1989, (issued to the industry by NUMARC January 4, 1990). CP&L should submit, within 30 days of receipt of this letter, a proposed resolution of the recommendations presented in the enclosed SE and present a schedule for their implementation in accordance with 10 CFR 50.63(c)(4).

9102110193 910204 PDR ADOCK 05000261 P,

_PDR

Lynn February 4, 1991 In addition, the following areas may require a follow-up inspection by the NRC to verify that the implementation of any modifications and the supporting documentation are adequate to meet the SBO Rule. Inspection guidance is being developed for this as follows.

a. Hardware and procedural modifications,
b. SBO procedures in accordance with RG 1.155, Position 3.4, and NUMARC 87-00, Section 4,
c. Operator staffing and training to follow the identified actions in the procedures,
d. EDG reliability program to meet, as a minimum, the guidelines of RG 1.155,
e. Equipment and components required to cope with the SBO are incorporated in a QA program that would meet the guidance of RG 1.155, Appendix A, and
f. Actions taken pertaining to the specific recommendation noted in the SE.

The guidance provided by the Technical Specifications (TS) for a SBO states that the TS should be consistent with the Interim Commission Policy Statement on Technical Specifications. The staff has taken the position that TS are required for SBO response equipment. However, the question of how specifica tions for the SBO equipment will be applied is currently being considered generically by the NRC in the context of the Technical Specifications Improve ment Program and remains an open item at this time. In the interim, the staff expects plant procedures to reflect the appropriate testing and surveillance requirements to ensure the operability of the necessary SBO equipment. If the staff later determines that TS regarding the SB0 equipment is warranted, you will be notified of the requirements.

Sincerely, Ronbie H. Lo, Senior Project Manager Project Directorate II-1 Division of Reactor Projects -

I/II Office of Nuclear Reactor Regulation

Enclosure:

As Stated cc w/enclosure:

See next page DISTRIBUTION See attached page OFC

PM:PDI
D:PDTII NAME :LE~r K0_
RLo:s
EAde sam DATE :/

/91

//9 OIGIAL RORD COPY Document Name:

LTR LYNN W. EURY 68595

Mr. L. W. Eury H. B. Robinson Steam Electric Carolina Power & Light Company Plant, Unit No. 2 cc:

Mr. R. E. Jones, General Counsel Mr. Dayne H. Brown, Director Carolina Power & Light Company Department of Environmental, P. 0. Box 1551 Health and Natural Resources Raleigh, North Carolina 27602 Division of Radiation-P'rotection P. 0. Box 27687 Raleigh, NoNth Carolina 27611-7687 Mr. H. A. Cole Special Deputy Attorney General Mr.-kobert P. Gruber State of North Carolina Eiecutive Director P. 0. Box 629 Public Staff -

NCUC Raleigh, North Carolina 27602 P. 0. Box 29520 Raleigh, North Carolina 27626-0520 U.S. Nuclear Regulatory Commission Mr. C. R. Dietz Resident Inspector's Office Manager, Robinson Nuclear Project H. B. Robinson Steam Electric Plant Department Route 5, Box 413 H. B. Robinson Steam Electric Plant Hartsville, South Carolina 29550 P. 0. Box 790 Hartsville, South Carolina 29550 Regional Administrator, Region II U.S. Nuclear Regulatory Commission Mr. Heyward G. Shealy, Chief 101 Marietta Street Bureau of Radiological Health Suite 2900 South Carolina Department of Health Atlanta, Georgia 30323 and Environmental Control 2600 Bull Street Mr. R. Morgan Columbia, South Carolina 29201 General Manager H. B. Robinson Steam Electric Plant P. 0. Box 790 Hartsville, South Carolina 29550

DISTRIBUTION

,-Docket File NRC PDR Local PDR S. Varga 14-E-4 G. Lainas 14-H-3 L. Reyes RII E. Adensam 14-B-20 P. Anderson 14-B-20 R. Lo 14-B-20 A. Toalston OGC (For inform. Only) 15-B-18 E. Jordan MNBB-3302 ACRS (10)

P-315 Robinson File