Discusses 900809 Region II Review of Emergency Response Facilities.Summary of Mods by Area Which Would Enhance NRC Ability to Respond to Site Encl
ML14184A740
Person / Time
Site: Robinson 
Issue date: 08/30/1990
From: Dan Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Eury L
CAROLINA POWER & LIGHT CO.
References
IEIN-86-018, IEIN-86-18, NUDOCS 9010010061
Download: ML14184A740 (5)


Text

AUG 3 0 1990 Docket No. 50-261 License No. DPR-23 Carolina Power and Light Company ATTN:

Mr. Lynn W. Eury Executive Vice President Power Supply P. 0. Box 1551 Raleigh, NC 27602 Gentlemen:

SUBJECT:

REVIEW OF EMERGENCY RESPONSE FACILITIES On August 9, 1990, Ms. A. 1. Ecland of the Region II staff conducted a review of the emergency response facilities at your H. B. Robinson site.

The review focused on the availability of workspiace and communications for NRC personnel in the event an Agency response is warranted for an incident at your site.

Facility tours were conducted in the Control Room, Technical Support Center, Cperations Support Center, Emergency Operations Facility, and Joint Information Center in order to identify current NRC resources as well as understand Robinson's emergency organization and response philosophy.

Concurrently, discussions were held with members of the Corporate and site emergency planniry staffs regarding NRC's Incident Response organization (Information Nctice P-18) and ways of most effectively integrating the NRC response into your existing Emergency Plans based uporn your organization and space and equipment capabilities. In addition, the lessons learned from NRC's participation in the.

1988 Brunswick exercise were factored into the review, due to the similarity in response facilities between the two sites.

A summary of the modifications by area which would enhance NRC's ability to effectively respond to the H. B. Robinson site is provided in the Enclosure.

Your staff indicated that incorporation of these items could be accommodated;

however, due to the fact that the location of the joint Information Center is changing in the near future, it was agreed that the recommendations for NRC accommodations would be deferred and incorporated into the new facility (scheduled for early 199]).

We appreciate the cooperation of your staff in determining the most effective and Efficient means of satisfying NRC's logistical and communications needs.

We believe the modifications proposed will enhance our ability to work 90101 9CI 008 30o PDR Aok050026

Carolina Power and Light Company 2

effectively with your staff in mEeting our overall responsibilities during an emergency.

Should any impediments or questions be encountered during implementation please contact A. Boland of my staff at 404-331-3758.

Sincerely, 0

!NA SIGWO 9Y C0UG2LAS M. CO&I.NS Douglas M. Collins, Chief Emergency Preparedness and Radiological Protection Eranch Division of Radiation Safety and Safeguards

Enclosure:

Modifications/Additions to NRC Response Resources cc w/encl:

C. R. Dietz, Manager Pobinscro Nuclear Project Department H. P. Robinson Steam Electric Plant P. 0. Box 790 Hartsville, SC 29550 R. E. Morgan, Plant General Manager H. B. Robinson Steam Electric Plant P. 0. Box 790 Hartsville, SC 29550 Heyward G. Shealy, Chief Bureau of Radiolocical Health Dept. cf Health and Environmental Control 2600 Bull Street Columbia, SC 29201 Dayne H. Brown, Director Division of Radiation Protection N. C. Department of Environment, Health & Natural Resources P. C. Box 27687 Raleigh, NC 27611-76&7 (cc w/encl:

Cont'd on page 3)

Carolina Power and Light Company 3

(cc w/encl: cont'd)

McCuen Morrell, Chairman Darlington County Board of Supervisors County Courthouse Darlington, SC 29535 Richard E. Jones, General Counsel Carolina Power and Light Company P. 0. Box 1551 Raleigh, NC 27602 H. A. Cole Special Deputy Attorney General State of North Carolina P. 0. Box 629 Raleigh, NC 27602 Robert Gruber Executive Director Public Staff -

NCUC P. 0. Box 29520 Raleigh, NC 27626-0520 bcc w/encl:

Document Control Desk NRC Resident Inspector U.S. Nuclear Regulatory Commission Route 5, Box 413 Hartsville, SC 29550 RI

DRSS RII: RP A

nd akin DVerrelli 08/,f/90 08/-It/90

ENCLOSURE MODIFICATIONS/ADDITIONS TO NRC RESPONSE RESOURCES Control Room o

Provisions for the use of I telephone in the Shift-Technical Advisor's Office for the NRC Resident Inspector.

Operations Support Center o

Provide 1 telephone for use by NRC Health Physics personnel.

(This was satisfied by provicing an already existing telephone located in the shop area - #1659).

Technical Support Center o

Add workspace and 1 telephone at the TSC Management Table next to the Radiological Control Director for the NRC Radiological Safety Coordinator.

  • Add 1 table and 2 telephones (accommodating 2) to the NRC area in the main TSC Command Room.

o Transfer the multiline RCLM phone currently ib NRC area in the main TSC Command Room to the already established NRC seat at the TSC Management Table for the NRC Operations Coordinator/Resident Inspector.

o Relocate ENS and HPN phones from NRC Room to the location of the Robinson communicators, thus providing an.ENS link for both NRC and licensee use in the main TSC Command Room.

Emergency Operations Facility 0

Provide additional work space at the EOF Management Table next to the NRC Director of Site Operations for the NRC Emergency Response Coordinator (no additional communications needed).

o Reconfigure NRC workspace in the main EOF Command Room to accommodate 7-8 persons rather then 4.

This area would then include NRC communicators, the Government Liaison Coordinator, the Protective Measures Coordinator, and the Reactor Safety Coordinator.

o Ado 3 telephones to the NRC workspace in Main EOF Command Room discussed in previous item.

a Provide workspace in Dose Assessment and Environmental Monitoring Area for the co-location 3 people (Dose Assessment Coordinator, Environmental Dose Assessment Coordinator, and Environmental Coordinator) with 1 standard telephone line and 1.

modem-line telephone.

Enclosure 2

o Move the HPN and ENS from NRC Room to NRC Area in Main Command Room.

Joint Information Center 0

Add 1 modem-line telephone for use with a computer.