Forwards SER of Util Responses Re USI A-46 Implementation at Hb Robinson Steam Electric Plant,Unit 2 in Resolution of Unresolved Safety Issue as Described in Suppl 1 to GL 87-02. Staff Determined That C/As & Physical Mods,Satisfactory
ML14183A873
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 10/15/1998
From: Subbaratnam R
NRC (Affiliation Not Assigned)
To: Young D
CAROLINA POWER & LIGHT CO.
Shared Package
ML14183A874 List:
References
REF-GTECI-A-46, REF-GTECI-SC, TASK-A-46, TASK-OR GL-87-02, GL-87-2, TAC-M69478, NUDOCS 9810200231
Download: ML14183A873 (5)


Text

October 15, 1998 Mr. D. E. Young, Vice Pr*ent Carolina Power & Light Company H. B. Robinson Steam Electric Plant, Unit No. 2 3581 West Entrance Road Hartsville, South Carolina 29550

SUBJECT:

COMPLETION OF LICENSING ACTION FOR GENERIC LETTER 87-02, EVALUATION OF H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2, RESOLUTION OF UNRESOLVED SAFETY ISSUE (USI) A-46, SUPPLEMENT NO. 1 TO GENERIC LETTER (GL) 87-02 (TAC NO. M69478)

Dear Mr. Young:

Enclosed is the Nuclear Regulatory Commission's (NRC's) Safety Evaluation of Carolina Power

& Light Company's responses concerning the USI A-46 implementation program at H. B.

Robinson Steam Electric Plant, Unit 2 (HBRSEP2). This was in resolution of Unresolved Safety Issue (USI) A-46, as described in Supplement No. 1 to GL 87-02. The focus of GL 87-02 was to verify if the licensee's physical modifications for resolution of outliers at HBRESP2 were adequate.

The NRC staff has determined that the licensee's corrective actions and physical modifications for resolution of outliers were satisfactory and found to be sufficient to close the USI A-46 review at the facility. The staff also concluded that the licensee's implementation program to resolve USI A-46 has adequately addressed the purpose of the 10 CFR 50.54(f) request.

Therefore, we consider GL 87-02 closed for your facility. However, your activities related to the USI A-46 implementation may be subject to NRC inspection.

If you have any questions regarding this matter, please contact Ram Subbaratnam at (301) 415-1478.

Sincerely, Original signed by:

Ram Subbaratnam, Project Manager Project Directorate 11-3 Division of Reactor Projects - I/Il Office of Nuclear Reactor Regulation

Enclosure:

Safety Evaluation Docket No. 50-261 cc: See next page V117 DISTRIBUTION:

Docket File JMa, NRR JZwolinski AJLee,NRR DDorman, NRR OGC PUBLIC RPelton, NRR LPlisco, Region II IO PDII-3 Reading File ACRS DOCUMENT NAME:G:\\ROBINSON\\M69478.CLO To receive a copy of this document, indicate in the box: "C" = Copy without enclosures "E" = Copy with enclosures "N" = No copy OFFICE PDII-3:PM I

PDII-2:LA I t PDIl-3:PD C

NAME Ram Subbaratnam EDunnington 19?

FHebdon DATE 10/5/98 1//198 10/0798 1

OFFICIAL RECORD COPY 9810200231 98i118~

PDR ADOCK 05000261 P

PDR

October 15, 1998 Mr. D. E. Young, Vice Pr ent Carolina Power & Light Company H. B. Robinson Steam Electric Plant, Unit No. 2 3581 West Entrance Road Hartsville, South Carolina 29550

SUBJECT:

COMPLETION OF LICENSING ACTION FOR GENERIC LETTER 87-02, EVALUATION OF H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2, RESOLUTION OF UNRESOLVED SAFETY ISSUE (USI) A-46, SUPPLEMENT NO. 1 TO GENERIC LETTER (GL) 87-02 (TAC NO. M69478)

Dear Mr. Young:

Enclosed is the Nuclear Regulatory Commission's (NRC's) Safety Evaluation of Carolina Power

& Light Company's responses concerning the USI A-46 implementation program at H. B.

Robinson Steam Electric Plant, Unit 2 (HBRSEP2). This was in resolution of Unresolved Safety Issue (USI) A-46, as described in Supplement No. 1 to GL 87-02. The focus of GL 87-02 was to verify if the licensee's physical modifications for resolution of outliers at HBRESP2 were adequate.

The NRC staff has determined that the licensee's corrective actions and physical modifications for resolution of outliers were satisfactory and found to be sufficient to close the USI A-46 review at the facility. The staff also concluded that the licensee's implementation program to resolve USI A-46 has adequately addressed the purpose of the 10 CFR 50.54(f) request.

Therefore, we consider GL 87-02 closed for your facility. However, your activities related to the USI A-46 implementation may be subject to NRC inspection.

If you have any questions regarding this matter, please contact Ram Subbaratnam at (301) 415-1478.

Sincerely, Original signed by:

Ram Subbaratnam, Project Manager Project Directorate 11-3 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation

Enclosure:

Safety Evaluation Docket No. 50-261 cc: See next page DISTRIBUTION:

Docket File JMa, NRR JZwolinski AJLee,NRR DDorman, NRR OGC PUBLIC RPelton, NRR LPlisco, Region II PDII-3 Reading File ACRS DOCUMENT NAME:G:\\ROBINSON\\M69478.CLO To receive a copy of this document, indicate in the box: "C" = Copy without enclosures "E" = Copy with enclosures "N" = No copy OFFICE PDII-3:PM PDII-2:LA C

PDII-3:PD NAME Ram Subbaratnam EDunnington FHebdon DATE 10/' /98 !Zz~

//98 100/98 OFFICIAL RECORD COPY

~p RE UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20585-001 October 15, 1998 Mr. D. E. Young, Vice President Carolina Power & Light Company H. B. Robinson Steam Electric Plant, Unit No. 2 3581 West Entrance Road Hartsville, South Carolina 29550

SUBJECT:

COMPLETION OF LICENSING ACTION FOR GENERIC LETTER 87-02, EVALUATION OF H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2, RESOLUTION OF UNRESOLVED SAFETY ISSUE (USI) A-46, SUPPLEMENT NO. 1 TO GENERIC LETTER (GL) 87-02 (TAC NO. M69478)

Dear Mr. Young:

Enclosed is the Nuclear Regulatory Commission's (NRC's) Safety Evaluation of Carolina Power

& Light Company's responses concerning the USI A-46 implementation program at H. B.

Robinson Steam Electric Plant, Unit 2 (HBRSEP2). This was in resolution of Unresolved Safety Issue (USI) A-46, as described in Supplement No. 1 to GL 87-02. The focus of GL 87-02 was to verify if the licensee's physical modifications for resolution of outliers at HBRESP2 were adequate.

The NRC staff has determined that the licensee's corrective actions and physical modifications for resolution of outliers were satisfactory and found to be sufficient to close the USI A-46 review at the facility. The staff also concluded that the licensee's implementation program to resolve USI A-46 has adequately addressed the purpose of the 10 CFR 50.54(f) request.

Therefore, we consider GL 87-02 closed for your facility. However, your activities related to the USI A-46 implementation may be subject to NRC inspection.

If you have any questions regarding this matter, please contact Ram Subbaratnam at (301) 415-1478.

Sincerely, Ram Subbaratnam, Project Manager Project Directorate 11-3 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation

Enclosure:

Safety Evaluation Docket No. 50-261 cc: See next page

Mr. D. E. Young H. B. Robinson Steam Electric Carolina Power & Light Company Plant, Unit No. 2 cc:

Mr. William D. Johnson Mr. Mel Fry, Director Vice President and Senior Counsel N.C. Department of Environment Carolina Power & Light Company and Natural Resources Post Office Box 1551 Division of Radiation Protection Raleigh, North Carolina 27602 3825 Barrett Dr.

Raleigh, North Carolina 27609-7721 Ms. Karen E. Long Assistant Attorney General Mr. Robert P. Gruber State of North Carolina Executive Director Post Office Box 629 Public Staff - NCUC Raleigh, North Carolina 27602 Post Office Box 29520 Raleigh, North Carolina 27626-0520 U.S. Nuclear Regulatory Commission Resident Inspector's Office Mr. Virgil R. Autry, Director H. B. Robinson Steam Electric Plant South Carolina Department of Health 2112 Old Camden Road Bureau of Land & Waste Management Hartsville, South Carolina 29550 Division of Radioactive Waste Management 2600 Bull Street Regional Administrator, Region II Columbia, South Carolina 29201 U.S. Nuclear Regulatory Commission Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Ms. D. B. Alexander Atlanta, Georgia 30303 Manager Performance Evaluation and Mr. J. W. Moyer Regulatory Affairs CPB 9 Director of Site Operations Carolina Power & Light Company Carolina Power & Light Company Post Office Box 1551 H. B. Robinson Steam Electric Plant Raleigh, North Carolina 27602-1551 Unit No. 2 3581 West Entrance Road Hartsville, South Carolina 29550 Chief, Reactor Projects Branch 4 U. S. Nuclear Regulatory Commission Public Service Commission Atlanta Federal Center State of South Carolina 61 Forsyth St., SW, Suite 23T85 Post Office Drawer 11649 Atlanta, Georgia 30303 Columbia, South Carolina 29211 Mr. T. M. Wilkerson Manager - Regulatory Affairs Mr. H. K. Chernoff Carolina Power & Light Company Supervisor, Licensing/Regulatory Programs H. B. Robinson Steam Electric Plant, Carolina Power & Light Company Unit No. 2 H. B. Robinson Steam Electric Plant, 3581 West Entrance Road Unit No. 2 Hartsville, South Carolina 29550-0790 3581 West Entrance Road Hartsville, South Carolina 29550

Mr. Jim Fisicaro Mr. Neil Smith, Chairman Duke Energy Corporation Seismic Qualification Utility Group P.O. Box 1006 (ECO7Q) clo MPR Associates, Inc.

Charlotte, North Carolina 28201-1006 320 King Street Alexandria, Virginia 22314