ML14178A410

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/93-25 on 931018-22.Violations Noted.Major Areas Inspected:Piping Sys Mods & TSs Snubber Insps
ML14178A410
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 11/16/1993
From: Blake J, Chou R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14178A408 List:
References
50-261-93-25, NUDOCS 9312140077
Download: ML14178A410 (9)


See also: IR 05000261/1993025

Text

UNITED STATES

0

NUCLEAR REGULATORY COMMISSION

REGION II

o0

101 MARIETTA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

Report No.:

50-261/93-25

Licensee: Carolina Power and Light Company

P. 0. Box 1551

Raleigh, NC 27602

Docket No.:

50-261

License No.:

DPR-23

Facility Name: H. B. Robinson

Inspection Conducted:

October 18 -

22, 1993

Inspector:

/L/1), /

,

7?,

R. C. Chou

Date Signed

Approved by:

/

/

/ 3

.J.

B1 *-,Chief

Date Signed

Mat ia nd Processes Section

En ne

ing Branch

Di ision of Reactor safety

SUMMARY

Scope:

This routine, announced inspection was conducted in the areas of piping system

modifications and Technical Specification snubber inspections.

Results:

In the areas inspected, two violations were identified. No deviations were

identified. The violations are failure to verify eight missing welds in field

for two supports and the purchase order for the material installed for a

support by the quality control (QC) inspectors and construction foremen. The

licensee has weaknesses in the review of the completed products performed by

the QC inspectors and foremen.

9312140077 931117

PDR ADOCK 05000261

G

PDR

REPORT DETAILS

@1.

Persons Contacted

License Employees

  • R. L. Barnett, Project Management Manager
  • D. Baur, Regulatory Affairs Specialist
  • R. Beverage, Quality Control (QC) Supervisor
  • T. Cleary, Technical Support Manager

D. Crook, Regulatory Affairs Senior Specialist

  • J. M. Curley, Engineering Support Manager
  • C. R. Dietz, Vice President on site
  • D. Dyksterhouse, Project Manager - Civil
  • W. Farmer, Inservice Inspection (ISI) Manager
  • M. Pearson, Plant Manager
  • C. S. Olexik, Assessment Section Manager
  • D. Waters, Regulatory Affairs Manager

J. Noble, Modification Coordinator

Other licensee employees contacted during this inspection included

craftsmen, engineers, mechanics, technicians, and administrative persons.

Other Organizations

PPM

T. Roland, Modification Implementation Unit (MIU) Coordinator

NRC Resident Inspector

  • C. Ogle, Resident Inspector
  • Attended Exit interview

2. Piping System Modification

The licensee had completed several modifications in piping systems before

and during the current refueling outage. A major modification is Mod.

No. 1104 which includes the modification of about 150 pipe supports in

several piping systems in the Containment, Reactor Auxiliary, and Turbine

Buildings.

The inspector randomly selected 18 pipe supports with modifications

completed before or during this refueling outage. The 18 pipe supports,

in safety related systems and Non-Safety related systems with seismic

design, were all in large bore piping. They involved Auxiliary Cooling

System, Chemical and Volume Control System, Fire Protection System, and

Safety Injection System in the pipe alley of Reactor Auxiliary Building

and for Auxiliary Feedwater System (portions of supports inspected are in

Non-Safety related system with seismic design) and Feedwater System in

the Turbine Building. The licensee treated the non-safety related but

seismically qualified piping systems as safety related piping systems

2

since those non-safety related but seismically qualified systems must be

prevented from falling and damaging the safety related piping systems,

structures, or equipment during earthquakes.

The walkdown reinspection was completed with assistance from the

licensee's engineers and QC inspector who was also qualified as a welding

inspector. The major acceptance criteria and procedures used by the

licensee's QC inspectors for the modifications are listed below:

-

Specification No. CPL-HBR2-C-011, Civil Inspection

Requirements

-

Modification Implementation Program MIP-200, Installation and

Inspection of Equipment, Supports, and Components

-

Corporate Weld Manual (CWM)

-

Maintenance Management Procedure MMM-028, Control of Field

Issued Material

The supports were partially reinspected, particularly for the current

modifications, against the detail drawings and procedures. They were

checked for configuration, identification, fastener/anchor installation,

anchor size, anchor type, anchor marking, anchor edge distance, base

plate size and thickness, plate warpage, member size, weld sizes,

component identification numbers, component sizes and settings, dimen

sions, oxidation accumulation, maintenance, welder identification,

purchase order, mark on materials, and damage protection. The supports

reinspected during the current inspection are listed below:

Table 1

Walkdown Reinspection Supports

Item No. Support No.

Rev. No. System

Bldg

Discrepancies/

Comments

1

AC-6-4055

A

AC

RAB

2

CH-6-117

lB

CVC

RAB

Two additional

attachments were

not shown in the

drawings.

3

CH-6-6004

A

CVC

RAB

4

FP-1-155

A

FP

RAB

5

FP-2-110

A

FP

RAB

6

SI-20-237

OA

SI

RAB

3

7

SI-20-1200

2A

SI

RAB

8

WD-1-185

A

WD

RAB

9

FW-1-6226

A

AFW

TB

10

FW-1-7234

A

AFW

TB

11

FW-1-7241

A

AFW

TB

12

FW-6B-73

2A

FW

TB

Four welds are

missing in two

base plates

between the stiff

ener plates and

base plates.

13

FW-6C-109

2A

FW

TB

Same as FW-6B-73

14

FW-7-33A

A

AFW

TB

Construction ID

SS-2232

15

FW-7-33C

A

AFW

TB

The purchase order

PO 710701 Item 2

was found in east

pipe clamps. The

document was

signed off as

purchase order PO

7G0046, Item 1.

Construction ID

SS-2233.

16

FW-7-40A

A

AFW

TB

Construction ID

SS-2234

17

FW-7-54B

A

AFW

TB

18

FW-7-54C

A

AFW

TB

Notes:

1. Abbreviation Symbols:

a. AC

-

Auxiliary Coolant System

b. CVC -

Chemical and Volume Control System

c. FP

-

Fire Protection System

d.

SI

-

Safety Injection System

4

e. WD -

Waste Disposal System

f. AFW -

Auxiliary Feedwater System

g.

FW -

Feedwater System

h. RAB -

Reactor Auxiliary Building

i. TB -

Turbine Building

2. Item 14 FW-7-33A to Item 18 FW-7-54C are non-safety related but

seismically qualified supports.

Support AC-6-4055 required a partial penetration weld to connect a new

base plate to the existing base plate. Support CH-6-117 required a full

penetration weld to connect a new base plate to the existing base plate.

The inspector could not determine if those two new welds were full or

partial penetration welds by visual inspection since the new and existing

base plates had been painted.

Support WD-1-185 required a full penetration weld to connect two plates

in the air off walls or floors to restrain the pipe. The inspector could

see evidence of weld on both sides of the plate and therefore, concluded

that this weld connection was a full penetration weld even though the

plates were painted over.

Support CH-6-117 was found to have two additional attachments, a tube

track unistrut and an instrument support FI-60168, which were not shown

in the drawings. Prior to the modifications, the licensees design

engineers had requested field information and found that the two new

attachments added about 10 percent additional loads, but decided not to

include them in the analysis due to the relatively small addition. The

licensee's engineers recognized the mistake of not including those loads

in the analysis and agreed to revise the calculations and drawings to

include those additional supports.

Support SI-20-237 was found with Item 14, angle steel, shown on the wrong

side of Item 1 in the drawing. The licensee's engineers stated that they

had found this problem during their previous inspection and were in the

process of revising the drawings.

Supports FW-6B-73 and FW-6C-109 were found to have four welds missing in

each support between the connections of base plates and long stiffener

plates. The licensee's engineers stated that those missing welds were

part of modification for plant Mod. 988 during Refueling Outage 13 (the

last refueling outage). The design for that modification required those

welds. The QC documentation for support/restraining welding, the Seismic

Weld Data Report (SWDR) was signed off as having all required welds

complete. The SWDR used at that time does not delineate specific welds

inspected therefore the specific inspection of the weld in question can

not be identified. The licensee concluded that the installers did not

make the missing welds and the QC inspectors did not note that the welds

5

had not been made. The licensee's engineers re-reviewed the calculation

and concluded that the missing welds are not required, therefore, there

is no impact on the safety of the unit. The licensee will revise the

drawings to reflect the as-built weld configuration.

10 CFR 50, Appendix

B, Criteria X, requires that examinations, measurements, or tests of

material or products processed shall be performed for each work operation

where necessary to assure quality. Robinson Nuclear Plant Unit 2

Specification No. CPL-HBR2-C-011, Civil Inspection Requirements required,

at Section 6.2.3, welded connection, verify that welds are in accordance

with design documents. Section 9.0 of this specification and, at Section

3.2.2 of Attachment G, requires that when restraint sketches provide weld

information, size, type, length if any defect were detected they shall be

verified. Contrary to the above, four welds at each support were missing

in the field and were not noted by the installers and QC inspectors.

This missing weld problem is identified as Violation 50-261/93-25-01,

Missing Welds at Supports FW-6B-73 and FW-6C-109.

During the inspection, the inspector could not find the welder identifi

cation (ID)

number and material purchase order marked or stenciled in

half of the 10 sway struts inspected due to the combination of paint and

"light" marks. To show the welder ID and purchase order having been

marked in the installed materials, the licensee removed paint from four

sway strut supports. The welder ID and purchase order are required to be

marked by procedures. Support FW-7-33C also called SS-2233 was found to

have material purchase order PO-710701 marked in the pipe clamps in the

east side. The Installation Data Report (IDR) for Support No. SS-2233

(this is the construction identification number for the support in the

field) was signed off as PO-7G0046, Item 1 by the installer and verifier

(QC inspector) on September 22, 1993.

Per the purchase and warehouse procedures, the sway strut supports

normally consisting of end attachment, strut pipe and adjusters, and pipe

clamps, are purchased as an assembly, with the same purchase order, and

which were marked individually on the three parts by the Quality Assur

ance (QA) inspectors after the assembly had been received and accepted.

Therefore, the purchase order marked on the three parts of the installed

sway strut support No. FW-7-33C should be the same and as documented in

the IDR.

(Per construction coordinator, it is a normal process to

discard the entire assembly if part or portion of the assembly was

damaged or could not be repaired.) The materials installed with the

different purchase order without the approval from the supervisor and

without the document revision were unacceptable. The construction

foremen and the QC inspector apparently did not adequately review or

verify that the final installed products met the requirements and were as

received from the warehouse. There may have been some existing problems

between receiving the right materials and installing the wrong materials

without the notice of the construction foremen and QC inspectors. CP&L

Robinson Technical Specification in Section 6.5.1, Procedures, Tests, and

Experiments, requires that written procedures shall be established,

implemented, and maintained covering the activities recommended in

Appendix "A" of Regulatory Guide 1.33, Rev. 2, February 1978.

6

CP&L Robinson Maintenance Management Procedure No. MMM-028, Control of

Field Materials, requirements are as stated below:

Section 5.4.1.1 -

This number (purchase order number) is the pri

mary identification for traceability of most

material used.

Section 5.4.1.2 -

All identification transfer operations shall

include the transfer of this number (purchase

order number) unless authorized otherwise by

Maintenance or Modification Implementation Unit

(MIU) Supervision.

Section 5.9.2 -

Maintenance and MIU Supervision shall ensure

that the proper material is used and installa

tion documents are properly marked to indicate

the job on which the material was installed.

Contrary to the above, the purchase order number PO-710701, Item 2 at

pipe clamps installed in east side for Pipe Support FW-7-33C (Special

Support SS-2233) was different from the purchase order number PO-7G0046,

Item 1 for the material received from the warehouse. This problem is

identified as Violation 50-261/93-25-02, Material Purchase Order Differ

ences between the Field Installation and Documents for Support

FW-7-33C.

During the inspection in the Turbine Building area, the inspector noticed

that two anchor bolt nuts for support FW-6B-59 have gaps (no contact)

between the nuts and base plates. The licensee's engineers will issue a

nonconformance report to repair the gaps.

The inspectors asked the licensee's engineers about the current practice

for establishing hold points on welding. They provided an example

consisting of page 29 of Attachment 6, of IDR for construction of Support

ID SS-2232 (design drawing No. FW-7-33A). This page contained seven QC

hold points as indicated by the licensee hold point terminology. They

considered that each step requires QC to verify or sign on the document

as a hold point. Actually, some steps can be combined and signed at one

time because the succeeding step would not cover up and preclude inspec

tion of the previous step. Therefore, the actual hold point may be that

QC verifies and signs a couple of steps in the documents.

There were seven steps in this example for a weld inspection for the

connection between the cut end of a strut pipe and the adjuster. These

are:

1. Verify use of approved fixture and fixture number

2. Verify end preparation on extension piece (pipe)

3. Fit-up (including tack weld)

7

4. Surface inspection

5. Visual examination of root pass weld

6. Visual examination of final weld

7. Verify location of sight hole

The normal practice is that the above seven steps are combined into four

hold points as:

1. Hold point 1:

QC inspector will inspect steps 1 to 4 at same

time.

2. Hold point 2:

for step 5

3. Hold point 3:

for step 6

4. Hold point 4:

for step 7

The inspector did not see any problems for the above hold points and

signing off steps 1 to 4 in the same time for one hold point.

3. Snubber Inspection

All snubbers in safety-related systems, and non-safety related systems

required to protect safety-related systems, are required to be operable.

Technical Specification (TS) 4.13.1 requires 100 percent visual inspec

tion and ten percent functional testing of these snubbers during each

refueling outage. There are a total of 53 snubbers in Robinson plant and

most of them have been inspected during this refueling outage. Three

snubbers, No. 16, 32, and 36 had been found out of cold setting ranges

and were transferred to the engineering department for evaluation of

impact on the piping systems. The procedures used for snubber inspection

and reinstallation are listed below:

-

Engineering Surveillance Test Procedure EST-032, Visual Inspec

tion of Hydraulic and Mechanical Shock Suppressors,

Rev. 17.

-

CM-401, Removal and Reinstallation of Hydraulic and Mechanical

Shock Suppressors, Rev 13.

The inspector randomly selected seven snubbers for inspection. They are

Snubber Nos. 28, 29, 30, 31, 32, 33, and 34. All the snubbers inspected

are acceptable.

During the inspection, the inspector noticed that the current inspection

procedure did not require the snubber inspectors to inspect the support

ing structure for the snubbers and the gaps between washers and spherical

bearings at the both ends. The current practices are:

8

-

The snubber inspector will inspect the snubber from the end

bracket attachment point to the other attachment including the

base plate and anchor bolts if present. But the snubber

inspectors can go beyond and inspect the whole support if they

want. Inspection of the whole support is an option.

-

The snubber inspector will inspect the snubber rod paddle swing

angles to be within 5 degrees in each direction.

The above practices have deficiencies. If a snubber inspector just

inspects end-to-end of the snubber and is not required to inspect the

whole support structure for existing defects, the snubber may be in good

shape but the supporting structures might have defects which could not

support intended function of the snubber. The inspection of swing angle

within 5 degrees in each direction will prevent binding, but it could not

prevent excessive shifting or wear-out in the bearing and pin due to

vibrations or transients. A limited gap between washers and spherical

bearings at the both ends is required to prevent the excessive movement

and wear-out between the bearing and pin. The licensee's engineers

agreed to add the requirements in the next procedure revision to include

inspecting the whole support structure visually and establishing inspec

tion and acceptance criteria for the inspection of the gap between

washers and spherical bearings at the rod ends, near the brackets, or the

piston rod eyes, near the pipe clamps. No violations or deviations were

identified in this area.

4. Exit Interview

The inspection scope and results were summarized on October 22, 1993,

with those persons indicated in paragraph 1. The inspector described the

areas inspected and discussed in detail the inspection results listed

below. Proprietary information is not contained in this report.

Dissenting comments were not received from the licensee.

Violation 50-261/93-25-01, Missing Welds at Supports FW-6B-73 and

FW-6C-109.

Violation 50-261/93-25-02, Material Purchase Order Differences Between

the Field Installation and Documents for Support FW-7-33C.