ML14178A393

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/93-20 on 930913-17 & 27-1001.Violations Noted.Major Areas Inspected:Isi,Fac & Previous Violation Corrections
ML14178A393
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 10/21/1993
From: Blake J, Crowley B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14178A391 List:
References
50-261-93-20, NUDOCS 9311080231
Download: ML14178A393 (21)


See also: IR 05000261/1993020

Text

CIV '$O

R~a'9'UNITED

STATES

o

NUCLEAR REGULATORY COMMISSION

- 1

REGION II

0 o

101 MARIETTA STREET, N.W., SUITE 2900

C

ATLANTA, GEORGIA 30323-0199

Report Nos.: 50-261/93-20

Licensee: Carolina Power and Light Company

P. 0. Box 1551

Raleigh, NC, 27602

Docket Nos.: 50-261

License No.:

DPR-23

Facility Name: H. B. Robinson

Inspection Conducted: September 13-17 and September 27 - October 1, 1993

Inspectors:

,-.

,-

4

/

B. R. Crowley

Date Signed

Approved by:

[L--

fo

1

3

. J. Blake, Chief

Date Signed

at rials and Processes Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This routine, announced inspection was conducted on site in the areas of:

(1) Inservice Inspection (ISI), (2) Flow Accelerated Corrosion (FAC), and (3)

review of corrective actions for previous inspection findings.

Results:

In the areas inspected, one violation - failure to follow procedures for

calibration and certification of ET equipment - Paragraph 2.c.(7) - was

identified. No deviations were identified.

In the area of ISI, weaknesses were identified relative to lack of details in

administrative control procedures and coordination of examination preparation

and examinations. However, in general, the program appeared to be functioning

well.

Examinations were being conducted in a conscientious manner by

qualified personnel in accordance with approved procedures and required Codes.

Level III personnel were involved with the inspection process. Neat and

orderly records were being generated and maintained.

Relative to the FAC program, significant improvements were noted. Engineering

Design Guidelines had been issued and Engineering was involved in the process.

9311080231 931029

PDR ADOCK 05000261 1

0

PDR

&

2

Detailed site procedures and department guidelines had been issued to

implement the program.

All affected organizations, Operations, Maintenance,

Engineering, and Chemistry were involved in the program. A knowledgeable Site

FAC Coordinator was in place and ensuring that the program was properly

implemented. The Technical Support Department had a positive attitude about

implementing a good program. A Susceptibility Analysis of plant piping had

been performed and susceptible piping walked down and Isometric Drawing

prepared. The EPRI CHECMATE Model had been implemented and the Pass 1

analysis completed. An aggressive inspection program for the current outage

had been implemented to obtain data to further improve the program and predict

future wear.

REPORT DETAILS

1. Persons Contacted

Licensee Employees

  • T. Cleary, Manager, Technical Support
  • R. Crook, Senior Specialist, Regulatory Affairs
  • C. Dietz, Vice President, Robinson Nuclear Power Division
  • S. Farmer, Manager Inservice Inspection

C. Griffin, Senior Engineer, Nuclear Engineering Department

T. Freeman, Flow Accelerated Corrosion Coordinator

J. Lane, RCS System Engineer

  • C. Osman, Principle NDE Specialist, Technical Services

I. Simpson, Supervisor, NDE Services

P. Tingen, NED Technician

  • M. Vernon, Manager, NDE Services

D. Weber, Senior Inservice Inspection Specialist

Contractors

M. Baugh, QA/QC Welding Supervisor - Power Cutting Inc.

R. Brown, Manager, NDE Services - ABB Combustion Engineering Nuclear

40

Services, Steam Generator Project Manager

S. Larson, Level III Examiner - Nuclear Energy Services (NES)

T. Roland, Modification Implementing Hanger (MIH) Coordinator - Power

Plant Maintenance (PPM)

R. Valladares, Authorized Nuclear Inservice Inspector (ANII) - Hartford

Steam Boiler

Other licensee employees contacted during this inspection included

engineers, QA/QC personnel, craft personnel, security force members,

technicians, and administrative personnel.

NRC Employees

  • C. Ogle, Resident Inspector
  • W. Orders, Senior Resident Inspector
  • Attended exit interview

Acronyms and initialisms used throughout this report are listed in the

last paragraph.

2

2. Inservice Inspection (ISI)

The inspector reviewed documents and records, and observed activities, as

indicated below, to determine whether ISI was being conducted in accor

dance with applicable procedures, regulatory requirements, and licensee

commitments. The applicable code for ISI is the American Society of

Mechanical Engineers Boiler and Pressure Vessel (ASME B&PV) Code,

Section XI, 1986 Edition, except that the extent of examination for pipe

welds, category B-J, is the 1974 Edition, Summer 1975.

The third 10-Year interval started February 19, 1992 and ends February

19, 2002. This is the second outage of the first period of the third

interval.

The third 10-Year interval program was submitted in August, 1991.

Additional information was provided by letters dated February 13, 1992

and June 18, 1992. A total of 18 relief requests were submitted. The

NRC issued a Safety Evaluation Report (SER) on October 19, 1992. Relief

Request numbers 1, 2, 3, 5, 8, 12, and 18 were granted, number 13 was

granted with conditions, and all others were withdrawn by the licensee.

The site ISI organization in the Technical Support Department is

responsible for the 10-Year Program and issuing the Outage Plan. The

Corporate NDE Services Department is responsible for performing the

inspections. A contractor, presently NES, performs the NDE inspections

under the direction of the NDE Services Department. NDE procedures are

provided by the contractor and are issued under the licensee's program as

site procedures.

a. ISI Program Review (73051)

The inspector reviewed the documents listed below related to the ISI

program to determine whether relief requests had been approved by

NRR, the services of an Authorized Nuclear Inservice Inspector

(ANII) had been procured and the inspector was involved in ISI

activities, the plan had been approved by the licensee and to assure

that procedures and plans had been established (written, reviewed,

approved and issued) to control and accomplish the following appli

cable activities:

program organization including identification of

commitments and regulatory requirements, preparing plans and

schedules, and qualification, training, responsibilities, and duties

of personnel responsible for ISI; NDE personnel qualification

requirements; and guidance for identifying and processing relief

requests.

-

Carolina Power and Light H B Robinson Nuclear project Unit No 2

Third Ten year Inservice Inspection program Plan, Revision 0

-

CP&L PLP-025, Revision 25, In-Service Inspection Program

3

-

CP&L Examination Program Plan For Carolina Power and Light

Company H. B. robinson Unit 2 Inservice Inspection - Interval-3

Period-I Outage-2

-

CP&L SP-1235, Revision 0, Ultrasonic Linearity Verification

-

CP&L SP-1216, Revision 0, Calibration of Thermometers

-

CP&L SP-1221, Revision 0, Procedure for Certifying

Nondestructive Examination Personnel

-

NES 83A5464, Revision 1, Quality Assurance Program Plan For

Inspection and Related Services For Carolina Power and Light

Company

-

NES 80A9003, Revision 13, NES Document Control

-

NES 80A9022, Revision 10, Quality Assurance Audit Procedure

-

NES 80A9054, Revision 3, Calibration of Magnetic Particle

Examination Equipment

-

NES 80A9069, Revision 14, Certification of Visual Examination

Personnel

-

NES 809084, Revision 6, Nondestructive Examination Procedure

Qualification

-

NES 80A9099, Revision 8, Identification, Storage, and Retention

of Quality Assurance Records

Relative to review of programmatic controls, the inspector

identified the following weakness:

Administrative controls were not well defined procedurally in a

number of areas relative to the general operation of the ISI NDE

program. The following are examples of areas with weak procedural

details:

-

The overall description of how the program works, including

interface between the Site ISI Organization, Corporate NDE

Services Department, and the contractor.

-

Issue, control, and use of the outage plan.

-

Process for review and approval of inspection data, including

disposition of rejectable defects and sample expansion when

rejectable defects are found.

-

Reference system for identification and layout of welds.

-

Disposition of limited examinations.

4

Although these areas lacked procedural details, the inspector did

not identify specific problems resulting from this weakness.

b. Review of Procedures (73052)

The inspector reviewed the following NDE procedures to determine

whether these procedures were consistent with regulatory

requirements and licensee commitments. The procedures were reviewed

in the areas of procedure approval, requirements for qualification

of NDE personnel, compilation of required records, and division of

responsibility between the licensee and contractor personnel. In

addition, the procedures were reviewed for technical adequacy and

conformance with ASME, Sections V and XI, and other licensee

commitments/requirements.

-

SP-1217, Revision 0, Liquid Penetrant Examination Procedure

-

SP-1218, Revision 0, Magnetic Particle Examination Procedure

-

SP-1223, Revision 0, Ultrasonic Examination of Piping Welds and

Systems

-

SP-1230, Revision 0, VT-3 Visual Examination of Nuclear Power

Plant Components

-

SP-1220, Revision 0, PSI/ISI Examination Areas and Volumes

During review of the MT procedure, SP-1218, the inspector noted

conflicting requirements relative to verification of the strength of

MT Yokes.

Paragraph 8.2.2 requires verification at the beginning of

each shift.

Paragraph 9.1.1 states that daily verification is

recommended. Based on discussions with inspection personnel and

observation of inspections, the actual practice is verification

prior to each inspection. Therefore, the actual practice is more

conservative than the most conservative procedure requirement.

c. Observation of Work and Work Activities (73053)

The inspector observed work activities, reviewed NDE personnel

qualification records, and reviewed certification records of NDE

equipment/materials, as detailed below. The inspector verified:

availability of and compliance with approved NDE procedures, use of

knowledgeable NDE personnel, and use of NDE personnel qualified to

the proper level.

(1) Liquid Penetrant Examination (PT)

The inspector observed the in-process PT examinations as

indicated below. The observations were compared with the

inspection attributes of the applicable procedure and the ASME

B&PV Code to verify the performance of acceptable examinations.

5

Examinations Observed

Drawing

Welds/Component

CPL-125

1BC

CPL-125

3

CPL-125

4

(2) Magnetic Particle (MT) Examination

The inspector observed the in-process MT examinations as

indicated below. The observations were compared with the

inspection attributes of the applicable procedure and the ASME

B&PV Code to verify the performance of acceptable examinations.

Examinations Observed

Drawing

Welds/Component

CPL-205

6

CPL-212

7

CPL-212

7LS

(3) Ultrasonic (UT) Examination

The inspector observed the in-process UT examination of weld 7

on drawing CPL-212. The observations were compared with the

inspection attributes of the applicable procedure and the ASME

B&PV Code to verify the performance of acceptable examinations.

(4) Visual (VT) Examination

The inspector observed the in-process VT examinations as

indicated below. The observations were compared with the

inspection attributes of the applicable procedure and the ASME

B&PV Code to verify the performance of acceptable examinations.

Examinations Observed

Drawing

Support/Component

CPL-245

Hanger A

CPL-247

Hangers b, E, and G

6

(5) Eddy Current (ET) Examination

The Inspector observed the in-process ET data acquisition for

the steam generator (SG) tubes listed below. The data

acquisition was compared with the applicable procedure and the

ASME B&PV to verify acceptable data acquisition activities.

Examinations Observed

SG

Tube Row/Column

A

R35/C38

A

R33/C38

A

R30/C38

A

R35/C38

B

R11/C38

B

R9/C38

B

R6/C38

B

R12/39

B

R16/39

C - observed calibration activities

In addition to these observations, the inspector reviewed the

scan plans and discussed the planned inspection program with

licensee and contractor personnel.

The planned inspection

will include BOBBIN coil inspection of approximately 45% of

tubes in each SG. This will complete BOBBIN coil inspection of

100% of all tubes since the SGs were replaced. In addition,

Rotating Pancake Coil (RPC) inspections will be performed on

any questionable tube and selected tubes previously identified

with manufacturing burnish marks.

(6) Personnel Qualification/Certification

The inspector reviewed personnel qualification documentation as

indicated below for examiners who performed the examinations

detailed in paragraphs (1),

(2), (3), (4), and (5) above.

These personnel qualifications were reviewed in the following

areas:

employer's name; person certified; activity qualified

to perform; current period of certification; signature of

employer's designated representative; basis used for

certification; and, annual visual acuity, color vision

examination, and periodic recertification.

Examiner Records Reviewed

Method

Level

Employer

Number

PT

II

NES

5

PT

I

NES

1

MT

II

NES

4

UT

II

NES

3

7

Examiner Records Reviewed

Method

Level

Employer

Number

VT

II

NES

2

ET

II

ABB

3

In addition, qualification documentation for 1 level III

examiner (PT, MT, and UT) was reviewed.

(7) Equipment Certification Records

Equipment/material certification records, as listed below, for

equipment/materials used in the inspections detailed in

paragraphs (1),

(2), (3), (4), and (5) above were reviewed to

ensure compliance with applicable requirements.

Equipment Type

Equipment Identification

Penetrant Cleaner

Batch 92D02P

Penetrant

Batch 93E01K

Penetrant Developer

Batch 92A01P

Magnetic Particles

Batch 83L067

UT Transducer

Serial M12411

UT Transducer

Serial E18404

UT Instrument

Serial 27276-3702

UT Instrument

Serial 27276-749

UT Instrument

Serial 27276-807

UT Couplant

Batch 093001

ET Calibration Standard

Serial Z-8554

ET Calibration Standard

Serial Z-8555

ET Calibration Standard

Serial Z-8556

ET MIZ-18A RDAU

Serial 020

ET MIZ-18A RDAU

Serial 023

ET MIZ-18A RDAU

Serial 056

During review of the above certification records, the inspector

noted that the on site certification records for the MIZ-18A ET

equipment at the job site had expired for two sets of

equipment. Three sets of equipment (serial numbers 023, 056

and 195), one in each steam generator, were being used. After

further investigation, the ET contractor located the current

certification for equipment serial numbers 023 and 056 off-site

at their offices. However, certification records for equipment

serial number 195 could not be found. Attachment 8.3,

paragraph 7.0 of CP&L Procedure SP-1240, Revision 0, Steam

generator Eddy Current Testing During RFO 15, requires that the

MIZ-18A equipment be certified and that documentation of

calibration be provided prior to the start of the inspection.

Failure to follow procedure requirements for calibration and

certification of ET equipment is in violation of 10 CFR 50,

Appendix B, Criterion 5, and is identified as Violation (VIO)

261/93-20-01, Failure to Follow Procedures for Calibration and

8

Certification of ET Equipment. As immediate corrective action,

the ET contractor replaced equipment serial number 195 with a

set of qualified/certified equipment and re-inspected the SG

tubes that had been inspected with serial number 195 equipment.

Also, certification of UT characteristics for transducer serial

number M14135, used for inspection of weld 7 on Drawing CPL-212

was not available at the site. Although not a code requirement

to have this certification, it is industry practice to obtain

this certification from the transducer manufacturer to ensure

proper sound characteristics and repeatability of inspection

results. The licensee stated that they will obtain the

certification or, if not available, determine the transducer

characteristics and certify the transducer.

(8) Steam Generator Feedwater Nozzle to Reducer Welds

During a previous inspection (See NRC Inspection Report 50

261/92-92-14), the NRC inspector questioned the UT inspection

of the "C" SG Feedwater nozzle to reducer weld. The weld had

been re-examined to look for thermal fatigue cracks based on

cracking being found at another utility. Based on concerns of

the inspector relative to disposition of indications as

geometry in the area where cracking would be expected, the weld

and base material were re-inspected at the time of the 92-14

inspection. In addition to UT using a number of different

transducers, the weld and adjacent base material were

radiographed (RT).

Based on the additional UT inspection of

the questionable areas (16" to 32" clockwise looking toward the

SG), and comparison of the RT film to the original fabrication

RT film, it was concluded that the indications were caused by

geometry.

During the current inspection, the following UT inspections

were performed:

-

Loop A - Welds 1 (Reducer to Nozzle), 2 (Elbow to

Reducer), and 4 (Pipe to Elbow) were inspected using 00,

450 shear wave, and 600 shear wave transducers.

The

inspections included the entire surface of the reducer and

half of the elbow base material inspecting for thermal

fatigue cracking.

-

Loops B and C - The entire surface of the reducers and

half of the surface of the elbows were UT inspected using

0o, 450 shear wave, and 600 wave transducers inspecting

for thermal fatigue cracks. These inspections included

welds 1 and 2.

9

-

Loop C - The questionable area noted above (16" to 32"

clockwise) was inspected using 450 L-Wave and 600 L-Wave

transducers.

-

Techniques and personnel with demonstrated capability to

detect thermal fatigue cracks were used for these

inspections.

The inspector reviewed the UT shear wave inspection data and

observed the UT L-Wave inspections on the "C" loop. In

addition, the original fabrication RT film and the RT film from

the 1992 inspection were reviewed. Apparently the indications

have not changed since the last inspection. It appears that

the indications are geometric reflections from the reducer

counterbore. The RT film show a machining groove at the

intersection of the counterbore and counterbore taper. The

licensee plans to continue to inspect these areas during future

outages. In addition, the licensee has contacted Structural

Integrity Associates to: (1)

make a proposal for monitoring the

effectiveness of their control of the thermal fatigue cracking

in the feedwater piping, and (2)

determine the best

alternatives for material and configuration for pipe

replacements.

During observation of examination activities, the inspector noted a

general weakness relative to coordination of examinations and

preparation (scaffold erection, insulation removal, cleaning,

determination of Health Physics (HP) requirements, etc.) and

performance of examinations. The following are examples:

-

In attempting to inspect the pipe hangers identified in

paragraph (4) above, the examiners found that the required

clearances between the hangers and the pipe could not be

verified because the insulation had not been adequately

removed. Also, a significant amount of time was spent locating

the hangers.

-

About 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> was spent inside the radiation control area (RCA)

to perform PT inspection of the 3 welds identified in paragraph

(1) above. These are 2" diameter welds and are located in a

high radiation area. The cleaners entered the RCA to clean the

welds at the same time as the NDE examiners entered the RCA to

perform the inspection. HP did not swipe the area and

determine the full dress requirements until the cleaners and

examiners were ready to enter the high radiation area.

Requirements were added for paper outer clothing after everyone

was dressed, inside the RCA, and ready to enter the high

radiation area. Although the full 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> was not spent in the

high radiation area (much of the time was spent waiting in low

dose areas), the time inside the RCA could have been decreased

significantly with better planning.

10

-

During MT and UT examination of Main Steam system weld 7 on

drawing CPL-212, the inspector noted that other welds in the

same area required the same inspection, but could not be

inspected because of lack of cleaning, insulation removal, or

scaffold erection. This caused repeated calibrations and/or

entries into the RCA.

d. Inservice Inspection Data Review and Evaluation (73755)

In addition to review of in-process data for the inspections

observed in paragraph c. above, the inspector reviewed P-Scan UT

inspection data for SG girth weld 5 on SG "A".

As noted in NRC Inspection Report 50-261/92-13, UT indications were

identified in girth weld 5 for SGs "A" and "C" using manual UT

equipment in 1990. The indications appeared to be fabrication

flaws, but some exceeded the criteria of ASME Section XI, IWB-3500.

Based on flaw specific analysis, the indications were found to be

acceptable for the next 18 month operation cycle. Because of the

severe access restriction in obtaining reliable manual UT data, in

refueling outage (RFO) 14 in 1992, the licensee contracted with

Siemens Nuclear Power Services Inc. (SNPS) to perform a

mechanical/semi-automated P-Scan UT inspection of selected

indications in both SGs. This inspection was considered more

reliable, accurate, and repeatable than the manual inspection

because of the severe access restriction. This inspection showed

the indications to be smaller than thought based on the manual

inspection. Using the more accurate sizing of the P-scan

inspections, the indications met ASME Section XI, IWB-3500 without

the requirement for analysis. In addition to the P-Scan UT

inspection, the licensee MT inspected some of the inside of the SG

"A" weld at some of the indication locations which appeared to be

open to the surface. Only minor fabrication type flaws were found.

During the current outage, the licensee had SNPS re-perform the P

Scan UT examination on 5 selected indications in the "A" SG girth

weld to verify that the flaws have not changed. Although there was

some small changes in the indication sizes (some dimensions slightly

larger and others slightly smaller), the licensee concluded that the

changes were within the accuracy of the inspection method and setup.

The final conclusion was that the indications are acceptable

fabrication flaws and do not warrant further special inspection

monitoring. These welds will revert back to the normal inspection

schedule.

The inspector reviewed the preliminary P-Scan data and inspection

results for the current outage and a comparison with the previous

inspection results. It appears that licensee action for the SG

girth weld indications has been appropriate.

RESULTS

In the areas inspected, one violation, as detailed in paragraph c.(7),

was identified relative to use of non-certified SG tube ET equipment.

Weaknesses were identified relative to lack of details in administrative

control procedures (paragraph a. above) and coordination of examination

preparation and examinations (paragraph c. above).

However, in general,

the program appeared to be functioning well.

Examinations were being

conducted in a conscientious manner by qualified personnel in accordance

with approved procedures and required Codes.

Level III personnel were

involved with the inspection process. Neat and orderly records were

being generated and maintained.

3. Flow Accelerated Corrosion (FAC) Program (49001)

In response to Generic Letter (GL) 89-08, Erosion/Corrosion Pipe Wall

Thinning, licensee's have implemented long term Erosion/Corrosion (E/C)

or FAC programs. The licensee's FAC program was evaluated in an

inspection documented in NRC Inspection Report 50-261/92-13. During that

inspection the inspector identified a weak program, specifically citing

lack of corporate involvement and organization of the program. The

licensee acknowledged a weak program and indicated that improvements were

planned. The purpose of the current inspection was to evaluate the

status of the program and determine if an adequate program was in place.

The following is a summary of the inspection activities and results:

a. General

Based on discussions with licensee personnel, review of the

documents listed in paragraph b. below, and observation of the

inspections listed in paragraph c. below, the following actions have

been completed by the licensee:

-

A full time individual had been assigned as the Site FAC

Coordinator. A full time position at the corporate level has

been posted in the Nuclear Engineering Department (NED).

-

Corporate Design Guides have been issued to define the program

and site implementing procedures and guides have been issued.

Corporate is involved in defining the program and resolving

inspection findings.

-

ABB Impell was contracted in late 1992 through early 1993 to

walkdown systems, perform a susceptibility analysis for plant

systems, provide isometric drawings for susceptible systems,

and perform a CHECMATE Pass 1 Analysis.

12

-

CP&L Nuclear Assessment Department (NAD) performed an

assessment of the FAC program corporate wide, including

Robinson. Their report, NAD 93-504 was issued on September 9,

1993. The assessment identified a number of weaknesses in the

program. The weaknesses have been corrected or plans are in

place for correction.

-

For the current outage, the Robinson inspection plan includes

approximately 285 inspection locations in large bore piping

plus approximately 65 locations in small bore piping. The

selection of locations for inspection was based on the Pass 1

CHECMATE analysis, plant experience, industry experience, and

engineering judgement. The inspection results will be entered

into the CHECMATE model to perform the Pass 2 analysis.

In addition to the above completed actions, the Site FAC Coordinator

identified the following further program improvements planned to be

completed in the next six Months:

-

The NAD assessment noted that the Isometric Drawings are not

plant controlled drawings. The drawings will be converted to

plant controlled documents, errors corrected, and replacement

materials identified.

-

The 1994 budget has budgeted funds to: develop Isometric

Drawings for unmodelled, susceptible piping; fund CHUG

participation, and perform additional inspections in small bore

and isolable lines.

-

Backup FAC Coordinator will attend CHECMATE training in,

November.

-

Modify Work Request (WR) computer program (AMMS) to flag piping

replacements in secondary plant to help track replacements.

-

The Chemistry Group belongs to EPRI water chemistry group. The

Cycle 16 Plan includes raising Ph (additional hydrazine) and

consideration of ethanol amine treatment.

-

Plans are to develop a budget for replacement of small bore

lines with stainless steel for turbine shell drains, crossunder

drains, and steam dump bypass (keep-warm) piping.

b. Review of Procedures

The inspector reviewed the following documents which define the FAC

program

-

NED Design Guide DG-VII.5, Revision 0, Corporate Program for

Flow Accelerated Corrosion

13

-

NED Design Guide DG-VII.6, Revision 0, CHECMATE Modelling

Guideline

-

NED Design Guide DG-VII.7, Revision 0, Guideline for FAC

Component Selection, Sample Expansion, and Evaluation

-

ABB Impell Corporation Calculation No. 0132-00142-02, H. B.

Robinson Unit 2 Systems Elimination Calculation

-

PLP-051,, Revision 1, Flow Accelerated Corrosion (FAC)

monitoring Program

-

RFO-15 Project Plan - Erosion/Corrosion Monitoring Program

-

CP&L NAD Report NAD 93-504, Corporate Flow Accelerated

Corrosion Assessment Report

-

Technical Support Guideline TSG-210, Revision 0, FAC Program

Implementation

-

NDEP-427, Revision 0, Interim Change 1, Digital Ultrasonic

Thickness Measurement (Panametrics Model 26DL Plus) for

Erosion/Corrosion Detection and Monitoring

-

NDEP-1012, Revision 0, Gridding of Components for

Erosion/Corrosion

c. Observations and Reviews

In addition to review of the above program, procedures, and plans,

the inspector observed in-process activities and reviewed other

aspects of the FAC program as detailed below:

-

In-process grid layout was observed for components FW 10-14, FW

9-15, FW 11-17, FW 10-8, and FW 11-20 on Isometric Drawing FW

02.

In addition, UT thickness measurement were observed for

components FW 9-14 and FW 9-15 on Isometric Drawing FW-02.

Personnel qualification and certification records for 5 NDE

examiners who performed this work were reviewed.

-

The inspector attempted to review records and determine the

extent of previous problems with through-wall piping leaks due

to FAC. Records were not readily available to determine the

exact number of through-wall leaks. However, based on

discussions with System Engineering personnel, since issue of

Revision 3 (early 1989) to the Temporary Modification

procedure, MOD 18, any repair to a leak with liquid sealant

would require issue of a Temporary Modification. Therefore,

the inspector reviewed the Temporary Modification Log to obtain

some indication of the past through-wall leaks due to FAC.

This indicates something less than 10 through-wall leaks in the

last 4 to 5 years. It is not clear that all of these leaks

14

were due to FAC. Based on this log, only one of these leaks

were in 6" diameter piping. The others were in small diameter

(less than 2") piping. Although not a complete picture, since

this does not include piping thinned and replaced before

leaking, this does give some indication of previous FAC

problems at Robinson.

The inspector examined licensee's past practice and future

plans for material replacements for FAC degraded piping, i.e.,

practices for replacing "like for like" or upgrading to better

materials. Although the type material used for past

replacements is not readily available without extensive review

of modification and maintenance history records, the Site FAC

Coordinator had performed some records reviews of past pipe

replacements and recorded the information on the Isometric

Drawings. A review of this data indicated use of the following

materials:

Date

Size and System

Material(s) Used

10/84

3" - Htr. Drains and Vents

Carbon Steel

(Reheat Excess Stm to

No. 6 FW Heaters)

10/88

"

Carbon and Stainless

10/84

3" and 6" - Heater Drains

Carbon Steel

11/88

"

Carbon and Stainless

5/87

8" - Heater Drains

Carbon Steel

-

Feedwater Recirc Piping

Stainless

-

Steam Generator Blowdown

Stainless

Piping

1990

High Pressure Extraction

2-1/4 Cr-Mo

Steam Piping

5/87

Feedwater Heater Drains

Carbon Steel

Downstream of Cont. Vlvs.

5/92

Discharge on Heater Drain

Carbon Steel

Pumps

From the above it is obvious that there was not always an

attempt to upgrade materials for piping replacements. In the

past, the plant could replace "like for like" as long as the

original design was met. As noted above, in the past, the FAC

program was relatively weak and it appeared there was not much

emphasis on upgrading materials.

15

Today, the general policy is to replace small diameter FAC

degraded piping with Stainless Steel and large diameter with

Cr-Mo material.

The improved FAC program requires input from

Technical Support (FAC Coordinator) and NED on dispositioning

FAC degraded piping and pipe replacements. Any change in

material requires Engineering approval through the Modification

Process. The improved program should ensure that high priority

is given to material upgrades whenever materials are replaced.

-

At the completion of the inspection, 185 of the 285 large bore

piping locations had been inspected. Forty-one of the 185

required NED evaluation (less than 0.875 X tnam).

However,

only 4 were predicted to be below minimum wall before the next

RFO. These are being evaluated for replacement.

RESULTS

No violations or deviations were identified.

Significant improvements were noted in the FAC program. Engineering

Design Guidelines had been issued and Engineering was involved in the

process. Detailed site procedures and department guidelines had been

issued to implement the program.

All affected organizations,

Operations, Maintenance, Engineering, and Chemistry were involved in the

program. A knowledgeable Site FAC Coordinator was in place and ensuring

that the program was properly implemented. The Technical Support

Department had a positive attitude about implementing a good program. A

Susceptibility Analysis of plant piping had been performed and

susceptible piping walked down and Isometric Drawing prepared. The EPRI

CHECMATE Model had been implemented and the Pass 1 analysis completed.

An aggressive inspection program for the current outage had been

implemented to obtain data to further improve the program and predict

future wear.

The inspector noted the following areas where further improvement is

needed:

-

The Outage Plan needs more formal details on how the plan is

developed, issued, controlled, and implemented, especially the

interface with NDE Services and the flow of data and inspection

results. Before the end of the inspection, the FAC Coordinator was

working on procedure changes to provide more details for the Outage

Plan.

-

Modification Procedures need to provide for FAC Coordinator review

of modification and change documents for systems susceptible to FAC

to obtain his input and keep him informed of changes to the systems.

16

A draft interface procedure for Corporate and Sites had been

written, but not issued. This procedure needs to be issued to

define interface agreements and assure that Design Guides will

continue to be implemented.

Corrective actions for the weaknesses identified in the NAD

Assessment need to be completed, especially upgrading the Isometric

Drawings to plant controlled drawings.

4. Observation of Miscellaneous Work Activities (55050 and 37700)

During observation of ISI and FAC in-plant activities, the inspector

examined the following work activities:

a. Modification M-1104, Pipe Support Work

This Modification covers extensive re-work of pipe supports in

systems through-out the plant. The inspector discussed the work

with the contractor (PPM).

Completed Auxiliary Feedwater (AFW)

system supports SS-2225 and SS-2228 in the Turbine Building were

inspected. In addition, the completed work packages, including

Seismic Weld Data Reports, for these supports were reviewed. In

process work (layout work and preparation for fitup) was observed

and in-process records were reviewed for AFW Support SS-2288.

Also, completed work packages for supports SS-2232, SS-2233, and

SS-2234, which involved changing the length of the extension piece

on the pipe support struts by cutting and re-welding, were reviewed.

The records included drawings, weld records and detailed work

instructions, including verification of transfer of identification

on the studs (weldless EYE) after cutting.

RESULTS

The completed supports were painted and detailed inspections of

welds were not possible. However, general workmanship of the

supports and welds appeared to be very good.

All work documents reviewed were detailed and had many QC hold

points and inspections required. All required sign-offs had been

completed.

b. Welding

The inspector observed fitup and tack welds on Service Water System

piping weld FW-9 on Weld Map HVH-1-6-CW22. The work was being

performed by contractor PCI.

The weld is an ASME Class 3 weld and

the applicable code is the ASME B&PV,Section III, Subsection NC.

In addition to observation of the in-process work and review of in

process documentation, the inspector reviewed supporting records for

the following:

17

-

Welding Material Test Reports

3/32" ERNiCrMo-3 -

Heat # PCI-1357

1/8" ERNiCrMo-3 - Heat # PCI-1358

-

Welder Qualification Records

Welders M255 and M289

-

Visual (VT) Qualification Records

1 VT Examiner Who Inspected the Fitup

Within the areas inspected, no violations or deviations were identified.

5. Licensee Action on Previous Inspection Findings (92701, 92702)

a. (Closed) IFI 261/92-13-01, Erosion/Corrosion Program Improvement

This item involved concerns relative to a poor FAC program. The FAC

program has been significantly improved and now appears to be moving

toward a first class program. See paragraph 3. above for details of

inspection efforts in this area.

b. (Closed) IFI 261/92-09-02, Corrosion on Exterior Surfaces of Service

Water Lines at the Intake Structure

See NRC Inspection Report 50-261/92-13 for documentation of a

previous inspection of this item. As noted in report 92-13, the

licensee evaluated the damage to the subject Service Water lines and

determined that the lines should be replaced in RFO 14. During the

92-13 inspection, the inspector observed the degraded condition of

the piping and noted the licensee had no preventive maintenance

program to monitor the condition of the subject exposed piping.

During the current inspection, the inspector visually observed the

newly installed piping as well as other service water piping nearby.

The piping was painted and appeared to be in good condition. Based

on discussions with System Engineering personnel, the previous

piping had been insulated, which allowed moisture to collect between

the piping and the insulation since the piping is an outside

environment. This contributed to the corrosion degradation of the

piping. The insulation has been deleted which should preclude

moisture collection and also allow easy access for monitoring the

condition of the piping.

The licensee has also implemented a PM

Task for periodic monitoring of the piping for coating and corrosion

damage. This periodic monitoring requirement (WR/JO 94HSE001, Route

2 S 82 001) was reviewed by the inspector. Also, Licensee Technical

Support personnel pointed out that an External Corrosion Program is

planned which will cover monitoring this type piping for

degradation.

18

c.

(Open) IFI 265/90-24-01, Welds not Identified on Inservice

Inspection Isometric Sketches

This item concerned missing welds on ISI Isometric sketches used to

identify configuration, weld location and weld population in the ISI

program.

The licensee's letter of response, dated December 20,

1990, indicated that corrective actions will include verification of

the accuracy of the Isometric Drawings by physical walkdown and

other appropriate means and drawing revisions as necessary. This

action is to be completed by the end of the first period of the

third 10-Year interval or June, 1995. The inspector discussed the

status of this action with the Site Senior ISI Specialist. He

indicated that the work is about 65% complete.

6.

Exit Interview

The inspection scope and results were summarized on October 1, 1993, with

those persons indicated in paragraph 1. The inspector described the

areas inspected and discussed in detail the inspection findings. The

violation listed below was found after the exit interview and was

identified to Regulatory Affairs personnel as an Unresolved Item (URI)

before the inspector left the site. After further review in Region II

Offices and after additional information was provided by the licensee,

licensee Regulatory Affairs Specialist (D. Crook) was contacted by phone

and informed that the URI would be changed to a Violation. Proprietary

information is not contained in this report. Dissenting comments were

not received from the licensee.

(Open) Violation 261/93-20-01, Failure to Follow Procedures for

Calibration and Certification of ET Equipment.

7. Acronyms

AFW

Auxiliary Feedwater

ANII

Authorized Nuclear Inservice Inspector

ASME

American Society of Mechanical Engineers

CrMo

Chromium Molybdenum

E/C

Erosion/Corrosion

EPRI

Electric Power Research Institute

ET

Eddy Current Examination

FAC

Flow Accelerated Corrosion

GL

Generic Letter

HP

Health Physics

ISI

Inservice Inspection

MT

Magnetic Particle Examination

NAD

Nuclear Assessment Department

NDE

Nondestructive Examination

NED

Nuclear Engineering Department

NES

Nuclear Energy Services

NRC

Nuclear Regulatory Commission

NRR

Nuclear Reactor Regulation

19

PCI

Power Cutting, Inc.

PLP

Plant Procedure

PPM

Power Plant Maintenance

PT

Liquid Penetrant Examination

QA

Quality Assurance

QC

Quality Control

RCA

Radiation Control Area

RDAU

Remote Data Acquisition Unit

RFO

Refueling Outage

RH

NRC Region II

RPC

Rotating Pancake Coil

R&R

Repair and Replacement

SER

Safety Evaluation Report

SG

Steam Generator

SNPS

Siemens Nuclear Power Services, Inc.

SP

Special Procedure

TI

Technical Instruction

tnom

Nominal Pipe Wall Thickness

TS

Technical Support

URI

Unresolved Item

UT

Ultrasonic Examination

VT

Visual Examination

VIO

Violation

WR

Work Request