ML14178A271

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/92-22 on 920718-0807.Violations Noted.Major Areas Inspected:Operational Safety Verification,Maint Observation & Followup
ML14178A271
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 08/21/1992
From: Christensen H, Garner L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14178A269 List:
References
50-261-92-22, NUDOCS 9209020095
Download: ML14178A271 (5)


See also: IR 05000261/1992022

Text

01REG( qUNITED

STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.V.

ATLANTA, GEORGIA 30323

Report No.:

50-261/92-22

Licensee:

Carolina Power and Light Company

P. 0. Box 1551

Raleigh, NC 27602

Docket No.:

50-261

License No.: DPR-23

Facility Name: H. B. Robinson Unit 2

Inspection Conducted: July 18 - August 7, 1992

Lead Inspector:

ci/-

7 f

L. W. Garner, Senior Re

ent

spector

Date Signed

Other Inspectors: C. R. Ogle, Resident Inspector

D. J. Roberts, Project Inspector

Approved by:

4-?.- >, L

H. 0. Christensen, Chief

D e igned

Reactor Projects Section 1A

Division of Reactor Projects

SUMMARY

Scope:

This routine, announced inspection was conducted in the areas of operational

safety verification, maintenance observation, and followup.

Results:

One violation was identified involving failure to follow an annunciator

procedure (paragraph 3).

9209020095 920821

PDR

ADOCK 05000261

0

PDR

REPORT DETAILS

1.

Persons Contacted

  • R. Barnett, Manager, Outages and Modifications
  • C. Baucom, Senior Specialist, Regulatory Compliance

S. Billings, Technical Aide, Regulatory Compliance

  • R. Chambers, Plant General Manager, Robinson Nuclear Project

B. Clark, Manager, Maintenance

C. Dietz, Vice President, Robinson Nuclear Project

  • D. Dixon, Manager, Control and Administration

J. Dobbs, Manager, Nuclear Assessment Department Site Unit

R. Femal, Shift Supervisor, Operations

  • W. Flanagan, Manager, Operations

R. Moore, Shift Supervisor, Operations

  • A. Padgett, Manager, Environmental and Radiation Control

M. Page, Manager, Technical Support

D. Seagle, Shift Supervisor, Operations

  • D. Stadler, Onsite Licensing Engineer, Nuclear Licensing

W. Stover, Shift Supervisor, Operations

D. Winters, Shift Supervisor, Operations

Other licensee employees contacted included technicians, operators,

engineers, mechanics, security force members, and office personnel.

NRC Managements Visits

J. P. Stohr, Director, Division of Radiation Safety and Safeguards, was

on site July 21, 1992, to meet with plant management and tour the

facility with the inspectors.

  • Attended exit interview on August 11, 1992.

Acronyms and initialisms used throughout this report are listed in the

last paragraph.

2. Plant Status

The unit remained at full power operation during the inspection period.

3. Operational Safety Verification (71707)

The inspectors evaluated licensee activities to confirm that the

facility was being operated safely and in conformance with regulatory

requirements. These activities were confirmed by direct observation,

facility tours, interviews and discussions with licensee personnel and

management, verification of safety system status, and review of facility

records.

To verify equipment operability and compliance with TS, the inspectors

reviewed shift logs, Operations' records, data sheets, instrument

traces, and records of equipment malfunctions. Through work

observations and discussions with Operations staff members, the

2

inspectors verified the staff was knowledgeable of plant conditions,

responded properly to alarms (except as discussed below), adhered to

procedures and applicable administrative controls, cognizant of in

progress surveillance and maintenance activities, and aware of

inoperable equipment status. Theinspectors performed channel

verifications and reviewed component status and safety-related

parameters to verify conformance with TS. Shift changes were observed,

verifying that system status continuity was maintained and that proper

control room staffing existed. Access to the control room was

controlled and operations personnel carried out their assigned duties in

an effective manner. Control room demeanor and communications were

appropriate.

Plant tours and perimeter walkdowns were conducted to verify equipment

operability; assess the general condition of plant equipment; and verify

that radiological controls, fire protection controls, physical

protection controls, and equipment tagging procedures were properly

implemented.

B EDG Jacket Water Temperature Switch Malfunction

On June 30, 1992, the inspectors noted that the B EDG jacket water

temperature was 97 degrees F, well below the jacket water heater

actuation temperature of 110 degrees F. Additionally, it was noted by

the inspectors that despite this low temperature condition, the low

jacket water temperature alarm of 105 degrees F had not activated.

Subsequent troubleshooting by Operations and Maintenance Department

personnel indicated that both the temperature control switch for the

jacket water heater (TC-4515B) and the temperature alarm switch (TS

4514B) were out of calibration. The jacket water heater control switch

was replaced, and both the control and alarm temperature switches were

calibrated. Engineering evaluation 92-011 for the B EDG was conducted

to demonstrate that the B EDG remained operable despite this low jacket

water temperature condition.

CST High Level Alarm Procedure Not Implemented

On July 23, 1992, the inspectors noted that a condensate storage tank

(CST) HI/LO level annunciator was lit on the RTGB due to high CST level

(95%).

As a result of this observation, the inspector subsequently

questioned the makeup water treatment operator as to the level in the

CST. Upon noting the high level condition, the makeup water treatment

operator secured filling the CST. Discussions between the inspectors,

the shift supervisor, makeup water treatment operator and other control

room personnel indicated that the makeup water to the CST was throttled,

but not stopped as required by alarm procedures. Makeup flow was

throttled to allow the temporary truck mounted makeup water treatment

system to remain in service verses being shutdown. Alarm procedure E7

of annunciator panel procedure APP-006, S/G & PPS Systems, required that

the following action be taken, "If High Level, STOP source of CST makeup

water."

Subsequent review by the licensee revealed that the control

room operator had informed the makeup water treatment operator that a

3

high level alarm had been received, but failed to inform him of the

required action. The failure to follow the procedural requirements of

APP-006, (i.e., stop filling the CST on the receipt of a high level

alarm) is considered a VIO:

Failure To Implement Alarm Procedure When

High CST Level Alarm Was Received, 92-22-01.

One violation was identified. Except as noted above, the program area

was adequately implemented.

4. Monthly Maintenance Observation (62703)

The inspectors observed safety-related maintenance activities on systems

and components to ascertain that these activities were conducted in

accordance with TS and approved procedures. The inspectors-determined

that these activities did not violate LCOs and that administrative,

testing, and radiological controls were adhered to. In particular, the

inspectors observed/reviewed the following maintenance activities:

WR/JO 92-AEE323

A And B EDG Governor Brush Cap Inspection

WR/JO 92-AKTP1

Control Rod Drive Room Temperature Alarm

Repair

No violations or deviations were identified. Based on the information

obtained during the inspection, the program area was adequately

implemented.

5. Followup (92700, 92701, 92702)

(Closed) IFI 90-03-01, Review Containment Spray Header Penetration

Isolation Configuration With GDC. A question was raised as whether

manual CV spray isolation valves SI-891A and B met the containment

'isolation boundary requirements of the draft GDCs to which the plant was

licensed. Specifically, the inspectors had questioned whether or not CV

spray pump discharge check valves SI-890A and B were also part of the CV

isolation boundary. In discussions between the licensee and NRR, it was

determined that SI-890A and B did not perform a containment isolation

function. In a letter to the NRC, dated May 14, 1992, the licensee

confirmed this position and committed to change the check valve IST

classification to category A/C and provide specific quantitative

acceptance criteria for backflow leakage. The inspectors verified that

TMM-004, In-Service Inspection Testing, was revised to classify the

check valves as category A/C, and EST-058, SI-890 and 890B Check Valve

Test, was revised to include a maximum allowable backleakage rate of 3.7

gpm. The actions taken addressed the inspectors questions. This item

is considered closed.

No violations or deviations were identified. Based on the information

obtained during the inspection, the program area was adequately

implemented.

4

6. Exit Interview (71701)

The inspection scope and findings were summarized on August 10, 1992,

with those.persons indicated in paragraph 1. The inspectors described

the areas inspected and discussed in detail the inspection findings

listed below and in the summary. The licensee did not identify as

proprietary any of the materials provided to or reviewed by the

inspectors during this inspection.

Item Number

Description/Reference Paragraph

92-22-01

VIO - Failure To Implement Alarm Procedure When

High CST Level Alarm Was Received (paragraph 3)

7. List of Acronyms and Initialisms

APP

Annunciator Panel Procedure

CST

Condensate Storage Tank

CV

Containment Vessel

EDG

Emergency Diesel Generator

F

Fahrenheit

GDC

General Design Criteria

gpm

Gallons Per Minute

i.e.

That is

IFI

Inspector Followup Item

IST

Inservice Test

LCO

Limiting Condition for Operation

LVL

Level

NRR

Nuclear Reactor Regulation

PPS

Penetration Pressurization System

RTGB

Reactor Turbine Generator Board

S/G

Steam Generator

SI

Safety Injection

TMM

Technical Support Management Manual

TS

Technical Specification

VIO

Violation

WR/JO

Work Request/Job Order