0CT 2 5 1991
Docket No. 50-261
License No. DPR-23
Carolina Power and Light Company
ATTN: Mr. Lynn W. Eury
Executive Vice President
Power Supply
P. 0. Box 1551
Raleigh, NC 27602
Gentlemen:
SUBJECT: NRC INSPECTION REPORT NO. 50-261/91-20
This refers to the inspection conducted by L. W. Garner of this office on
September 7 - October 11, 1991.
The inspection included a review of activities
authorized for your H. B. Robinson facility.
At the conclusion of the
inspection, the findings were discussed with those members of your staff
identified in the enclosed inspection report.
Areas examined during the inspection are identified in the report.
Within
these areas, the inspection consisted of selective examinations of procedures
and representative records,
interviews with personnel,
and observation of
activities in progress.
Based on the results of this inspection, one apparent violation was identified
and is being considered for escalated enforcement action in accordance with the
"General
Statement of Policy and Procedure for NRC Enforcement Actions"
(Enforcement Policy), 10 CFR Part 2, Appendix C (1991).
The apparent violation
concerns recently identified examples of inadequate engineering design controls
and interfaces.
Accordingly, no Notice Of Violation is presently being issued
for these inspection findings.
Please be advised that the number and
characterization of apparent violations described in the enclosed inspection
report may change as a result of further NRC review.
An enforcement conference to discuss this apparent violation has been scheduled
for November 6, 1991.
The purposes of this conference are to discuss the
apparent violation, its cause and safety significance; to provide you the
opportunity to point out any errors in our inspection report; to provide an
opportunity for you to present your proposed corrective action(s); and to
discuss any other information that will help us determine the appropriate
enforcement action in accordance with the Enforcement Policy.
You will be
advised by separate correspondence of the results of our deliberations on this
matter. No response regarding the apparent violation is required at this time.
9 1112-20016J
9 110-25
ADOCK 05000261
0
Carolina Power and Light Company
2
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of
this letter and its enclosure(s) will be placed in the NRC Public Document
Room.
Should you have any questions concerning this letter, please contact us.
Sincerely,
Original signed by:
Ellis W. Merschoff
Ellis W. Merschoff, Acting Director
Division of Reactor Projects
Enclosure:
NRC Inspection Report
cc w/encl:
C. R. Dietz, Vice President
Robinson Nuclear Project Department
H. B. Robinson Steam Electric Plant
P. 0. Box 790
O
Hartsville, SC 29550
R. H. Chambers, Plant General Manager
H. B. Robinson Steam Electric Plant
P. 0. Box 790
Hartsville, SC 29550
Heyward G. Shealy, Chief
Bureau of Radiological Health
Dept. of Health and Environmental
Control
2600 Bull Street
Columbia, SC 29201
Dayne H. Brown, Director
Division of Radiation Protection
N. C. Department of Environment,
Health & Natural Resources
P. 0. Box 27687
Raleigh, NC
27611-7687
McCuen Morrell, Chairman
Darlington County Board of Supervisors
County Courthouse
Darlington, SC 29535
(cc w/encl cont'd - See page 3)
Carolina Power and Light Company
3
(cc w/encl cont'd)
Mr. H. Ray Starling
Manager -
Legal Department
P. 0. Box 1551
Raleigh, NC 27602
H. A. Cole
Special Deputy Attorney General
State of North Carolina
P. 0. Box 629
Raleigh, NC 27602
Robert Gruber
Executive Director
Public Staff -
NCUC
P. 0. Box 29520
Raleigh, NC
27626-0520
J. D. Kloosterman, Director
Regulatory Compliance
H. B. Robinson Steam
Electric Plant
P. 0. Box 790
Hartsville, SC 29550
c w/encl:
Document Control Desk
H. Christensen, RII
R. Lo, NRR
NRC Resident Inspector
U.S. Nuclear Regulatory Commission
Route 5, Box 413
Hartsville, SC
29550
R
RII:DRP
RII:DRP
RII:EIC
- ar 0l:tj
HChitensen
D
1
Gdenkins
1nia /01
10/94i/91
10/29/91
10/ c#9