|
---|
Category:E-Mail
MONTHYEARML24289A2052024-10-0909 October 2024 E-mail with Responses to Clarification Questions on Response to Request for Additional Information on the Phase 1 Final Status Survey Reports ML24025A1792024-01-23023 January 2024 State Consultation Response e-mail on Fort Calhoun Station, Unit 1 License Termination Plan License Amendment– (License No. DPR-40, Docket No. 50-285) ML24024A2242024-01-22022 January 2024 State Consultation e-mail on Fort Calhoun Station, Unit 1 License Termination Plan License Amendment- (License No. DPR-40, Docket No. 50-285) ML23311A0862023-11-0505 November 2023 Letter to M Morales Re Ft Calhoun License Termination Section 7 Determination for Ipac 2022-0029456 ML23038A1882023-01-31031 January 2023 Request for Additional Time to Respond to Request for Additional Information on License Amendment Request for Approval of License Termination Plan (License No. DPR-40, Docket No. 50-285) ML22222A1192022-08-0808 August 2022 Email Section 106 NHPA- Ft Calhoun Station License Termination Plan ML21069A2482021-03-10010 March 2021 Umax, 07200054, 05000361, 05000362, FSAR Revision 4 for San Onofre ISFSI ML21335A3352021-01-25025 January 2021 January 25, 2021 e-mail from J. Parrott, NRC to C. Cameron, OPPD Use of Resrad Model to Represent Well Water Concentrations in a Basement Substructure (License No. DPR-40, Docket No. 50-285) ML20204B0782020-07-22022 July 2020 Donna Gilmore Email Holtec Umax Materials (07200054, 05000361, 05000362) ML20113F0622020-04-22022 April 2020 E-mail Results of Acceptance Review of OPPD Request for Exemption from 10 CFR 20, App G, Section Iii.E (License No. DPR-40, Docket No. 50-285) ML20100J2272020-03-26026 March 2020 E-mail Notification to the State of Nebraska on the Issuance of the License Amendment for Revised Security Plans to Reflect an ISFSI-only Configuration (License No. DPR-40, Docket Nos. 50-285 and 72-54) ML20100L7232020-03-15015 March 2020 Email: Town of Desoto National Register of Historic Places Eligibility ML19353C3612019-12-11011 December 2019 E-mail to State of Nebraska Informing of the Pending Revision to the Emergency Plan to Reflect Independent Spent Fuel Storage Installation Only Status (License DPR-40, Docket Nos. 50-285 and 72-054) ML19309F1112019-10-11011 October 2019 ISFSI-Only Tech Specs ML19241A1812019-08-21021 August 2019 Request for Additional Information on Proposed Changes to the FCS Emergency Plan and Emergency Action Level Scheme to Reflect an ISFSI-only Status ML19175A0212019-06-19019 June 2019 Acceptance Review - License Amendment Request to Revise Security and Safeguards Requirements to Reflect ISFSI-Only Configuration ML19130A2082019-05-0808 May 2019 Email - NRC Email to FEMA Dated May 8, 2019: NRC Response to Comment on FEMA Review of Proposed Changes to DBNPS Emergency Plan for Permanently Defueled Condition ML19126A2802019-05-0101 May 2019 Acceptance Review - License Amendment Request for ISFSI-Only EP and EAL Scheme ML18100A2712018-04-0909 April 2018 04-09-18 OPPD E-Mail (FCS Permanently Defueled Emergency Plan Implementation) ML17236A3462017-08-24024 August 2017 NRR E-mail Capture - Final RAI for Fort Calhoun LAR Regarding Permanently Defueled TS (MF9567) ML17236A3442017-08-24024 August 2017 NRR E-mail Capture - Final RAI for Fort Calhoun Exemption from 10 CFR 140.11(a)(4), Off-site Primary and Secondary Liability Insurance (MF9664) ML17234A4692017-08-22022 August 2017 NRR E-mail Capture - Final RAI for Fort Calhoun LAR Regarding Removal of Dry Cask Loading Limits (MF9831) ML17194A9732017-07-13013 July 2017 NRR E-mail Capture - Final RAI for Fort Calhoun Ultimate Strength Design for Aux. Bldg LAR (MF8525) ML17191B0212017-07-10010 July 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review of Modification of LC 3.C to Delete Commission-approved CSP ML17184A0042017-06-30030 June 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review of Removal of Dry Cask Loading Limits ML17139C8342017-05-19019 May 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review Partial Exemption from Record Retention Requirements ML17139C5082017-05-19019 May 2017 NRR E-mail Capture - (External_Sender) Need Corrected Page 6 for LIC-17-0043 ML17144A0132017-05-19019 May 2017 NRR E-mail Capture - Fort Calhoun PSDAR - Findings and Concerns ML17142A0202017-05-19019 May 2017 NRR E-mail Capture - (External_Sender) Need Corrected Page 6 to TQ-DC-FC-101 ML17139B6762017-05-18018 May 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review Exemption from 10 CFR 140.11(a)(4), Off-Site Liability Insurance ML17139B6782017-05-18018 May 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review Exemption from 10 CFR 50.54(w)(1), On-Site Property Damage Insurance ML17136A1692017-05-16016 May 2017 NRR E-mail Capture - (External_Sender) OPPD FCS Decommissioning Financial Reports ML17115A4722017-04-25025 April 2017 NRR E-mail Capture - (External_Sender) Corrected Page 18 to TQ-DC-FC-201 ML17114A3112017-04-24024 April 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review TS Changes to Align for Decommissioning ML17112A0362017-04-20020 April 2017 NRR E-mail Capture - Fort Calhoun Station - Final RAI Regarding Permanently Defueled EP and EAL Scheme Change LAR ML17090A3942017-03-31031 March 2017 NRR E-mail Capture - Fort Calhoun - Final RAI Regarding Administrative Control TS Change LAR (MF8437) ML17082A0022017-03-22022 March 2017 NRR E-mail Capture - Fort Calhoun Station - Final Nsir/Dpr RAI Regarding Proposed Emergency Planning Exemption ML17081A0192017-03-21021 March 2017 NRR E-mail Capture - Fort Calhoun Station - Final RAI Regarding Proposed Emergency Planning Exemption ML17052A0272017-02-15015 February 2017 NRR E-mail Capture - Fort Calhoun Station, Unit No. 1 - Acceptance of Requested Amendment Revise Permanently Defueled Emergency Plan and EAL Scheme ML17033A9692017-02-0202 February 2017 NRR E-mail Capture - Fort Calhoun Station - Final Request for Additional Information Concerning Post-Shutdown Eplan Amendment ML16351A0432016-12-15015 December 2016 NRR E-mail Capture - (External_Sender) Fort Calhoun Station Offsite Response Organizations ML16350A0392016-12-15015 December 2016 NRR E-mail Capture - Acceptance Review (CAC No. MF8858) Fort Calhoun, Unit 1 - License Amendment Request (LAR) 16-06; Removal of License Condition 3.D., Fire Protection Program ML16334A3002016-11-29029 November 2016 NRR E-mail Capture - Acceptance Review (CAC No. MF8525) Fort Calhoun, Unit 1 - License Amendment Request LAR-16-04 to Revise Current Licensing Basis to Use Aci Ultimate Strength Requirements ML16333A2312016-11-28028 November 2016 NRR E-mail Capture - Acceptance Review (CAC No. MF8843)Fort Calhoun, Unit 1, Request for Rescission of Interim Compensatory Measure B.1.a from EA-02-026, Order for Interim Safeguards and Security Compensatory Measures. ML16333A0992016-11-28028 November 2016 NRR E-mail Capture - Acceptance Review (CAC No. MF8452), Fort Calhoun, Unit 1 - Request for Exemption from Specific Provisions in 10 CFR 73.55 ML16286A0812016-10-12012 October 2016 NRR E-mail Capture - Acceptance Review Fort Calhoun Station, Unit 1, License Amendment Request 16-03, Technical Specifications to Align Staffing Requirements to Those Required for Decommissioning ML16278A0292016-10-0303 October 2016 NRR E-mail Capture - Acceptance Review Fort Calhoun Station Radiological Emergency Response Plan (RERP) for Decommissioning ML16257A0262016-09-12012 September 2016 NRR E-mail Capture - (External_Sender) OPPD Slides for 9/13/16 Pre-Application Meeting on Class 1 Structures ML16207A0182016-07-22022 July 2016 NRR E-mail Capture - Acceptance Review ML16137A0092016-05-16016 May 2016 NRR E-mail Capture - Acceptance Review CAC No. MF7574 2024-10-09
[Table view] |
Text
NRR-PMDAPEm Resource From: Rankin, Jennivine Sent: Wednesday, June 25, 2014 3:36 PM To: BHansher@oppd.com; medwards@oppd.com
Subject:
Acceptance Review - Request for Relief from Certain IST Requirements (MF4167)
Mr. Hansher and Mr. Edwards, By letter dated May 16, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14136A466), Omaha Public Power District (the licensee), submitted a request for relief (proposed alternative) from the American Society of Mechanical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants (OM Code), Appendix I scheduling requirements, for Fort Calhoun Station, Unit 1.
The proposed relief request would provide relief from those requirements until the next refueling outage.
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in the scope and depth to allow the NRC staff to complete its detailed technical review.
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Pursuant to Sections 50.55a(a)(3)(i) and 50.55a(a)(3)(ii) of Title 10 of the Code of Federal Regulations, the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety, or that compliance with the specified requirements of Section 50.55a would result in hardship or unusual difficulty without a compensating increase in the level of quality or safety.
The NRC staff has reviewed your request and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and to make an independent assessment regarding the acceptability of the requested relief in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
If you have any questions, please contact me at (301) 415-1530.
- Thanks, Jennie Jennie Rankin, Project Manager Palo Verde Nuclear Generating Station Fort Calhoun Station Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation 1
Hearing Identifier: NRR_PMDA Email Number: 1402 Mail Envelope Properties (E85CAE0ED2FC5449B808712D77E97576B5E9DF1232)
Subject:
Acceptance Review - Request for Relief from Certain IST Requirements (MF4167)
Sent Date: 6/25/2014 3:35:48 PM Received Date: 6/25/2014 3:35:00 PM From: Rankin, Jennivine Created By: Jennivine.Rankin@nrc.gov Recipients:
"BHansher@oppd.com" <BHansher@oppd.com>
Tracking Status: None "medwards@oppd.com" <medwards@oppd.com>
Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 2671 6/25/2014 3:35:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: