Forwards IE Insp Rept 50-261/81-15 on 810411-0510,notice of Violation & Notice of Deviation
ML14176A635
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 06/01/1981
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Jackie Jones
CAROLINA POWER & LIGHT CO.
Shared Package
ML14176A633 List:
References
NUDOCS 8107240239
Download: ML14176A635 (2)


See also: IR 05000261/1981015

Text

REG~

UNIED SATESOFFICIAL

COPY

'

s

SoUNITED

STATES

NUCLEAR REGULATORY COMMISSION

REGION 11

101 MARIETTA ST., N.W., SUITE 3100

ATLANTA, GEORGIA 30303

JUN 011981

Carolina Power and Light Company

ATTN:

Mr. J. A. Jones, Senior Executive

Vice President and Chief

Operating Officer

411 Fayetteville Street

Raleigh, NC

27602

Gentlemen:

Subject: Report No. 50-261/81-15

This refers to the routine safety inspection conducted by Mr. S. Weise of this

office on April 11 -

May 10,

1981,

of activities authorized by NRC Operating

License No.

DPR-23 for the H. B. Robinson facility.

Our preliminary findings

were discussed with Mr. R. B. Starkey, General Manager, at the conclusion of the

inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these areas,

the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel,

and observations by the inspectors.

During the inspection,

it

was found that certain activities under your license

appear to violate NRC requirements.

These items and references to pertinent

requirements

are listed in the Notice of Violation enclosed herewith as

Appendix A. Elements to be

included in your response are delineated in

Appendix A.

During the inspection it

was found that certain activities under your license

appear to deviate from commitments to the Commission

and have safety signi

ficance. This item is identified in the Notice of Deviation enclosed herewith as

Appendix B. Please provide us in writing your comments including a description

of corrective actions that have been or will be taken, corrective actions which

will be taken to avoid further deviations, and the date your corrective actions

will be completed.

We have examined actions you have taken with regard to previously identified

enforcement matters and unresolved items.

The status of these items is discussed

in the enclosed report.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this

letter and the enclosed report will be placed in the NRC's Public Document Room.

If

the report contains any information that you believe to be exempt from

disclosure under 10 CFR 9.5(a)(4),

it is necessary that you:

(a) notify this

office by telephone within ten days from the date of this letter of your

intention to file a request for withholding; and (b) submit within twenty-five

8107240239 810707

PDR ADOCK 05000261

G PDR

J

Carolina Power and Light Company

2

JUN 0 11981

days from the date of this letter a written application to this office to

withhold such information. If your receipt of this letter has been delayed such

that less than seven days are available for your review, please notify this

office promptly

so that a new due date may be established.

Consistent with

section 2.790(b)(1),

such application must

be

accompanied

by

an affidavit

executed by the owner of the information which identifies the document or part

thereof sought to be withheld, and a full statement of the reasons on the basis

of which it

is claimed that the information should be withheld from public

disclosure.

This section further requires the statement to address with

specificity the considerations listed in 10 CFR 2.790(b)(4).

The information

sought to be withheld shall be incorporated as far as possible into a separate

part of the affidavit.

If

we do not hear from you in this regard within the

specified periods noted above, the report will be placed in the Public Document

Room.

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

RCL

wis, Acting Director

Division of Resident and

Reactor Project Inspection

Enclosures:

1. Appendix A, Notice of Violation

2. Appendix B, Notice of Deviation

3.

Inspection Report No. 50-261/81-15

cc w/encl:

R. B. Starkey, Jr., Plant Manager