Forwards IE Insp Rept 50-261/80-03 on 800204-06 & Notice of Violation
ML14175B144
Person / Time
Site: Robinson 
Issue date: 02/27/1980
From: Stohr J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Jackie Jones
CAROLINA POWER & LIGHT CO.
Shared Package
ML14175B141 List:
References
NUDOCS 8004250275
Download: ML14175B144 (2)


See also: IR 05000261/1980003

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA ST., N.W., SUITE 3100

ATLANTA, GEORGIA 30303

FEB 2 7 1980

In Reply Refer To:

RII:JRW

50-261/80-3

Carolina Power and Light Company

ATTN:

J. A. Jones

Senior Executive Vice President and

Chief Operating Officer

411 Fayetteville Street

Raleigh, NC 27602

Gentlemen:

This refers to the inspection conducted by J. R. Wray of this office on

February 4-6, 1980, of activities authorized by NRC Operating License No. DPR-23

for the H. B. Robinson facility, and to the discussion of our findings held with

R. B. Starkey, Jr. at the conclusion of the inspection.

The inspection was an examination of the activities conducted under your license

as they relate to radiation safety and to compliance with the Commission's rules

and regulations and the conditions of your license. The inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

We have examined actions you have taken with regard to previously identified

enforcement matters. These are discussed in the enclosed inspection report.

During the inspection, it was found that certain activities under your license

appear to be in noncompliance with NRC requirements.

These items and references

to pertinent requirements are listed in the Notice of Violation enclosed here

with as Appendix A. This notice is sent to you pursuant to the provisions of

Section 2.201 of the NRC's "Rules of Practice," Part 2, Title 10, Code of Federal

Regulations. Section 2.201 requires you to submit to this office, within 20

days of your receipt of this notice, a written statement or explanation in reply

including:

(1) corrective steps which have been taken by you and the results

achieved; (2) corrective steps which will be taken to avoid further noncom

pliance; and (3) the date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room. If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within 20 days

to this office to withhold such information from public disclosure. Any such

application must include a full statement of the reasons on the basis of which

it is claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained in a

separate part of the document. If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document Room.

8004250

0

0

Carolina Power and Light

-2

Company

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

.

Philip Sto r, Chief

Fuel Facility and Materials

Safety Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report No. 50-261/80-3

cc w/encl:

R. B. Starkey, Jr., Plant Manager

P. 0. Box 790

Hartsville, SC

29550