Forwards IE Bulletin 79-28, Possible Malfunction of Namco Model EA180 Limit Switches at Elevated Temps. Action Required
ML14170A558
Person / Time
Site: Harris, Brunswick, Robinson  
Issue date: 12/07/1979
From: O'Reilly J
NRC Office of Inspection & Enforcement (IE Region II)
To: Jackie Jones
Carolina Power & Light Co
References
NUDOCS 7912200006
Download: ML14170A558 (6)


Text

REQ&,q 05 UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 101 MARIETTA ST., N.W., SUITE 3100 ATLANTA, GEORGIA 30303 DEC 7 1979 In Reply Refer To:

RII:JPO 50-325, 50-324 50-400, 50-401 50-402, 50-403 Carolina Power and Light Company ATTN:

J. A. Jones Senior Executive Vice President and Chief Operating Officer 411 Fayetteville Street Raleigh, North Carolina 27602 Gentlemen:

Enclosed is IE Bulletin No. 79-28 which requires action by you with regard to your power reactor facility(ies) with an operating license or a construction permit.

Should you have questions regarding this Bulletin or the actions required of you, please contact this office.

Sincerely, James P. O'Reilly Director

Enclosures:

1.

IE Bulletin No. 79-28 w/its Attachment

2.

List of Recently Issued IE Bulletins

'Jg~g2U-

/4

0 BDEC 7 1979 Carolina Power and Light Company

-2 cc w/encl:

A. C. Tollison, Jr.

Plant Manager Box 458 Southport, North Carolina 28461 R. Parsons, Site Manager Post Office Box 101 New Hill, North Carolina 27562 R. B. Starkey, Jr., Plant Manager Post Office Box 790 Hartsville, South Carolina 29550

UNITED STATES SSINS No.: 6820 NUCLEAR REGULATORY COMMISSION Accession No.:

OFFICE OF INSPECTION AND ENFORCEMENT 7910250505 WASHINGTON, D.C. 20555 December 7, 1979 IE Bulletin No. 79-28 POSSIBLE MALFUNCTION OF NAMCO MODEL EA180 LIMIT SWITCHES AT ELEVATED TEMPERATURES Description of Circumstances:

The NRC has been recently advised through a 10 CFR 21 report from Namco Controls that a malfunction of a Namco Model EA180 stem mounted limit switch (SMLS) occurred at the Cooper Nuclear Station. Investigation into the switch failure by the licensee revealed yellow and brown "crystal-like" resin deposits on the internal components of the switch. The affected switch is located inside the drywell containment at this facility and was being used as the replacement switch for an unqualified SMLS previously identified in IE Bulletin Nos.

78-04 and 79-01.

According to the manufacturer, the problem was traced to a batch of top cover gaskets of which some were over-impregnated and insufficiently heat cured. It has been determined that this condition can leave an uncured residue of "Loctite" in the gasket, which vaporizes at sustained temperatures above 175 0 F. To correct the problem, the manufacturer has revised production techniques beginning September 1979 in order to better control the impregnation process and to properly heat cure the gaskets following impregnation. This problem is unique to all Namco Model EA180 series switches received by licensees after March 1, 1979.

According to the manufacturer, the suspect switches can be identified by checking the date code which is a 4 digit number stamped on the conduit boss of the switch housing.

Namco recommends that any EA180 series switch with a date code between 02-79 through 08-79 should have its top cover gasket replaced. Also, licensees should request from their suppliers of equipment on which Namco EA180 series switches are used that they check their inventory and replace top cover gaskets on switches date coded between 02-79 through 08-79.

The enclosed letter from Namco further describes the high-temperature environ mental problem with the top cover gaskets used in their EA180 switches and provides recommendations to correct the problem. According to Namco, this letter has been sent to each customer who was shipped EA180 switches between February 21, 1979, and August 24, 1979.

Action to be Taken by Licensees of Power Reactor Operating Facilities and Holders of Construction Permits:

1.

Determine if your facility has installed or plans to install Namco EA180 switches in any safety-related equipment located inside or outside containment, including valve position indicating circuitry related to containment isolation valves.

IE Bulletin No. 79-28 December 7, 1979 Page 2 of 2

2.

If such switches are identified, examine the four digit number stamped on the conduit boss of the switch housing. If this number falls between 02-79 and 08-79, replace the top gasket of the switch in accordance with the manufacturer's recommendations provided in the enclosed letter.

3.

Submit your plans and programs, including schedules for corrective action, regarding your findings in response to Items 1 and 2 above.

4.

Provide the response in writing within 30 days for facilities holding an operating license and within 60 days for those holders of construction permits. Reports should be submitted to the Director of the appropriate NRC Regional Office and a copy should be forwarded to the U. S. Nuclear Regulatory Commission, Office of Inspection and Enforcement, Division of Reactor Operations Inspection, Washington, D.C. 20555.

Approved by GAO, B180225 (R0072); clearance expires July 31, 1980. Approval was given under a blanket clearance specifically for identified generic problems.

Attachment:

Extract of Namco Controls Letter dated 8/30/79

EXTRACT NAMC 0 C 0 NTR 0 LS August 30, 1979 Attention:

Subject:

Possible malfunction of Namco Model EA180 limit switches at elevated ambient temperatures Gentlemen:

Namco Controls has determined that the EA180 series limit switches shipped against your purchase order(s) #

may have top cover gaskets which will emit a resin vapor at temperatures above 175 0 F.

This vapor could condense into deposits on the normally open contacts, possibly causing a switch malfunction.

We have reported this situation to the NRC, and we are contacting each customer who has received switches with gaskets from the questionable production lot, with the following recommendations:

a)

If the switches have not been put into service, and the ultimate ambient temperatures are unknown, the top cover gasket should be replaced.

b)

If the switches are in service and are subjected to a continuous ambient temperature of more than 175 0 F, they should be inspected for deposits, the contacts cleaned if necessary, and have the top cover gasket replaced.

c)

If the switches are in service, (or scheduled for service) in a continuous ambient temperature of 175 0F or less, no action is necessary.

We will provide you with whatever number of new top cover gaskets you may require, free of charge. Or, if you prefer, we will accept switches returned to our Jefferson plant freight collect, for gasket replacement and/or cleaning.

We sincerely regret any inconvenience this remedy may cause.

If you have any questions, please contact either Robert H. Kantner, 216-268-4200 or John R.

Bendokaitis, 216-576-4070.

IE Bulletin No. 79-28 Enclosure December 7, 1979 RECENTLY ISSUED IE BULLETINS Bulletin Subject Date Issued Issued To No.

79-28 Possible Malfunction of 12/07/79 All power reactor Namco Model EA180 Limit facilities holding Switches at Elevated OL or CP Temperatures 79-27 Loss Of Non-Class-1-E 11/30/79 All power reactor Instrumentation and facilities holding Control Power System Bus OLs and to those During Operation nearing licensing 79-26 Boron Loss From BWR 11/20/79 All BWR power reactor Control Blades facilities with an OL 79-25 Failures of Westinghouse 11/2/79 All power reactor BFD Relays In Safety-Related facilities with an Systems OL or CP 79-17 Pipe Cracks In Stagnant 10/29/79 All PWR's with an (Rev. 1)

Borated Water System At OL and for information PWR Plants to other power reactors 79-24 Frozen Lines 9/27/79 All power reactor facilities which have either OLs or CPs and are in the late stage of construction 79-23 Potential Failure of 9/12/79 All Power Reactor Emergency Diesel Facilities with an Generator Field Operating License or Exciter Transformer a construction permit 79-14 Seismic Analyses For 9/7/79 All Power Reactor (Supplement 2) As-Built Safety-Related Facilities with an Piping Systems OL or a CP 79-22 Possible Leakage of Tubes 9/5/79 To Each Licensee of Tritium Gas in Time-who Receives Tubes pieces for Luminosity of Tritium Gas Used in Timepieces for Luminosity 79-13 Cracking in Feedwater 8/30/79 All Designated (Rev. 1)

System Piping Applicants for OLs