ML14169A646
| ML14169A646 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 06/16/2014 |
| From: | Vincent Gaddy Operations Branch IV |
| To: | Luminant Generation Co |
| References | |
| 50-445/14-06, 50-446/14-06 50-445/OL-14, 50-446/OL-14 | |
| Download: ML14169A646 (7) | |
Text
Instructions
[Refer to Section D of ES-401 and Appendix B for additional information regarding each of the following concepts.]
- 1. Enter the level of knowledge (LOK) of each question as either (F)undamental or (H)igher cognitive level.
- 2. Enter the level of difficulty (LOD) of each question using a 1 B 5 (easy B difficult) rating scale (questions in the 2 B 4 range are acceptable).
- 3. Check the appropriate box if a psychometric flaw is identified:
The stem lacks sufficient focus to elicit the correct answer (e.g., unclear intent, more information is needed, or too much needless information).
The stem or distractors contain cues (i.e., clues, specific determiners, phrasing, length, etc).
The answer choices are a collection of unrelated true/false statements.
The distractors are not credible; single implausible distractors should be repaired, more than one is unacceptable.
One or more distractors is (are) partially correct (e.g., if the applicant can make unstated assumptions that are not contradicted by stem).
- 4. Check the appropriate box if a job content error is identified:
The question is not linked to the job requirements (i.e., the question has a valid K/A but, as written, is not operational in content).
The question requires the recall of knowledge that is too specific for the closed reference test mode (i.e., it is not required to be known from memory).
The question contains data with an unrealistic level of accuracy or inconsistent units (e.g., panel meter in percent with question in gallons).
The question requires reverse logic or application compared to the job requirements.
- 5. Check questions that are sampled for conformance with the approved K/A and those that are designated SRO-only (K/A and license level mismatches are unacceptable).
- 6. Enter question source: (B)ank, (M)odified, or (N)ew. Check that (M)odified questions meet criteria of ES-401 Section D.2.f.
- 7. Based on the reviewer=s judgment, is the question as written (U)nsatisfactory (requiring repair or replacement), in need of (E)ditorial enhancement, or (S)atisfactory?
- 8. At a minimum, explain any AU@ ratings (e.g., how the Appendix B psychometric attributes are not being met).
Page 1 of 7 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 1
F 2
B S
C, 41. 1, 2
F 3
M S
C.41.14 3
F 2
X X
B E/S B, 41.0, Stem describes the actions to take (K/A). Choices are which action is allowed? Distractors are actions not allowed. They are given, a soak is in progress, what action is not in accordance with a soak? Restructured to ask required action.
4 H
2 X
B U/S A, 41.8, Are the last 2 bullets in the stem required? The operators should know that phase B split out the CCW trains, does any procedure allow them (CCW Pumps)to be cross-connected? The nuggets to know here are: Train A RHR has no CCW cooling, but can be run if pumping water from the RWST. The last 3 responses each talk about RHR cross-tie, which have no affect and can be thrown out. There is only one reasonable answer. Might think about 2 of the responses being for Cntmt Spray operation. Revised Question.
5 F
3 X
X N
U/S A, 41.8. K/A mismatch. CFR should be 41.5, This should be a generic question concerning RCP malfunctions. Restructured Question.
6 H
1 X
X B
U/S B, 41.7, K/A mismatch. Does not deal with a loss of RHR system. Answer is obvious. I dont understand explanation of correct answer. What is the relationship between SI being reset or not. If valve is closed, same result. Replaced.
7 H
3 X
X N
E/S D, 41.7, K/A concerns controlling flow rates to components cooled by CCW. Multiple correct answers. C is a direct answer in the ALM. How much flow can go through the recirc line, is this realistic? Restructured Question.
Form ES-401-9 Page 2 of 7 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 8
H 1
X X
B U/S A, 41.7, Stem says heaters cannot be secured. It might be better to say without operator action. Response C and D are completely unrealistic. PORVs do not control pressure, only lower pressure uncontrollably. This is a repeat question from the last NRC exam (wording may have been slightly changed. This question not compatible with Question 34. Suggest replace this question. Replaced.
9 H
3 X
N U/S B, 41.5, Why would anyone think power would go up? Pressure coefficient not normally considered in Westinghouse, more applicable to CE unit. Are attached lesson plans for Comanche Peak? A and C not credible. Revised.
10 F
2 M
E/S B, 41.7 Replace D response. Revised.
11 F
3 X
B E/S A, 41.4 revise D Revised.
12 F
2 X
B E/S D, 41.7, What is the status of offsite power now, All heaters not on DG. What is source of control power (DC or 120 v AC)? Backup heater breakers will close if control power is available. Control Bank C must be closed from control board.
Where is locally, described in A and B? In containment? Explanation for group C heaters is misleading. It does not matter about a demand signal, closed from control room. A and C not credible. Revised.
13 F
4 X
N E/S D, 41.6 TDAFW Pump Speed indication pretty unimportant. It might be better to ask, TDAFW Pump start or not start, and DG start or not start. Revised.
14 F
3 X
X N
U/S B, 41.10, The DG SSW return valves are always open at CPNPP, so this is not a good distractor. C and D are not credible. Revised.
15 F
3 X
X B
U/S Both B and C could be correct. The most correct answer is not good enough.
Revised.
16 H
3 X
N E/S There are lots of info in the stem and it is unclear what is being asked. Revised.
17 H
3 X
X N
U/S A, 41.10 B and C not credible. Stem cues correct answer. Revised.
18 F
3 X
N E/S D, 41.5 Clarify Stem. Clarified.
19 F
3 X
N E/S A, 41.6, I believe must be greater than either P7 or P10 for rods to withdraw in auto.
Problem with third bullet. Stem has IR just at P6 setpoint. I believe SR counts would be lower (to allow P6 SR block to occur prior to SR RX trip)/ Revise Stem. Revised.
20 H
3 X
X B
E/S A, 41.1 Explanations could be cleaned up a little. They imply that cooldown restores power and rods restore temperature. Rods in automatic (not just D bank in auto).
Revised.
21 F
3 X
B E/S Add MINIMUM in caps in stem. Added.
Form ES-401-9 Page 3 of 7 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 22 F
3 X
N U/S Two distractors not credible. Revise distractors to make 2X2. Revised.
23 F
4 X
N U/S This is an SRO only question. Change reference from tech specs to an administrative procedure. Revised.
24 F
3 X
B E/S.D, 41.10 Revise C. Revised.
25 F
3 X
X N
E/S C, 41.5, Take out all references to which pump is running, or will be started. It has nothing to do with the K/A, If the idea was to mimimize dose rates, then flow would probably be lowered to 45 GPM. Last bullet in stem should read Letdown is in service at 75 gpm. A and B responses should read Lower letdown flow to 45 gpm
. C and D responses should read Increase letdown flow to 120 - 140 gpm Revised.
26 F
3 X
B E/S C, 41.10 Revise distractors to make 2X2 Revised.
27 F
3 N
S 28 H
2 B
S C, 41.5, 29 H
3 X
N U/S K/A mismatch. Transfer of Control, not transfer of suction. K/A may be N/A for Comanche Peak. I believe this K/A was written for plants that can select another instrument for level control. Replaced.
30 H
3 B
S 31 H
2 X
B E/S C, 41.10, Answer not supported by the documentation. Change C to read, Centrifugal Charging Pumps running in the injection mode will collapse the pressurizer bubble and increase the risk of damaging the pressurizer safeties.
Revised.
32 H
3 X
B E/S B, 41.5, There are 3 VCT level decrease and 1 VCT level will remain the same.
Suggest change C response to show VCT level remain the same (along with the other responses). This would be the case if letdown did not isolate. Revised.
33 F
2 X
X N
E/S C, 41.7, Make it clear that the answers are based on the electrical lineup following the stem conditions. Revised.
34 H
3 X
N U/S B, 41.7, Make it clear without operator action. This same topic is being tested in Scenario 2 - replace. Replaced.
35 H
3 B
S 36 H
3 X
M U/S D, 41.5, Neither A nor C are plausible answers. 650 psig above accumulator pressure and way above RHR discharge pressure. With loss of offsite power, no power to RCPs. Revised.
Form ES-401-9 Page 4 of 7 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 37 F
3 X
N U/S A, 41.9, K/A mismatch. I believe K/A is asking What signals from the Containment Cooling system cause a containment isolation? Maybe a break in the vent chilled water system isolates vent chilled water????? Replaced.
38 F
2 X
N E/S C, 41.8, B and D responses are not allowed. (The stem says cooling is lost, B and D say nothing is wrong.) Revised.
39 H
3 X
N U/S K/A is asking for bases for cooldown limit, not a steam dump design question.
Rewrote question.
40 H
3 N
S A, 41.10.
41 H
3 B
S B, 41.10, 42 H
3 B
S C, 41.5, 43 F
1 X
N U/S D, 41.6, The DC control power to a reactor trip breaker is not a major DC load. The low importance rating would not fit for the operation of a reactor trip breaker. If the reactor was at 100% power, then it would not be tripped. K/A mismatch To answer the question one needs to know the difference between train A and train B and the reactor is at power - nothing about major DC loads. Replaced.
44 F
3 X
X N
E/S B, 41.10, Not an RO question, K/A mismatch. This is strictly a TS, TS basis question, not related to anything in task list page 3.6-8 of K/A catalog. Rewritten.
45 H
2 X
B E/S D, 41.13, Add procedure in stem. Revised.
46 H
3 N
S B, 41.10.
47 H
2 X
N E/S D, 41.9. A and C are not good distractors. This question is based on instrument air supplying the motive force for 1-HV-3486. Is this true?? Revised A and C.
48 H
3 B
S C. 41.9..
49 F
2 X
B E/S C, 41.3 Revise A. Revised.
50 H
3 X
B E/S D, 41.5, B response not reasonable, a better distractor would be RHR suction pressure relief setpoint. Would this be a possible second correct answer, considering the initial spike? Replace B. Replaced.
51 H
3 X
X B
E/S A, 41.7. Delete 2nd half of stem. Revise distractors. Revised..
52 H
3 X
M U/S Why would SGs become depleted? AFW flow is reduced initially due to excessive cooldown from depressurization. Once SGs blowdown, AFW flow is increased to stabilize RCS temperature. FRH is N/A, EOP -2 is also N/A. C and D not credible.
Replaced.
Form ES-401-9 Page 5 of 7 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 53 F
2 B
S D, 41.10.
54 F
2 B
S A, 41.10 55 F
2 X
B E/S A, 41.7 Change would to should in stem. Revised.
56 F
2 X
X B
U/S C, 41.6, K/A mismatch. Question is for K/A 2.02 not 2.01. B and D not credible distractors. Generator does not feed motor. B and D not credible. Rewritten.
57 F
3 X
N E/S A, 41.3, The question is misleading; the alarm helps to identify the presence of leakage, not the amount. OPT-303 is used to identify the volume of leakage. Look at the OPT-303 to see which items are looked at. There may be several potential correct answers. Part of the reference talks about the RCP number 2 seal and has nothing to do with the question. Revised.
58 F
2 B
U/S C. 41.5. A and B are not plausible. Why would anyone think level program only starts at 20% power? Revised.
59 F
2 X
X B
U/S C, 41.6. Multiple correct answers. If C is correct, then D is also correct (There would be >5% between the highest and the lowest). It is even possible for B to be correct.
Replaced.
60 H
3 X
X N
U/S A, 41.7. Multiple partial correct answers. A RX trip causes a turbine trip. A feedwater isolation occurs on every RX trip when steam dumps lower Tavg to setpoint. Motor Driver AFW pumps get a direct start. Replaced.
61 F
3 X
B S
D, 41.10.
62 H
3 X
N U/S D, 41.7, This question is for system 039, not 035. Wrong reference material, ABN-709 is for steam pressure failure. This is also event 2 in scenario 1. Replaced.
63 H
3 X
M E/S D, 41.7. Steam pressure setpoint at zero confusing. Should say potentiometer is set at zero. (and controller in auto) Revised.
64 H
4 N
S A, 41.7 65 F
4 X
N E/S B. 41.10. Reference says approximately 82%. Can we defend 85 % as being wrong (another acceptable answer)? Revised Distractors.
66 F
2 X
B U/S A, 41.10. C could be argued as correct also. Replaced.
67 F
2 X
N U/S B, 41.10 Concept same as question 99. Replaced.
68 F
2 X
B U/S C, 41.10. I think either B or C might be considered correct. 10 CFR says licensee must inform NRC. Licensee is defined as person who is authorized to conduct activities under a license. Rewritten.
Form ES-401-9 Page 6 of 7 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 69 F
3 X
B E/S B, 41.10 In B response, change or to and. Suspend core alterations AND (not or) positive reactivity additions AND initiate boraton Revised.
70 F
4 N
S D, 41.10, 71 F
3 X
X M
E/S Modify stem and distractors. Revised.
72 F
2 X
B U/S A, 41.9, B and C responses not credible. 3 out of 4 fans normally run. Start the 4th fan prior to stopping the desired fan. Rewritten.
73 F
2 X
B U/S D, 41.12, See reference. An Electronic Dosimeter alarms - it is an alarming electronic dosimeter. Two correct answers. Replaced.
74 H
2 N
S C, 41.10 75 F
2 N
S D, 41.7 76 H
3 N
S A, 43.5 77 H
3 B
S A, 43.5 78 H
3 N
S B, 43.5 79 H
3 N
S B, 43.5 80 H
3 X
X N
E/S B, 43.2. 2 AFW Pumps will start and feed 4 SGs for both B and D. Clean up the explanation to indicate only the TS bases. Revised.
81 H
3 X
N U/S A, 43.5. K/A is for EOP entry conditions and immediate action steps. Not TS.
Replaced.
82 H
3 B
U/S B, 43.2 All of action not in responses - verify within limits or initiate boration and mode 3. Verify COLR limit is correct. No correct answer. Replaced.
83 H
3 N
S C, 43.2 84 H
2 N
S C, 43.5 85 H
3 M
S C, 43.1 86 H
2 M
S C, 43.5 87 H
2 X
B U/S C, 43.2, K/A Mismatch. Specific question on a generic K/A. Question asks how does valve fail and it is operable. I agree its in the required ECCS position, but I dont know if it is operable. For example, a failed closed containment isolation valve would not be considered operable if the same thing occurred. Replaced.
Form ES-401-9 Page 7 of 7 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 88 H
2 X
N U/S A, 43.5 If A is correct, then B is also correct. If C was correct, then D would also be correct. 155 F is > 135 F, so same actions would be required. (Applicant gets to choose temp, since it was not given.) Is basis for bypassing the demins to protect demins from temperature or plant from reactivity effects? Is this written anywhere?
Are there directions in ABN-502 which addresses this issue? Replaced.
89 H
2 N
S B, 43.2 90 F
2 X
N U/S A, 43.5. This question tests some of the same concepts as question 52. If RCS Tcold is 170 degrees, is any AFW flow needed? This procedure no longer applies.
C and D not credible. Rewritten.
91 X
M E/S Add procedure in stem. Added.
92 F
2 X
N U/S D, 43.5. This is an example of a generic question. The stem says cntmt spray was verified. Responses A and B say not verified. There are really only 2 choices, stay in EOP-2 or go to FRZ. Only two credible distractors. Replaced.
93 F
3 X
B U/S C, 43.5. Attached references do not support the answer. Note says CPC Supervisor will assume SM duties. No correct answer. Rewritten.
94 H
4 M
S D, 43.2.
95 H
4 N
S C, 43.2 96 F
3 B
S 97 F
3 X
X N
U/S B, 43.4 Question is specific. Can more generic terms be used to ask this question?
Two correct answers. Rewritten.
98 F
3 X
X N
U/S B, 43.4, Specific question for generic K/A. Replaced.
99 F
2 N
S A, 43.1 100 F
2 B
S B, 43.5