MONTHYEARML12053A3402012-03-12012 March 2012 Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident Project stage: RAI LIC-12-0078, OPPD 90-Day Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendations 2.1 and 2.3 (Flooding), of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2012-06-0808 June 2012 OPPD 90-Day Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendations 2.1 and 2.3 (Flooding), of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Response to RAI LIC-12-0170, 180-Day Response to NRC Request for Information Re Flooding Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2012-11-27027 November 2012 180-Day Response to NRC Request for Information Re Flooding Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Request LIC-13-0102, OPPD Supplemental Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendations 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2013-08-15015 August 2013 OPPD Supplemental Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendations 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Supplement ML13310A8892013-10-26026 October 2013 Superseding Omaha Public Power District'S (OPPD) Response to NRC Request for a Timeline to Implement Strategies at Fort Calhoun Station, Unit 1 to Address Higher Flooding Hazards Relative to the Design Basis Project stage: Request ML14058A2252014-02-26026 February 2014 Extension Request - Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flooding Hazard Reevaluation Report Project stage: Request ML14129A1492014-05-0909 May 2014 Station/Cooper Nuclear Station - Meeting Slide for Flood Hazard Reevaluation Report Schedule Extension Review Project stage: Request ML14139A3582014-06-0505 June 2014 5/9/2014 Summary of Meeting with Omaha Public Power District and Nebraska Public Power District to Discuss Flooding Hazard Evaluation Extension Requests for Fort Calhoun, Unit 1, and Cooper Nuclear Station Project stage: Meeting LIC-14-0078, Extension Request - Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flooding Hazard Reevaluation Report2014-06-0505 June 2014 Extension Request - Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flooding Hazard Reevaluation Report Project stage: Request ML14156A2832014-06-16016 June 2014 Summary of 5/22/2014 Meeting with Omaha Public Power District and Nebraska Public Power District to Discuss Flooding Hazard Evaluation Extension Requests for Fort Calhoun, Unit 1, and Cooper Nuclear Station Project stage: Meeting ML14169A2672014-07-17017 July 2014 Relaxation of Response Due Date Regarding Flooding Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of the Insights from the Fukushima Dai-Ichi Accident Project stage: Approval 2013-08-15
[Table View] |
|
---|
Category:Letter type:LIC
MONTHYEARLIC-24-0012, Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information2024-10-0707 October 2024 Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information LIC-24-0011, Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-00952024-10-0202 October 2024 Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-0095 LIC-24-0007, License Amendment Request (LAR) to Revise License Termination Plan (LTP)2024-06-18018 June 2024 License Amendment Request (LAR) to Revise License Termination Plan (LTP) LIC-24-0008, Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI2024-05-16016 May 2024 Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI LIC-24-0003, Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report2024-04-25025 April 2024 Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-24-0006, (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan2024-04-17017 April 2024 (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan LIC-24-0005, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2024-03-0101 March 2024 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-24-0002, Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report2024-02-27027 February 2024 Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report LIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-22-0006, Reactor Head Disposition Project Overview2022-03-17017 March 2022 Reactor Head Disposition Project Overview LIC-22-0004, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2022-02-17017 February 2022 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-21-0008, Organizational and Management Change2021-10-28028 October 2021 Organizational and Management Change LIC-21-0007, ISFSI Only Emergency Plan Update2021-09-0808 September 2021 ISFSI Only Emergency Plan Update LIC-21-0006, Annual 2021 Decommissioning Funding/Irradiated Fuel Management Status Report2021-09-0808 September 2021 Annual 2021 Decommissioning Funding/Irradiated Fuel Management Status Report LIC-21-0004, Radiological Effluent Release Report and Radiological Environmental Operating Report2021-04-29029 April 2021 Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-21-0003, Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report2021-03-30030 March 2021 Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-21-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-22022 February 2021 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0015, Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092)2020-07-29029 July 2020 Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092) LIC-20-0014, Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2020-07-15015 July 2020 Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-20-0012, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2020-05-18018 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool LIC-20-0011, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-05-0707 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0009, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2020-04-30030 April 2020 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-20-0008, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-04-13013 April 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0006, (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E2020-03-26026 March 2020 (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E LIC-20-0004, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-03-10010 March 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2020-02-27027 February 2020 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0002, Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan2020-02-27027 February 2020 Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan LIC-20-0001, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-02-0606 February 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0025, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-12-19019 December 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0007, Post-Shutdown Decommissioning Activities Report2019-12-16016 December 2019 Post-Shutdown Decommissioning Activities Report LIC-19-0021, Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme2019-11-20020 November 2019 Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme LIC-19-0022, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-11-18018 November 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0018, Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2019-11-14014 November 2019 Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-19-0020, Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis2019-10-17017 October 2019 Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis LIC-19-0017, Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 20042019-08-0808 August 2019 Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 An LIC-19-0010, License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associa2019-05-20020 May 2019 License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated LIC-19-0008, Submittal of 2018 Annual Report2019-04-0404 April 2019 Submittal of 2018 Annual Report LIC-19-0004, Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP)2019-03-28028 March 2019 Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP) LIC-19-0005, 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report2019-03-28028 March 2019 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report LIC-19-0001, License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2019-02-28028 February 2019 License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme LIC-19-0003, Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation R2019-02-28028 February 2019 Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation Requ LIC-19-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2019-01-0303 January 2019 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2024-06-18
[Table view] |
Text
WITHHOLD FROM PUBLIC DISCLOSURE UNDER 10 CFR 2.390 ENCLOSURE 2 CONTAINS SECURITY-RELATED INFORMATION.
UPON REMOVAL OF ENCLOSURE 2, THIS LETTER IS DECONTROLLED.
UPPAW OmahaPublic PowerDistct 444 South 1eh Street Mall Omaha, NE 68102-2247 10 CFR 50.54(f)
LIC-14-0078 June 5, 2014 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285
Subject:
Extension Request - Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 2, Flooding Hazard Reevaluation Report
References:
See Page 3 On February 26, 2014, OPPD requested NRC approval to extend the scheduled submittal date for the FCS Flooding Hazard Reevaluation Report to ten (10) months after data from the USACE System Dam Failure Analysis was received (Reference 1). Reference 2 transmitted the USACE System Dam Failure Analysis to OPPD on April 4, 2014. Reference 3 summarizes a closed meeting between the NRC and OPPD in which OPPD provided a strategy for mitigating the effects of beyond design basis floods up to a certain flood level for FCS. In Reference 4 OPPD provided a timeline for implementing these strategies. Attachment 1 to Reference 4 provided a list of the actions taken or planned to be taken along with additional supporting details and the dates by which they have or will be implemented. Reference 5 documents the NRC inspection of interim mitigation actions for potential flooding hazards in which no findings were identified.
OPPD is in the process of assessing our strategies discussed in References 3 and 4 factoring in the information provided in Reference 2. Enclosure 1 to this letter contains new regulatory commitments. These new regulatory commitments supersede the commitments in Reference 4 for reasons explained in Enclosure 2. Enclosure 2 provides the status of and information from the assessment of flooding mitigation strategies.
If you should have any questions regarding this submittal or require additional information, please contact Mr. Bill R. Hansher at (402) 533-6894.
WITHHOLD FROM PUBLIC DISCLOSURE UNDER 10 CFR 2.390 ENCLOSURE 2 CONTAINS SECURITY-RELATED INFORMATION.
UPON REMOVAL OF ENCLOSURE 2, THIS LETTER IS DECONTROLLED.
Employment with Equal Opportunity
WITHHOLD FROM PUBLIC DISCLOSURE UNDER 10 CFR 2.390 ENCLOSURE 2 CONTAINS SECURITY-RELATED INFORMATION.
UPON REMOVAL OF ENCLOSURE 2, THIS LETTER IS DECONTROLLED.
U. S. Nuclear Regulatory Commission LIC-14-0078 Page 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on June 5, 2014.
Respectfly, Louis P. Cortopassi Site Vice President and CNO LPC/JKG/brh
Enclosures:
- 1. Summary of Regulatory Commitments
- 2. Higher Flood Hazards Relative to Design Basis c: E. J. Leeds, Director of Office of Nuclear Reactor Regulation (w/o Enclosure 2)
M. L. Dapas, NRC Regional Administrator, Region IV J. W. Sebrosky, NRC Senior Project Manager J. C. Kirkland, NRC Senior Resident Inspector WITHHOLD FROM PUBLIC DISCLOSURE UNDER 10 CFR 2.390 ENCLOSURE 2 CONTAINS SECURITY-RELATED INFORMATION.
UPON REMOVAL OF ENCLOSURE 2, THIS LETTER IS DECONTROLLED.
WITHHOLD FROM PUBLIC DISCLOSURE UNDER 10 CFR 2.390 ENCLOSURE 2 CONTAINS SECURITY-RELATED INFORMATION.
UPON REMOVAL OF ENCLOSURE 2, THIS LETTER IS DECONTROLLED.
U. S. Nuclear Regulatory Commission LIC-14-0078 Page 3
References:
- 1. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), Extension Request - Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2. 1, Flooding, Required Response 2, Flooding Hazard Reevaluation Report, dated February 26, 2014, Accession No. ML14058A225 (LIC-14-0010)
- 2. NRC Letter, Fort Calhoun Station, Unit No. 1 - Redacted Letter, Transmittal of U.S. Army Corp of Engineers Flood Hazard Reevaluation Information (TAC No. MF3036), dated April 4, 2014, Accession No. ML14091A345
- 3. NRC Letter, Summary of Closed Meeting Held on April 22, 2013, with Omaha Public Power District to Discuss Means for Protecting Fort Calhoun Station Unit 1 , Against Flooding (TAC No. MF0598), dated April 25, 2012 (ML13114A881)
- 4. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), Superseding Omaha Public Power District's (OPPD) Response to NRC Request for a Timeline to Implement Strategies at Fort Calhoun Station Unit 1 to Address Higher Flooding Hazards Relative to the Design Basis, dated October 26,2013, (ML13310A889) (LIC-13-0140)
- 5. NRC Letter, Fort Calhoun Station - Integrated Inspection Report Number (05000285/2013019) Errata, dated May 20, 2014, (ML14140A572)
WITHHOLD FROM PUBLIC DISCLOSURE UNDER 10 CFR 2.390 ENCLOSURE 2 CONTAINS SECURITY-RELATED INFORMATION.
UPON REMOVAL OF ENCLOSURE 2, THIS LETTER IS DECONTROLLED.
WITHHOLD FROM PUBLIC DISCLOSURE UNDER 10 CFR 2.390 ENCLOSURE 2 CONTAINS SECURITY-RELATED INFORMATION.
UPON REMOVAL OF ENCLOSURE 2, THIS LETTER IS DECONTROLLED.
U. S. Nuclear Regulatory Commission LIC-14-0078 Summary of Regulatory Commitments The following table identifies commitments made in this document. (Any other actions discussed in the submittal represent intended or planned actions. They are described to the NRC for the NRC's information and are not regulatory commitments.)
COMMITMENT COMMITTED DATE COMMITMENT TYPE OR "OUTAGE" One-Time Programmatic Action (Yes/No)
(Yes/No)
Formalize a process to monitor Missouri July 31, 2014 Yes No River basin conditions Complete Gap Analysis and identification July 31, 2014 Yes No of the actions necessary to close the identified gaps Develop a resource loaded schedule for August 31, 2014 Yes No full implementation of the interim strategy before the Spring 2015 refueling outage WITHHOLD FROM PUBLIC DISCLOSURE UNDER 10 CFR 2.390 ENCLOSURE 2 CONTAINS SECURITY-RELATED INFORMATION.
UPON REMOVAL OF ENCLOSURE 2, THIS LETTER IS DECONTROLLED.