Public Meeting on the Operating License Public Meeting on the Operating License Application for Watts Bar Nuclear Plant Unit 2 April 9, 2014 1
Meeting Agenda eet g
ge da
- Introductions
Introductions
- TVA presentation on project status
- NRC presentation on project status and remaining p
p j
g activities
- Questions and comments 2
Topics op cs
- Background
Background
- Restart of Unit 2 Review
- Licensing Activities g
- Oversight Activities
- Upcoming Milestones
- Public Involvement
- Questions 3
=
Background===
1971 - Under Part 50, NRC receives construction permit (CP) application 1972 M
d t h
i h ld 1972 - Mandatory hearings held 1973 - CPs issued 1976 - Operating licenses (OLs) received 1976 Operating licenses (OLs) received 1985 - TVA suspends construction 1990 to 95 - TVA addresses construction quality issues for Unit 1 and defers work on Unit 2 February 7, 1996 - NRC issues OL for Unit 1 4
Restart of Unit 2 Review 2007 - TVA informs NRC of its intent to restart construction activities and complete construction in 2012 2007 -2008 - NRC established Unit 2 resident inspector office (IMC2517 ADAMS ML13136A301) 2008 - NRC established the licensing review process (LIC-110 ADAMS ML092160833) 2009 - Notice in Federal Register to provide opportunity for hearing 2012 - TVA informs NRC of delays to construction of Unit 2
- Operating License/Fuel load between January and June 2015
- Commercial Operation by December 2015 5
Operating License Review Safety Review Commission OL SSER Environmental Approval OL SSER Review Inspection 6
Licensing Activities g
Staff is working toward an operating license decision in January 2015 Licensing activities completed Licensing activities completed
- Issued 6 Supplemental Safety Evaluation Reports (SSERs) documenting the staffs safety review
- Held 9 ACRS Subcommittee and one Full Committee meetings
- Issued Supplement 2 to the Final Environmental Statement Licensing activities remaining Closing out open items identified in previous 6 SSERs
- Closing out open items identified in previous 6 SSERs
- Final ACRS Subcommittee and Full Committee meetings
- Fukushima Orders review 7
Construction Inspection Program Inspection Manual Chapter (IMC) 2517, Watts Bar Unit 2 Construction Inspection Program NRC Construction Inspection Program IMC 2517 Construction Phase IMC 2512 Startup Testing IMC 2514 Preop Testing
& Operational Prep IMC 2513 8
IMC 2512 IMC 2513
Status of Inspection Items 547 t
ti i
ti it i
th I
ti
- 547 construction inspection items in the Inspection Planning and Scheduling (IP&S) database
- Inspections completed for 378 IP&S items Closed ten (10) Corrective Action Programs and
- Closed ten (10) Corrective Action Programs and Special Programs
- Pre-operational testing inspections started 9
Remaining Inspection Items C
l t i
ti f
169 IP&S it
- Complete inspections for 169 open IP&S items
- Many remaining IP&S items have been inspected, but Many remaining IP&S items have been inspected, but require additional effort to close Planning completed for preoperational testing
- Planning completed for preoperational testing inspections - Waiting on testing to be performed
- Operational readiness inspections started
- Majority of IMC 2514 start up testing inspections 10
- Majority of IMC 2514 start-up testing inspections performed after licensee issuance
Oversight Activities Impact of Constr ction Sched le on Inspection Program Impact of Construction Schedule on Inspection Program
- Increased number of residents to four
- Increased resident support activities from the region
- Focus is on scheduling and inspecting activities
- Focus is on scheduling and inspecting activities Reviewing TVAs Primavera construction schedule Adjusting NRC schedule for remaining inspection items Pace of regional inspections has increased S h d li f i ti
- Scheduling of inspections Scheduled inspections for 77% of the remaining open items Scheduled 34 inspections to review pre-operational activities Scheduled 6 operational readiness inspections Planning underway for transition to the Reactor Oversight Process 11
Milestones http://www.nrc.gov/info-finder/reactor/wb/watts-bar.html 12
Additional Information W b it Website - http://www.nrc.gov/info-finder/reactor/wb/watts-bar.html NRR Office Instruction LIC-110
- ADAMS (http://www.nrc.gov/reading-rm/adams.html) Accession No. ML092160833 ML092160833 Inspection Manual Chapter 2517
- Accession No. ML13136A301 Points of contact Points of contact
- Justin Poole, Senior Project Manager Phone: 301-415-2048 Email: justin.poole@nrc.gov
- Jeanne Dion Project Manager
- Jeanne Dion, Project Manager Phone: 301-415-1349 Email: jeanne.dion@nrc.gov
- Tomy Nazario, Senior Resident Inspector Phone: 423-365-9112 13 Phone: 423 365 9112 Email: tomy.nazario@nrc.gov