ML14108A068

From kanterella
Jump to navigation Jump to search
Enclosure 4: Watts Bar Unit 2 - NRC Slides for Public Meeting on the Operating License Application, April 9, 2014
ML14108A068
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 04/09/2014
From: Haag R
NRC/RGN-II/DCP/CPB3
To:
Michelle Adams
Shared Package
ML14108A050 List:
References
Download: ML14108A068 (13)


Text

Public Meeting on the Operating License Public Meeting on the Operating License Application for Watts Bar Nuclear Plant Unit 2 April 9, 2014 1

Meeting Agenda eet g

ge da

  • Introductions

Introductions

  • TVA presentation on project status
  • NRC presentation on project status and remaining p

p j

g activities

  • Questions and comments 2

Topics op cs

  • Background

Background

  • Restart of Unit 2 Review
  • Licensing Activities g
  • Oversight Activities
  • Upcoming Milestones
  • Public Involvement
  • Questions 3

=

Background===

1971 - Under Part 50, NRC receives construction permit (CP) application 1972 M

d t h

i h ld 1972 - Mandatory hearings held 1973 - CPs issued 1976 - Operating licenses (OLs) received 1976 Operating licenses (OLs) received 1985 - TVA suspends construction 1990 to 95 - TVA addresses construction quality issues for Unit 1 and defers work on Unit 2 February 7, 1996 - NRC issues OL for Unit 1 4

Restart of Unit 2 Review 2007 - TVA informs NRC of its intent to restart construction activities and complete construction in 2012 2007 -2008 - NRC established Unit 2 resident inspector office (IMC2517 ADAMS ML13136A301) 2008 - NRC established the licensing review process (LIC-110 ADAMS ML092160833) 2009 - Notice in Federal Register to provide opportunity for hearing 2012 - TVA informs NRC of delays to construction of Unit 2

- Operating License/Fuel load between January and June 2015

- Commercial Operation by December 2015 5

Operating License Review Safety Review Commission OL SSER Environmental Approval OL SSER Review Inspection 6

Licensing Activities g

Staff is working toward an operating license decision in January 2015 Licensing activities completed Licensing activities completed

- Issued 6 Supplemental Safety Evaluation Reports (SSERs) documenting the staffs safety review

- Held 9 ACRS Subcommittee and one Full Committee meetings

- Issued Supplement 2 to the Final Environmental Statement Licensing activities remaining Closing out open items identified in previous 6 SSERs

- Closing out open items identified in previous 6 SSERs

- Final ACRS Subcommittee and Full Committee meetings

- Fukushima Orders review 7

Construction Inspection Program Inspection Manual Chapter (IMC) 2517, Watts Bar Unit 2 Construction Inspection Program NRC Construction Inspection Program IMC 2517 Construction Phase IMC 2512 Startup Testing IMC 2514 Preop Testing

& Operational Prep IMC 2513 8

IMC 2512 IMC 2513

Status of Inspection Items 547 t

ti i

ti it i

th I

ti

  • 547 construction inspection items in the Inspection Planning and Scheduling (IP&S) database
  • Inspections completed for 378 IP&S items Closed ten (10) Corrective Action Programs and
  • Closed ten (10) Corrective Action Programs and Special Programs
  • Pre-operational testing inspections started 9

Remaining Inspection Items C

l t i

ti f

169 IP&S it

  • Complete inspections for 169 open IP&S items
  • Many remaining IP&S items have been inspected, but Many remaining IP&S items have been inspected, but require additional effort to close Planning completed for preoperational testing
  • Planning completed for preoperational testing inspections - Waiting on testing to be performed
  • Operational readiness inspections started
  • Majority of IMC 2514 start up testing inspections 10
  • Majority of IMC 2514 start-up testing inspections performed after licensee issuance

Oversight Activities Impact of Constr ction Sched le on Inspection Program Impact of Construction Schedule on Inspection Program

- Increased number of residents to four

- Increased resident support activities from the region

- Focus is on scheduling and inspecting activities

- Focus is on scheduling and inspecting activities Reviewing TVAs Primavera construction schedule Adjusting NRC schedule for remaining inspection items Pace of regional inspections has increased S h d li f i ti

- Scheduling of inspections Scheduled inspections for 77% of the remaining open items Scheduled 34 inspections to review pre-operational activities Scheduled 6 operational readiness inspections Planning underway for transition to the Reactor Oversight Process 11

Milestones http://www.nrc.gov/info-finder/reactor/wb/watts-bar.html 12

Additional Information W b it Website - http://www.nrc.gov/info-finder/reactor/wb/watts-bar.html NRR Office Instruction LIC-110

- ADAMS (http://www.nrc.gov/reading-rm/adams.html) Accession No. ML092160833 ML092160833 Inspection Manual Chapter 2517

- Accession No. ML13136A301 Points of contact Points of contact

- Justin Poole, Senior Project Manager Phone: 301-415-2048 Email: justin.poole@nrc.gov

- Jeanne Dion Project Manager

- Jeanne Dion, Project Manager Phone: 301-415-1349 Email: jeanne.dion@nrc.gov

- Tomy Nazario, Senior Resident Inspector Phone: 423-365-9112 13 Phone: 423 365 9112 Email: tomy.nazario@nrc.gov