Category:Report
MONTHYEARRS-24-105, Attachment: Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Environmental Report Additional Information2024-11-14014 November 2024 Attachment: Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Environmental Report Additional Information ML24177A1512024-06-24024 June 2024 Post Accident Monitoring Instrumentation Report ML23346A2392024-01-17017 January 2024 Seismic Hazard Report by the Office of Nuclear Reactor Regulation ML23334A2502023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation NMP1L3469, Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits2022-06-30030 June 2022 Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits CCN:22-15, Annual Commitment Revision Report for the Period 01/01/21 Through 12/31/212022-01-31031 January 2022 Annual Commitment Revision Report for the Period 01/01/21 Through 12/31/21 RS-21-001, Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping2021-01-0404 January 2021 Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping ML20329A3452020-11-24024 November 2020 Relief Request Associated with N-16A Reactor Pressure Vessel Instrument Nozzle Repairs - Submittal of Analyses ML20314A0282020-11-0606 November 2020 Verbal Relief for Penetration Nozzle ML20303A1752020-10-23023 October 2020 Proposed Relief Request from Section XI Repair/Replacement Documentation for Bolting Replacement of Pressure Retaining Bolting ML19310D2042019-09-12012 September 2019 TMI Alerts Testimony NUREG-1437 Supplement 10 Second Renewal GEIS for License Renewal of Nuclear Plants Supplement 10 Second Renewal Peach Bottom SLRA ML19053A4692019-06-10010 June 2019 Staff Review of Seismic Probabilistic Risk Assessment Associated with Reevaluation Seismic Hazard Implementation of the Near Term Task Force Recommendation 2.1: Seismic ML19007A3302019-01-0707 January 2019 Final Report PBAPS Thermal Study ML18354B0662018-12-20020 December 2018 Summary of Monitoring Well Installation Details RS-18-113, Report of Full Compliance with Phase 1 and Phase 2 of June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident.2018-09-28028 September 2018 Report of Full Compliance with Phase 1 and Phase 2 of June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident. RS-18-098, Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from .2018-08-28028 August 2018 Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from . ML18093A3822018-03-30030 March 2018 Decommissioning Status Report - 2017 ML18053A0232018-02-22022 February 2018 Compilation of Industry Provided Information on Anchor Darling Double Disc Gate Valve Population Affected by Flowserve, Part 21 Issue of Wedge Pin Failure on an Anchor Darling Double Disc Gate Valve in Report Format with Valve Count RS-18-002, Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2018-01-0505 January 2018 Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) ML17093A6972017-03-30030 March 2017 Decommissioning Status Report - 2016 ML19064B2232017-02-24024 February 2017 Final Report for Post-EPU Thermal and Biological Monitoring Peach Bottom Atomic Power Station ML17027A0152017-01-27027 January 2017 ISFSI - Biennial 1OCFR 50.59 and 10CFR 72.48 Reports for the Period 1/1/2015 Through 12/31/2016 and Annual Commitment Revision Report for the Period 1/1/16 Through 12/31/16 ML16342B6212016-12-0707 December 2016 Results of Visual Inspections of Replacement Steam Dryer RS-16-103, Mitigating Strategies Flood Hazard Assessment (Msfha) Submittal2016-06-30030 June 2016 Mitigating Strategies Flood Hazard Assessment (Msfha) Submittal ML16048A4412016-02-17017 February 2016 Transmittal of Extended Power Uprate: Results of Replacement Steam Dryer Power Ascension Testing ML19064B2162015-12-31031 December 2015 Data Report or Intake Screen Sampling at Peach Bottom Atomic Power Station in 2015 ML15275A1682015-10-0202 October 2015 Attachment 2, LTR-BWR-ENG-15-076-NP, Revision 1, Replacement Steam Dryer Report at Predicted EPU Conditions (Non-Proprietary) and Attachment 3, Affidavit ML15233A0952015-08-20020 August 2015 To LTR-BWR-ENG-15-076-NP, Replacement Steam Dryer Report at Predicted EPU Conditions ML15219A6182015-08-0707 August 2015 Extended Power Uprate: Results of Unit 2 Replacement Steam Dryer Power Ascension Testing ML15051A2622015-04-20020 April 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f), Seismic Hazard Reevaluations Related to Recommendation 2.1 ML15097A0762015-04-0606 April 2015 Soarca Peach Bottom 2005 Site File ML15096A0082015-04-0505 April 2015 Extended Power Uprate: Response to Replacement Steam Dryer Requests for Additional Information ML15026A4692015-02-12012 February 2015 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to EA-13-109 (Severe Accident Capable Hardened Vents) ML15029A6402015-01-29029 January 2015 Mellla+ License Amendment Request Supplement 1 Supplemental Reload Licensing Report ML15028A3812015-01-28028 January 2015 Independent Spent Fuel Storage Installation (ISFSI) - Biennial 10 CFR 50.59 and 10CFR 72.48 Reports for the Period 1/1/2013 Through 12/31/2014 and Annual Commitment Revision Report for Period 1/1/14 - 12/31/14 ML19064B2142014-12-31031 December 2014 Data Report or Intake Screen Sampling at Peach Bottom Atomic Power Station in 2014 RS-14-300, Expedited Seismic Evaluation Process Report (CEUS Sites), Response to Nrg Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.12014-12-19019 December 2014 Expedited Seismic Evaluation Process Report (CEUS Sites), Response to Nrg Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 RS-14-277, Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 12014-09-24024 September 2014 Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1 ML14176A9612014-06-24024 June 2014 Submittal of Non-Proprietary BWROG Technical Product, BWROGTP-11-006 - ECCS Containment Walkdown Procedure, Rev 1 (January 2011), as Formally Requested During the Public Meeting Held on April 30, 2014 ML14119A0572014-06-17017 June 2014 Staff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident (Tac Nos. MF0261 and MF0262) ML14086A6242014-04-30030 April 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident (MF0157 and MF0158) ML14105A3852014-04-11011 April 2014 Attachment 8: WCAP-17635-NP, Rev. 3, Comprehensive Vibration Assessment Program ML14105A3862014-04-11011 April 2014 Attachment 9: WCAP-17649-NP, Rev. 2, ASME Code Stress Report (Enclosure B.3) ML14105A3872014-04-11011 April 2014 Attachment 10: WCAP-17654-NP, Rev. 4, Replacement Steam Dryer Power Ascension Program Description for Extended Power Uprate ML14105A3882014-04-11011 April 2014 Attachment 11: WCAP-17655-NP, Rev. 4, Replacement Steam Dryer Power Ascension Program Description for Extended Power Uprate ML14072A0262014-03-31031 March 2014 WCAP-17655-NP, Rev 3,Peach Bottom Unit 3 Replacement Steam Dryer Power Ascension Program Description for Extended Power Uprate ML14072A0252014-03-31031 March 2014 WCAP-17654-NP, Rev 3, Peach Bottom Unit 2 Replacement Steam Dryer Power Ascension Program Description for Extended Power Uprate ML14072A0242014-03-31031 March 2014 WCAP-17609-NP, Rev 2, Peach Bottom Units 2 and 3 Replacement Steam Dryer Structural Evaluation for High-Cycle Acoustic Loads ML14072A0232014-03-31031 March 2014 WCAP-17635-NP, Rev 2, Peach Bottom Atomic Power Station Unit 2 and Unit 3 Replacement Steam Dryer Comprehensive Vibration Assessment Program RS-14-001, Enclosure 1, Seismic Walkdown Report in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Updated Transmittal 1 (Annex a) for the Peach Bottom, Unit 3. Report No. RS-14-0012014-03-25025 March 2014 Enclosure 1, Seismic Walkdown Report in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Updated Transmittal 1 (Annex a) for the Peach Bottom, Unit 3. Report No. RS-14-001 2024-06-24
[Table view] Category:Technical
MONTHYEARRS-24-105, Attachment: Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Environmental Report Additional Information2024-11-14014 November 2024 Attachment: Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Environmental Report Additional Information ML23346A2392024-01-17017 January 2024 Seismic Hazard Report by the Office of Nuclear Reactor Regulation NMP1L3469, Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits2022-06-30030 June 2022 Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits RS-21-001, Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping2021-01-0404 January 2021 Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping ML20329A3452020-11-24024 November 2020 Relief Request Associated with N-16A Reactor Pressure Vessel Instrument Nozzle Repairs - Submittal of Analyses ML20314A0282020-11-0606 November 2020 Verbal Relief for Penetration Nozzle ML19310D2042019-09-12012 September 2019 TMI Alerts Testimony NUREG-1437 Supplement 10 Second Renewal GEIS for License Renewal of Nuclear Plants Supplement 10 Second Renewal Peach Bottom SLRA ML19053A4692019-06-10010 June 2019 Staff Review of Seismic Probabilistic Risk Assessment Associated with Reevaluation Seismic Hazard Implementation of the Near Term Task Force Recommendation 2.1: Seismic ML19007A3302019-01-0707 January 2019 Final Report PBAPS Thermal Study ML18354B0662018-12-20020 December 2018 Summary of Monitoring Well Installation Details RS-18-113, Report of Full Compliance with Phase 1 and Phase 2 of June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident.2018-09-28028 September 2018 Report of Full Compliance with Phase 1 and Phase 2 of June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident. RS-18-098, Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from .2018-08-28028 August 2018 Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from . RS-18-002, Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2018-01-0505 January 2018 Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) ML16048A4412016-02-17017 February 2016 Transmittal of Extended Power Uprate: Results of Replacement Steam Dryer Power Ascension Testing ML15275A1682015-10-0202 October 2015 Attachment 2, LTR-BWR-ENG-15-076-NP, Revision 1, Replacement Steam Dryer Report at Predicted EPU Conditions (Non-Proprietary) and Attachment 3, Affidavit ML15233A0952015-08-20020 August 2015 To LTR-BWR-ENG-15-076-NP, Replacement Steam Dryer Report at Predicted EPU Conditions ML15219A6182015-08-0707 August 2015 Extended Power Uprate: Results of Unit 2 Replacement Steam Dryer Power Ascension Testing ML15029A6402015-01-29029 January 2015 Mellla+ License Amendment Request Supplement 1 Supplemental Reload Licensing Report RS-14-300, Expedited Seismic Evaluation Process Report (CEUS Sites), Response to Nrg Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.12014-12-19019 December 2014 Expedited Seismic Evaluation Process Report (CEUS Sites), Response to Nrg Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 RS-14-277, Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 12014-09-24024 September 2014 Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1 ML14176A9612014-06-24024 June 2014 Submittal of Non-Proprietary BWROG Technical Product, BWROGTP-11-006 - ECCS Containment Walkdown Procedure, Rev 1 (January 2011), as Formally Requested During the Public Meeting Held on April 30, 2014 ML14105A3852014-04-11011 April 2014 Attachment 8: WCAP-17635-NP, Rev. 3, Comprehensive Vibration Assessment Program ML14105A3882014-04-11011 April 2014 Attachment 11: WCAP-17655-NP, Rev. 4, Replacement Steam Dryer Power Ascension Program Description for Extended Power Uprate ML14105A3872014-04-11011 April 2014 Attachment 10: WCAP-17654-NP, Rev. 4, Replacement Steam Dryer Power Ascension Program Description for Extended Power Uprate ML14105A3862014-04-11011 April 2014 Attachment 9: WCAP-17649-NP, Rev. 2, ASME Code Stress Report (Enclosure B.3) ML14072A0252014-03-31031 March 2014 WCAP-17654-NP, Rev 3, Peach Bottom Unit 2 Replacement Steam Dryer Power Ascension Program Description for Extended Power Uprate ML14072A0242014-03-31031 March 2014 WCAP-17609-NP, Rev 2, Peach Bottom Units 2 and 3 Replacement Steam Dryer Structural Evaluation for High-Cycle Acoustic Loads ML14072A0232014-03-31031 March 2014 WCAP-17635-NP, Rev 2, Peach Bottom Atomic Power Station Unit 2 and Unit 3 Replacement Steam Dryer Comprehensive Vibration Assessment Program ML14072A0262014-03-31031 March 2014 WCAP-17655-NP, Rev 3,Peach Bottom Unit 3 Replacement Steam Dryer Power Ascension Program Description for Extended Power Uprate RS-14-001, Enclosure 1, Seismic Walkdown Report in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Updated Transmittal 1 (Annex a) for the Peach Bottom, Unit 3. Report No. RS-14-0012014-03-25025 March 2014 Enclosure 1, Seismic Walkdown Report in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Updated Transmittal 1 (Annex a) for the Peach Bottom, Unit 3. Report No. RS-14-001 ML19007A3282014-02-28028 February 2014 Final Report for the Thermal Study to Support a 316(a) Demonstration ML14077A0952014-01-30030 January 2014 BWROG-TP-14-001, Rev. 0, Containment Accident Pressure Committee (344) Task 1 - Cfd Report and Combined Npshr Uncertainty for Browns Ferry/ Peach Bottom Cvic RHR Pumps, Attachment 8 ML14077A0902013-12-31031 December 2013 BWROG-TP-13-021, Rev. 0, Containment Accident Pressure Committee (344) Task 4 - Operation in Maximum Erosion Rate Zone (Cvic Pump), Attachment 11 ML13220A1052013-11-22022 November 2013 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 - Mitigation Strategies ML13317A9502013-11-20020 November 2013 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Peach Bottom Atomic Power Station, Units 2 and 3, TAC Nos.: MF0845 and MF0846 ML19186A3832013-07-31031 July 2013 Analysis for the Maryland Department of Natural Resources Question of the Effect of Peach Bottom Station Uprate on Migratory Fishes. Prepared for Exelon Generation by Normandeau Associates, Inc. and Environmental Resource Management. July 2 ML14077A0912013-06-30030 June 2013 BWROG-TP-13-008, Rev. 0, Containment Accident Pressure Committee (344) Task 2 - Equation for Pump Speed Correction (Cvic Pump), Attachment 9 ML14077A0922013-06-30030 June 2013 BWROG-TP-13-010, Containment Accident Pressure Committee (344) Task 6 - Npshr Test Instrument Accuracy Effect on the Published Results (Cvic Pump), Attachment 13 ML14077A1022013-06-30030 June 2013 BWROG-TP-13-009, Rev. 0, Containment Accident Pressure Committee (344) Task 3 Pump Operation at Reduced Npsha Conditions (Cvic Pump), Attachment 10 ML13175A1102013-05-31031 May 2013 NEDO-33533, Revision 1, Peach Bottom Atomic Power Station Units 2 and 3 Safety Valve Setpoint Tolerance Increase Safety Analysis Report ML13032A5502013-01-31031 January 2013 NEDO-33808, Revision 0, Peach Bottom Atomic Power Station Units 2 and 3 SIL 636 Evaluation of Small Break Loca RS-12-174, Company, LLCs 180-day Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2012-11-19019 November 2012 Company, LLCs 180-day Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident ML12286A0152012-09-30030 September 2012 License Amendment Request - Extended Power Uprate, Attachment 4, NEDO-33566, Rev. 0, Safety Analysis Report, Constant Pressure Power Uprate, Page 2-359 Through Page 2-487 ML12286A0142012-09-30030 September 2012 License Amendment Request - Extended Power Uprate, Attachment 4, NEDO-33566, Rev. 0, Safety Analysis Report, Constant Pressure Power Uprate, Page 2-223 Through Page 2-358 ML12286A0132012-09-30030 September 2012 License Amendment Request - Extended Power Uprate, Attachment 4, NEDO-33566, Rev. 0, Safety Analysis Report, Constant Pressure Power Uprate, Cover Through Page 2-222 ML12286A0192012-09-30030 September 2012 License Amendment Request - Extended Power Uprate, Attachment 15, WCAP-17635-NP - Enclosure 15A, Rev. 1, Replacement Steam Dryer Comprehensive Vibration Assessment Program (Cvap) ML12286A0212012-09-30030 September 2012 License Amendment Request - Extended Power Uprate, Attachment 15, WCAP-17609-NP, Rev. 1 - Enclosure B2, Replacement Steam Dryer Structural Evaluation for High-Cycle Acoustic Loads ML12286A0222012-09-30030 September 2012 License Amendment Request - Extended Power Uprate, Attachment 15, WCAP-17649-NP, Rev. 0 - Enclosure B3, ASME Code Stress Report ML12286A0572012-09-30030 September 2012 License Amendment Request - Extended Power Uprate, Attachment 15, WCAP-17654-NP, Rev. 2 - Enclosure B.4U2, Replacement Steam Dryer Power Ascension Program Description for Extended Power Update ML12286A0582012-09-30030 September 2012 License Amendment Request - Extended Power Uprate, WCAP-17655-NP, Revision 2, Peach Bottom Unit 3 Replacement Steam Dryer Power Ascension Program Description for Extended Power Uprate 2024-11-14
[Table view] |
Text
Attachment 10 Peach Bottom Atomic Power Station Units 2 and 3 NRC Docket Nos. 50-277 and 50-278 WCAP-17654, Rev 3. Peach Bottom Unit 2 Power Ascension Program Description for Extended Power UDrate
Westinghouse Non-Proprietary Class 3 WCAP-17654-NP M
Revision 3 Peach Bottom Unit 2 Replacement Steam Dryer Power Ascension Program Description for Extended Power Uprate Westinghouse arch 2014
WESTINGHOUSE NON-PROPRIETARY CLASS 3 WCAP-17654-NP Revision 3 Peach Bottom Unit 2 Replacement Steam Dryer Power Ascension Program Description for Extended Power Uprate March 2014 Author:
Thomas Zalewski*
Engineering Projects Reviewer:
David A. Suddaby
- BWR Plant & Stress Analysis Approved:
David R. Forsyth*, Manager BWR Plant and Stress Analysis
- Electronically approved records are authenticated in the electronic document management system.
Westinghouse Electric Company LLC 1000 Westinghouse Drive Cranberry Township, PA 16066, USA
© 2014 Westinghouse Electric Company LLC All Rights Reserved
ii Record of Revisions Rev Revision Description Date 0
Original August 2012 1
MSL Limit curves updated based on ACM Rev. 4.2 analysis August 2012 2
Minor content edits September 2012 3
Content updated to reflect the use of[
March 2014 Since the changes were extensive, revision bars were not utilized.
WCAP-17654-NP March 2014 Revision 3
iii TABLE OF CONTENTS I
INTRODUCTION AND PURPOSE............................................................................................
1-1 2
POWER ASCENSION PROGRAM (PAP) SCOPE...............................................................
2-1 2.1 PARAMETER MONITORING.................................................................................
2-I 2.1.1 Steam Dryer [
]a.c............... 2-1 2.1.2 Steam Dryer Indirect Data Monitoring (Main Steam Line Strain Gauges)..... 2-2 2.2 POWER ASCENSION PROGRAM................................................................................
2-2 2.2.1 RSD PAP Test Level A (Low Power (<25%) to 100% of CLTP Power L ev el)...............................................................................................................
2 -2 2.2.2 RSD PAP Test Level B (100% CLTP Power Level to 112.4% CLTP Power L ev el)...............................................................................................................
2 -2 2.3 NRC COMMUNICATION..............................................................................................
2-3 2.3.1 Interface during RSD PAP...............................................................................
2-3 2.3.2 W ritten R eports................................................................................................
2-3 3
R E FE R E N C E S.............................................................................................................................
3-1 WCAP-17654-NP March 2014 Revision 3
iv LIST OF TABLES
].c...................................................................... 2-1 Table 2-1 Steam Dryer [
WCAP-17654-NP March 2014 Revision 3
1-1 1
INTRODUCTION AND PURPOSE This document describes the Exelon Peach Bottom Atomic Power Station Unit 2 Extended Power Uprate (EPU) Replacement Steam Dryer (RSD) Power Ascension Program (PAP). The RSD PAP includes the planned course of action for monitoring and evaluating the performance of the RSD during power ascension testing to EPU power level and operation.
The RSD PAP is divided into two test levels, A and B, to ensure sufficient monitoring of the RSD as defined in Regulatory Guide 1.20 Rev 3 (Reference 1).
Test Level A - Performs baseline data gathering from low power (<25%) to 100% (>0 MWt to 3514 MWt) of the Current Licensed Power Level (CLTP). Current Licensed Power Level (CLTP) is 3514 MWt.
Test Level B - Performs testing from approximately 100% to 112.4% of CLTP (3514 M Wt to 3951 MWt).
EPU power level is 3951 MWt.
The purpose of the PBAPS U2 RSD PAP is to provide assurance that the stresses in the individual steam dryer components will be conservative with respect to the calculated values, consistent with section 2.1 of Reference 1. This will confirm the RSD performs as predicted with the [
]a,, methodologies. The RSD PAP is a portion of the overall EPU Power Level startup testing program, which is presented in Attachment 10 of the LAR submittal.
Completion of the RSD PAP will ensure that the integrity of the steam dryer will be maintained in an acceptable state at EPU power.
The RSD PAP assesses the steam dryer performance for the EPU power level startup power ascension process. Each section establishes operating limits, data collection and analysis requirements, and any subsequent actions if necessary. There are three main elements of the RSD PAP:
- 1.
Power ascension with defined hold points and durations, allowing time for monitoring and analysis for ascension up to EPU power.
- 2.
A detailed power ascension monitoring and analysis program to trend steam dryer performance through the monitoring of RSD strain gauges. In addition, RSD accelerometers, and RSD pressure transducers will be monitored. These instruments are directly installed on the RSD.
- 3.
Documentation of the results from the instrumentation will be submitted to the NRC in reports consistent with Regulatory Guide 1.20 Rev 3 (Reference 1).
This program includes specific hold points and durations during power ascension; activities to be accomplished during hold points; data to be collected; data evaluation methods; and acceptance criteria for monitoring and trending plant parameters. This program is consistent with the guidance contained in Regulatory Guide (RG) 1.20 Rev 3 (Reference 1). Detailed procedures will be developed to implement this program.
WCAP-17654-NP March 2014 Revision 3
2-1 2
2.1 POWER ASCENSION PROGRAM (PAP) SCOPE PARAMETER MONITORING I
]a,c 2.1.1 Steam Dryer [
[
I 2.C
]a.c Table 2-I Steam Dryer [ I"*
a,c WCAP-17654-NP March 2014 Revision 3
2-2 2.1.2 Steam Dryer Indirect Data Monitoring (Main Steam Line Strain Gauges) pac 2.2 POWER ASCENSION PROGRAM Detailed test procedures will be developed for the implementation of the actual power ascension testing evolutions. The power ascension will occur over a period of time with gradual increases in power, hold periods, and engineering analysis of monitored data prior to subsequent power increases.
2.2.1 RSD PAP Test Level A (Low Power (<25%) to 100% of CLTP Power Level)
The RSD PAP Test Level A includes collection of data from low power (less than 25% RTP) to 3514 MWt. Instrumentation data will be obtained for baseline data at increments consistent with the overall Power Ascension Program.
Monitoring and Analysis - RSD PAP Test Level A Power ascension between 0 MWt and 3514 MWt will be achieved via the following methodology:
- 1.
Collection of data from low power (less than 25% RTP) to 3514 MWt.
- 2.
At increments consistent with the overall Power Ascension Program (Attachment 10 of the LAR submittal), compare measured plant data against predicted plant data.
- 3.
The duration of the individual power ascension steps will be determined by the time required to obtain the specified data.
EGC will perform
]ac 2.2.2 RSD PAP Test Level B (100% CLTP Power Level to 112.4% CLTP Power Level)
[
WCAP-17654-NP March 2014 Revision 3
2-3
]a,c Monitoring and Analysis - RSD PAP Test Level B The assessment of the system/component performance and integrity will be completed through the
]ac As noted, dryer performance and integrity will be evaluated [
]a.c 2.3 NRC COMMUNICATION 2.3.1 Interface during RSD PAP A brief stress summary report for the replacement steam dryer (RSD) based on [
]a.C A summary of the
]a~c 2.3.2 Written Reports The results of the power ascension testing for the RSD will be submitted to the NRC in a report within 90 days of completion of Peach Bottom Unit 2 EPU power ascension testing. [
]a.c WCAP-17654-NP March 2014 Revision 3
3-1 3
REFERENCES
- 1.
Regulatory Guide 1.20, Revision 3, "Comprehensive Vibration Assessment Program for Reactor Internals During Preoperational And Initial Startup Testing," March 2007 (ADAMS Accession No. ML070260376).
WCAP-17654-NP March 2014 Revision I