Text
oa-UNITED STATES q
NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 November 30, 1981 Docket No. 50-206
/
LSO5-81-11-083 MEMORANDUM FOR:
Thomas V. Wambach, Acting Chief Operating Reactors Branch #5, DL FROM:
Stanley J. Nowicki, Project Manager Operating Reactors Branch #5, DL
SUBJECT:
FORTHCOMING MEETING WITH SOUTHERN CALIFORNIA EDISON COMPANY REGARDING SAN ONOFRE NUCLEAR GENERATING STATION UNIT 1 DATE & TIME:
December 1, 1981 -
1:30 pm LOCATION:
P-110 Phillips Building, Bethesda, Maryland PURPOSE:
To discuss Southern California Edison's letter dated November 23, 1971 regarding SEP Topic 111-6 (agenda enclosed).
PARTICIPANTS:
NRC G. Lainas, W. Russell, T, Wambach, F. Schauer, S. Burns
- 0. Rothberg, P. Kuo, K. C. Leu, J. P. Knight.
SCE K. Baskin, R. Krieger, J. Rainsberry, supporting staff and consultants ORIGINAL SIGNED BY THOMAS V. WAMBACH FOR Stanley J. Nowicki, Project Manager Operating Reactors Branch #5 Division of Licensing
Enclosure:
'Agenda cc w/enclosure:
See next page 8112070090 811130' PDR ADOCK 05000206 T
~P PDR1 own OL.;0RB.#.515P.M DL..0RB OF~ c J.O
- ./ M D :O B # C.
SURNA Snow.i.k.i.:.rj... Tambach......................
C F
(....8 8..................................
0ICU
- NRC FORM 318 (10-80) NRCM 0240 OFFICIAL RECORD COPY USGPO: 1981-335-960
DISTRIBUTION FOR MEETING NOTICE Docket NRC PDR Local PDR TERA NSIC ORB #5 Reading J. Heletemes
- 3. Leonard G. Lainas D. Crutchfield H. Smith Project Manager - T. Wambach C. W. Thayer (BWRs)
S. Showe (PWRs)
W. Russell G. Cwalina S. Varga T. Ippolito R. A. Clark J. Stolz OELD O&E (3)
OSD Receptionist ACRS (10)
Participants:
F. Schauer S. BuIrnS
Rainesberry. SCE
Mr. R. Dietch 2 -
November 30, 1981 cc w/enclosure:
Charles R. Kocher, esquire Mr. R. Dietch, Vice President Assistant General Counsel Nuclear Engineering and Operations James Beoletto, Esquire Southern Californi&Edison Company Southern California Edison Company 2244 Walnut Grove Avenue Post Office Box'800 Post Office Box 800 Rosemead, California 91770 Rosemead, California 91770 David R. Pigott, Esquire Orrick, Herrington & Sutcliffe 600 Montgomery Street San FranciscoR California 94111 NlHarry B. StoehrEn San Diego Gas & Electric Company P.
P0.
Box 1831 San Diego, California a.92112 Resident Inspector/San Onofre NPS c/o U. S. NRC P. 0. Box 4329 San Clemente, California 92672 Mission Viejo Branch Library 24851 Chrisanta Drive Mission Viejo, California 92676 City of San Clenente San Clemente, California 92672 Chirman Eoard of Supervisors County of San Diego San Diego, California 92101 California Department of Health ATTN:
Chief, Environmental Radiation Control Unit Radiological Health Section 714 P Street, Room 498 Sacramento, California 95814 U. S. Environmental Protection Agency Region IX Office ATTN:
Regional Radiation Representative 215 Freemont Street San Francisco, California :94111
MEETING WITH SOUTHERN CALIFORNIA EDISON COMPANY SAN ONOFRE-NUCLEAR GENERATING STATION UNIT NO. 1 DECEMBER 1, 1981 AGENDA
- 1. Structural Details of the Fuel Storage Building A. Drawings B. All Calculations and Results of All Analyses
- 2. SCE's Response to the Following Questions:
A. Why does the Spent Fuel Building require extensive modification to meet 0.67g Housner siesmic input while reanalysis of other Category A structuers, which were origininally designed to 0.5g Housner DBE, did not require modifications?
B. What is the structural capacity of the existing Spent Fuel Building?
C. What are the limiting structural members? Is the problem limited to Block Walls above the 42 foot elevation and the roof fr'aming?
D. What are the safety consequences of possible structural failures?.
The effect on decay heat removal systems and the effect upon stored spent fuel should be identified?
E. Based upon the seismic hazard at the site, what is an appropriate schedule for implementation of any necessary modifications? The licensee's current schedule would provide preliminary results.for the Spent Fuel Building by January 31, 1982.
The licensee has not provided a schedule for implementation of modifications for this structure; however, the staff has required a schedule and case-by case justification for any modifications necessary to meet 0.67g Housner SSE which are not implemented by January 1, 1983.
- 3. Any SCE's comments Related to Other Sections of SER Dated November.16, 1981, Regarding Interim Seismic Adequacy with Regard to Availability Applicability, and Correctness of SCE's Supporting Information.
- 4. General Discus'sion of the Methods of Analysis for Other Masonry Load Carrying Walls in Category A Structures.and masonry walls whose failure or displacement could adversely affect the performance of safe shutdown equipment.