UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 SAFETY EVALUATION REPORT GENERIC LETTER 83-28, ITEM 2.1 (PART 2)

VENDOR INTERFACE PROGRAMS (RTS COMPONENTS)

SAN ONOFRE NUCLEAR GENERATING STATION, UNIT 1 DOCKET NO 50-206

1.0 INTRODUCTION

On February 25, 1983, both of the scram circuit breakers at Unit 1 of the Salem Nuclear Power Plant failed to open upon an automatic reactor trip signal from the reactor protection system. This incident was terminated manually by the operator about 30 seconds after the initiation of the automatic trip signal.

The failure of the circuit breakers was determined to be related to the sticking of the undervoltage trip attachment. Prior to this incident, on February 22, 1983, at Unit 1 of the Salem Nuclear Power Plant, an automatic trip signal was generated based on steam generator low-low level during plant start-up. In this case, the reactor was tripped manually by the operator almost coincidentally with the automatic trip.

Following these incidents, on February 28, 1983, the NRC Executive Director for Operations (EDO), directed the staff to investigate and report on the generic implications of these occurrences at Unit 1 of the Salem Nuclear Power Plant.

The results of the staff's inquiry into the generic implications of the Salem unit incidents are reported in NUREG-1000, "Generic Implications of the ATWS Events at the Salem Nuclear Power Plant." As a result of this investigation, the Commission (NRC) requested (by Generic Letter 83-28 dated July 8, 19831 all licensees of operating reactors, applicants for an operating license, and holders of construction permits to respond to generic issues raised by the analyses of these two ATWS events.

8803210420 980316 PDR ADOCK 05000206 PDR

-2 This report is an evaluation of the response submitted by Southern California Edison Company, the licensee for the San Onofre Nuclear Generating Station, Unit 1, for Item 2.1 (Part 2) of Generic Letter 83-28. The actual documents reviewed as part of this evaluation are listed in the references at the end of the report.

Item 2.1 (Part 2) requires the licensee to conform that an interface has been established with the NSSS or with the vendors of each of the components of the Reactor Trip System which includes:

periodic communication between the licensee/applicant and the NSSS or the vendors of each of the components of the Reactor Trip System,

and, a system of positive feedback which confirms receipt by the licensee/

applicant of transmittals of vendor technical information.

2.0 EVALUATION The licensee for the San Onofre Nuclear Generating Station, Unit 1 responded to the requirements of Item 2.1 (Part 2) with a submittal dated November 28, 2

1983.

The licensee stated in this submittal that Westinghouse is the NSSS vendor for the San Onofre, Units 1 plant and that the RTS is included as part of the Westinghouse interface program established for this plant. The response also confirms that this interface program includes both periodic communication between Westinghouse and the licensee and positive feedback from the licensee in the form of signed receipts for technical information transmitted by Westinghouse.

-3

3.0 CONCLUSION

Based on our review of these responses, we find the licensee's statements confirm that a vendor interface program exists with the NSSS vendor for components that are required for performance of the reactor trip function.

This program meets the requirements of Item 2.1 (Part 2) of the Generic Letter 83-28, and is therefore acceptable.

4.0 REFERENCES

1. NRC Letter, D. G. Eisenhut to all Licensees of Operating Reactors, Applicants for Operating License, and Holders of Construction Permits, "Required Actions Based on Generic Implications of Salem ATWS Events (Generic Letter 83-28),"

July 8, 1983.

2. Southern California Edison Company letter to NRC, M. 0.

Medford to Director, Office of Nuclear Reactor Regulation, "Generic Implications of Salem ATWS Events (Generic Letter 83-28)," November 28, 1983.