Informs That Design Details for ATWS Mitigation Sys at Plant Will Be Submitted by 870508.Submittal Date Rescheduled from 870316 Due to Efforts Required for Other Projects,Including Crdr & Penetration for Unit 1 mid-cycle Outage
ML13330B189
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 04/01/1987
From: Medford M
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 8704130443
Download: ML13330B189 (1)


Text

Southern California Edison Company P. 0. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 M.O.MEDFORD TELEPHONE MANAGER OF NUCLEAR ENGINEERING (818) 302-1749 AND LICENSING April 1, 1987 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Gentlemen:

Subject:

Docket No. 50-206 Anticipated Transients Without Scram San Onofre Nuclear Generating Station Unit 1 In our letter dated October 27, 1986, regarding the same subject, we indicated that the plant specific design details for the ATWS Mitigation System at San Onofre Unit 1 would be sent by March 16, 1987.

The purpose of this letter is to inform you that the design details will be submitted by May 8, 1987. The submittal date is being rescheduled due to efforts required for other projects including the installation of the third auxiliary feedwater train, the Unit 1 Control Room Design Review, preparation for the Unit 1 mid-cycle outage and the Units 2 and 3 refueling outage.

If you have any questions regarding this matter, please let me know.

Very truly yours, cc:

R. F. Dudley, NRR Project Manager, San Onofre Unit 1

3. B. Martin, Regional Administrator, NRC Region V F. R. Huey, NRC Senior Resident Inspector, San Onofre Units 1, 2 and 3 6704130443-870401 PDR ADOC41 05000206