DISTRIBUTION:

DOCKET FILE PDR LPDR Branch File D. Eisenhut J. Roe R. Tedesco Branch-Chief Licensing Assistant P. Wooley H. Thompson H. Berkson RSB/RF I&E (3)

ACRS (16)

NS IC TERRA ASLB ASLAB M. Service eo4

MAR 13 1981 Mr. W. R. Gould, President Southern California Edison Company P.O. Box 800 Rosemead, CA 91770

Dear Mr. Gould:

A recent study of the additional time needed to complete the operating license hearing process indicates that a number of plants have the potential for being ready to load fuel from a construction standpoint before the NRC decision on issuance of an operating license is reached. In order to eliminate or minimize the impact of the licensing and hearing process on current operating license applications, revised NRC staff Safety Evaluation Report (SER) and Supplemental Safety Evaluation Report (SSER) dates have been established to be used in work load scheduling by the NRC Office of Nuclear Reactor Regulation (NRR).

A list of plants showing our current schedules for technical input to the NRR Division of Licensing (DL) for SER and SSERs is enclosed (Enclosure 1).

I am also enclosing a more com prehensive schedule showing the relationship of these schedules to other important dates in the licensing process (Enclosure 2).

In general, the changes from previous schedules accelerate the due date for all technical input in order to allow time for a more extended hearing process.

The Commission currently is examining the details of the hearing process seeking ways to eliminate unnecessary delays without jeopardizing any legitimate interests of the parties affected or the public health and safety.

This examination is not yet complete.

In order for the NRR technical staff to meet these accelerated schedules, all information concerning your application identified as needed by the NRR staff must be provided by you or your contractors at least two weeks prior to the date indicated for staff technical input to DL. However, for SER s scheduled to be issued after June 1981, applicants should provide Equipment Qualification (EQ) information in accordance with IE Bulletin 79-01B at least four months prior to the SER issuance date. This request for EQ information amends the previous guidance provided in a letter from R. Tedesco, Assistant Director for Licensing dated November 25, 1980. Your personal attention and commitment is needed to make these accelerated schedules possible.

I also request that you arrange to have people, who can represent you and who can resolve any last minute open items, in residence near NRR headquarters in Bethesda during the two weeks immediately preceding the scheduled technical input deadlines. Your staff is requested to contact the Licensing Project Manager for specific needs related to the review of your application.

OFFICEO SURNAME.

DATE So....

I..

0NM2OF I

RC........... COPY.S.PO...................

1 NRC FORM 318 10/80) NRCM 0240 OFFICIAL RECORD COPY USGPO: 1980-329-824

Mr. W. R. Gould, President

- 2 Of course, if information concerning your application is not available when needed, the NRC staff will be unable to avoid changing your plant's priority consistent with other scheduled work. Working under the very tight schedule indicated means that a slip will affect not only your SER issuance date but will also delay other scheduled dates in the licensing and hearing process related to your plant, including the decision date.

Thank you for your cooperation in this matter.

I will keep you advised of additional information concerning this request and of any further schedule revisions.

Sincerely, Harold R. Denton, Director Office of Nuclear Reactor Regulation

Enclosures:

As stated OFFICEI SURNAMEO e o.R....................E.....................

C Y

NRCTORM 318 110/801 NRCM 0240 USP 10-2.2

___________OFFICIAL RECORD COPY SM18-2-2

Mr. Robert Dietch Vice President Southern California Edison Company 2244 Walnut Grove Avenue P. 0. Box 800 Rosemead, California 91770 Mr. D. W. Gilman Vice President -

Power Supply San Diego Gas & Electric Company 101 Ash Street P. 0. Box 1831 San Diego, California 92112 cc:

Charles R. Kocher, Esq.

James A. Beoletto, Esq.

Southern California Edison Company 2244 Walnut Grove Avenue P. 0. Box 800 Rosemead, California 91770 Chickering & Gregory ATTN:

David R. Pigott, Esq.

Counsel for San Diego Gas & Electric Company &

Southern California Edison Company 3 Embarcadero Center -

23rd Floor San Francisco, California 94112 Mr. George Caravalho City Manager City of San Clemente 100 Avenido Presidio San Clemente, California 92672 Alan R. Watts, Esq.

Rourke & Woodruff Suite 1020 1055 North Main Street Santa Ana, California 92701 Lawrence Q. Garcia, Esq.

California Public Utilities Commission 5066 State Building San Francisco, California 94102 Mr. V. C. Hall Combustion Engineering, Incorporated 1000 Prospect Hill Road Windsor, Connecticut 06095

Mr. Robert Dietch 2

Mr. D. W. Gilman

.3 cc: Mr. P.. Dragolovich Bechtel Power Corporation P. 0. Box 60860, Terminal Annex Los Angeles, California 90060 Mr. Mark Medford Southern California Edison Company 2244 Walnut Grove Avenue P. 0. Box 800 Rosemead, California 91770 Henry Peters San Diego Gas & Electric Company P. 0. Box 1831 San Diego, California 92112 Ms. Lyn Harris Hicks Advocate for GUARD 3908 Calle.Ariana San Clemente, California 92672 Richard J. Wharton, Esq.

Wharton & Pogalies University of San Diego School of Law Environmental Law Clinic San Diego, California 92110 Phyllis M. Gallagher, Esq.

Suite 222 1695 West Crescent Avenue Anaheim, California 92701 Mr. A. S. Carstens 2071 Caminito Circulo Norte Mt. La Jolla, California 92037 Resident Inspector, San Onofre/NPS C/o U. S. Nuclear Regulatory Commission P. 0. Box AA Oceanside, California 92054 Due Dates for Technical Input to SER and SSER Last Tech.

Plant Action Input to DL Susquehanna 1/2 SER 3/23/81 Summer 1 SSER 3/24/81 Sequoyah 2 SSER 4/01/81 San Onofre 2/3 SSER 4/17/81 LaSalle 1/2 SSER 4/30/81 Zimmer 1 SSER 5/01/81 Waterford 3 SER 5/08/81 Comanche Peak SER 5/22/81 Susquehanna 1/2 SSER 5/26/81 Fermi 2 SER 6/10/81 Shoreham 1 SSER 6/10/81 Waterford 3 SSER 7/16/81 Comanche Peak SSER 7/17/81 Grand Gulf 1 SER 8/14/81 Fermi 2 SSER 8/14/81 Watts Bar 1/2 SER 9/11/81 Grand Gulf 1 SSER 10/25/81 Watts Bar 1/2 SSER 11/26/81

ENCLOSURE 2 CY 199T-- 191fl.ANTS Estimated SER SSER Impact SEITT Saff Start NRC Construction (Months)

Technical Issue ACRS Technical Issue of Decision Completion (2)

Plant 1RE FF Input to DL SER (1)

Mtg Input to DL SSER (1)

Hearin (1) Date (1)

TH APIW Salem 2 12 12 (C)

(C)

None (C)

(C)

None 4/81 4/18/80(C) 4/16/80(C)

LaSalle 1 & 2 0

0 2/18/81(C) 3/05/81(C) 4/09/81 4/30/81 5/15/81 None 5/81 9/81 6/81 San Onofre 2 8 3 6

12 (C) 2/06/81(C) 3/12/81 2/19/81(TMI)(C) 2/25/81(TMI)(C) 4/17/81 5/8/81 07/81 4/82 10/81 4/15/81 Diablo Canyon 1 & 2 Low Power 11 13 (C)

(C)

None 2/20/81(C) 3/05/81(C) 05/81 2/82 3/81 1/81 Full Power 12 14 (C)

(C)

None 3/17/81 3731/81 05/81 3/82 3/81 1/81 McGuire 1 & 2 Low Power 0

0 None None None (C) 1/81(C) 2/24/81(H 2) 1/23/81(1) 1/23/81(C) 1/23/81(C)

Full Power 13 13 (C)

(C)

None 2/28/81 3/20/81 06/81 3/82 1/28/81(C) 1/28/81(C)

Farley 2 Low Power 0

0 (C)

(C)

None None None None 10/23/80(1) 10/23/80(C) 10/22/80(C)

Full Power 0

1 None None None 2/19/81(C) 3/06/81(C)

None 3/81 3/81 2/81 Shoreham I 1

5 3/10/81 3/31/81 5/07/81 6/10/81 7/3/81 01/82 10/82 9/82 5/31/82 Summer 1 8

10 (C) 2/06/81(C) 3/12/81 3/24/81 4/15/81 07/81 6/82 10/81 8/81 Susquehanna 1 & 2 8

17 3/23/81 4/06/81 5/07/81 5/26/81 6/15/81 10/81 11/82 3/82 6/81 Sequoyah 2 1

0 (C)

(C)

Nonk 4/01/81 4/15/81 None 4/30/81 6/81 4/15/81 Zimmer 1 3

8 (C)

(C)

None 5/01/81 5/29/81 10/81 7/82 4/82 11/81 Waterford 3 3

3 5/08/81 5/30/81 7/09/81 7/16/81 7/31/81 03/82 1/83 10/82 10/82 Comanche Peak 2

14 5/22/81 6/11/81 7/09/81 7/17/81 8/12/81 03/82 2/83 12/82 12/81 Fermi 2 0

0.

6/10/81 6/30/81 8/09/81 8/14/81 8/31/81 02/82 11/82 11/82 11/82 Grand Gulf 1 0

0 8/14/81 9/07/81 10/13/81 10/25/81 11/15/81 None 12/81 7/82 12/81 Watts Bar 1 & 2 0

1 9/11/81 10/09/81 11/12/81 11/26/81 12/11/81 None 1/82 8/82 11/81 WNP 2.

O 0

2/12/82 3/12/82 4/09/82 4/30/82 5/28/82 None 7/82 7/83 7/82 (1) Based on January 30, 1981 Report to Congress (2) Based on draft information from Office of Management and Program Analysis (MPA) dated February 10, 1981 except for Waterford 3.