ML13329A452

From kanterella
Jump to navigation Jump to search

Acceptance Review of IST Program Relief Request PVRR-001
ML13329A452
Person / Time
Site: Fermi 
(NPF-043)
Issue date: 11/15/2013
From: Thomas Wengert
Plant Licensing Branch III
To: Hassoun A
Detroit Edison, Co
Wengert T
References
TAC MF2927
Download: ML13329A452 (1)


Text

Wengert, Thomas From:

Sent:

To:

Cc:

Subject:

Wengert, Thomas Friday, November 15, 2013 9:36 AM

  • 'Alan I Hassoun' (hassouna@dteenergy.com)

Bedi, Gurjendra.

Fermi 2-Acceptance Review of IST Program Relief Request P\\/RR-001 (TAC No.

MF2927)

By letter dated October 22, 2013 (ADAMS Accession No. ML13296A533), DTE Electric Co. submitted Relief Request PVRR-001, concerning the lnservice Testing Program for Fermi 2, for the third ten-year Interval.

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed. technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any additional information needed to support the NRC staff's detailed technical review by separate correspondence.

Please contact me if you have any questions.

Tom Wengert Sr. Project Manager U.S. Nuclear Regulatory Commission NRRIDORL!LPL3-1 (301) 415-4037 1