ML13323B087

From kanterella
Jump to navigation Jump to search
Insp Repts 50-206/85-37,50-361/85-35 & 50-362/85-34 on 851112-15,1209-18 & 30.Violation Noted:Failure to Record as- Found Settings of Unit 1 Main Steam Relief Valves
ML13323B087
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 01/21/1986
From: Johnson P, Narbut P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML13323B084 List:
References
RTR-NUREG-0612, RTR-NUREG-612, TASK-A-36, TASK-OR 50-206-85-37, 50-361-85-35, 50-362-85-34, GL-85-05, GL-85-5, IEB-84-02, IEB-84-2, NUDOCS 8602130552
Download: ML13323B087 (12)


See also: IR 05000206/1985037

Text

U. S. NUCLEAR REGULATORY COMMISSION

REGION V

Report Nos.

50-206/85-37,

50-361/85-35,

50-362/857j4

37

Docket Nos'.

50-206, 50-361, 50-362

License Nos.

DPR-13) NPF-10

NPF-15

Licensee:

Southern California Edison Company

P. 0. Box 800

2244 Walnut Grove. Avenue

Rosemead, California 92770

Facility Name:

San Onofre Units 1, 2 and 3

Inspection at:

San Onofre, San Clemente, California

Inspection conducted:

November 12-15 and December 9-18 and 30, 1985

Inspector:

I

o

P. P. Narbut, Project Inspector

Date Signed

Aproved By:

I__

___

_

_

_

P. H. Johnson, Chief

Date Signed

Reactor Projects Section No. 3

Summary:

Inspection during period of November 12-15 and December 9-18 and 30, 1985

(Report Nos. 50-206/85-37, 50-361/85-35, 50-362/85-34)

Areas Inspected:

Unannounced inspection by a regional inspector of the

licensee's tests and experiments program and of the licensee actions on

previously identified items. The inspection involved 113 inspection hours

onsite andu24 inspection hours in-office by one inspector. During this

inspection, TE inspection procedures 37703, 92701, 92717, 92712, 90712, and

92703 were. used.

Results:

Of the areas inspected, one violation was identified (failure to

record as-found settings of Unit 1 Main Steam Relief Valves - paragraph 3.a).

8602130552 860127

PDR

ADOCK 05000206

PDR

DETAILS

1.

Persons Contacted

Southern California Edison Company

  • H. B. Ray, Vice President, Site Manager
    • W. G. Zintl, Manager, Compliance
    • C.

A. Kergis, Compliance Engineer

  • N. Maringas, Independent Safety Engineering Group (ISEG)
    • J. T. Reilly, Manager, Station Technical
    • H. E. Morgan, Station Manager
  • R. W. Krieger, Operations Manager
  • J. M. Curran, QA Manager

Z. Inwalski, Station Technical Engineer

M. J. McDevitt, Computer Engineer

S. Goslin, .Station Technical, NSSS

J. Redmon, Station Technical

  1. D. B. Schone, Site QA Manager
  1. M. A. Wharton, Deputy Site Manager
  1. H. W. Newton, Manager, Material Supply
  1. D. E. Shull Jr., Manager, Maintenance
  1. N. Maringas, ISEG Engineer
  1. D. A. Herbst, ISEG Supervisor
  1. W. R. Savage, Maintenance General Foreman
  1. H. Merten, Maintenance Manager
  1. G. Gibson, Supervisor, Compliance

Combustion Engineering, Inc.

G. Bundick, Site Representative

  • Indicates persons attending the exit interview of November 12, 1985.
  1. Indicates persons attending the exit interview of December 18, 1985.

2.

Examination of Tests and Experiments Program (37703)

The inspector examined the licensee's program for the control of tests

and experiments to assure that it was in conformance with regulatory

requirements.

10 CFR 50.59 authorizes licensees to make changes from the conditions

described in the FSAR. The licensee is authorized, therein, to perform

tests and experiments different from those described in the FSAR.

Limitations and conditions are placed on the changes that the licensee

can make. Prior NRC approval is required if the change involves an

unreviewed safety question or is not in accordance with technical

specifications. The licensee is required (when implementing departures

from the FSAR description) to maintain a record of the experiment,

perform a safety evaluation, and make an annual report to the NRC.

2

The most difficult aspect 'ofthis process is the determination of whether

a test or experiment is different from that described in the.FSAR.

Clearly, the regulation was not intended to limit endeavors such as

troubleshooting components in isolatedportions of systems .or performing

detailed maintenance procedures (none of which are described in the

FSAR).

Procedures

The inspector'.reviewed the licensee's, implementing procedures, which

prescribed requirements for tests.nd experiments to verify that the

requirements and/or commitments of 10.CFR 50.59, ANSI 18.7, the FSAR and

the licensetechnical spectficatidns were incorporated. The'procedures

reviewed were:

o

50123

I-1.0 Revision 10, Dbcument Review and Approval Process

a

50123 VI-1.3 Documenting Safety and*Environmental Evaluations

o

S0123 GCO-2 Rev. 0, Reporting Requirements to the 'NRC

o

E&C Procedure 40-9-21, NSG Review, Evaluation and Audit

Responsibility

The inspector concluded that the licensee.was adequately addressing the

review for an unreviewed s'afety question and the review for conformity to

technical specifications. These reviews are documented on a "Form 09-1"

contained in procedure S0123 VI-1.3, The review is performed by the

cognizant functional division manager or his specified designee.

There was no clearly and separately documented decision in the licensee's

process as to whether the test.or experiment is different from that

described in the FSAR. The licensee decision must be inferred from the

overall 50.59 review and approval. The lack of a documented decision

regarding the FSAR description is not a regulatory issue; it simply is.

not-as clear and direct. as the licensee.'s method of documenting decisions

regarding an unreviewed safety question or technical specification

applicability. This subject was discussed at the exit.interview on

November 18, 1985.

Sample of Tests and Experiments

The inspector examined a sample of tests and experiments conducted bythe

licensee to determine if the licensee's procedures for review were

properly.implemented'. Procedures reviewed included:

S023-SPE-33, CEDM 20 Investigation

S02 SPSU 8051, CVCS Letdown System Test

S023-V-1.0.6, Control Element Assembly Worth by Exchange

All the procedures were determined, by the licensee's review process, not

to involve an unreviewed safety question, not to violate technical

specificationi and not to be .different from the FSAR description.

3

The inspector had lengthy discussions regarding procedure S023-V-1.0.6

dealing with control rod worth. The central topic was whether or not the

procedure was different from that described in the FSAR for control rod

worth measurement. The licensee had perf.ormed the control rod worth in

the same manner as described in the FSAR (by boration/dilution) but, in

addition, had performed the rod worth measurements by an exchange method.

The method used was experimentaliin nature but had been extensively

discussed with NRC licensing-personnel and was part of a CE owner's Group

initiative. The FSAR did not specifically address the method used but

did generally authorize "alternate CEA configurations", when

"boration/dilution is impractical". The inspector discussed the

situation with NRC licensing personnel and concluded that the licensee

experiment was formally within the scope described by the FSAR but that

the licensee could have been more conservative and addressed the test as

a 50.59 test and experiment.'

Reports to the NRC

The inspector followed up the above noted observation by reviewing the

last SCE Annual Report to the NRC dated May 10, 1985.

It was noted that

the licensee reported no tests and experiments in that report, which was

for the entire 1984 calendar year for Units 1, 2 and 3.

At the exit interview on November 15, 1985, the inspector noted, for

licensee management's consideration, the two major conclusions from the

examination of the tests and experiments area;

0

The licensee's procedures do not force a documented decision as to

whether a test or experiment is or is not different from that

described in the FSAR.

o

The licensee's threshold for classifying a test or experiment as

applicable to 50.59 may be too high based on the absence of any such

classifications in 1984.

Licensee management stated they would consider the inspector's findings.

This item will be followed up in the normal course of periodic

inspections in this area.

No -violations or deviations were identified.

3.

Licensee Action on Previously Identified Items

a.

(Closed) Followup Item 50-206/82-15-03 - Main Steam Safety.Valves

This item is closed based on being superseded by a violation as

described herein. The item dealt with the failure to record the

as-found setpoint pressures of the main steam safety valves. At the

time (1982) only the as-left setpoint pressures were recorded.

.As-found relief settings are important information necessary to,

judge whether the periodicity of testing is sufficient to ensure the

valves remain at the proper .set point pressure between test

verifications.

4

The inspector examined the applicable test procedure which had been

revised to ensure as-found settings would be recorded. The

procedure, .S01-1-2.4, Valve Main Steam Safety, Pressure Setpoint

Check and Adjustment, Revision 4, dated October 26, 1984 was revised

to clearly require a sequence of determining the setpoint,..recording

the data, comparing the data with acceptance criteria, adjusting the

valve (if required) and then repeating the cycle until three

acceptable tests had been performed.

The inspector reviewed the main steam safety valve test data taken

using the procedure during the return to service in 1984 to

determine whether the as-found relief point pressures were taken.

Contrary to the procedure requirements, the as-found relief point

pressures were not recorded for 6 of the 10 main steam safety

valves, RV-2, 3, 4,,6, 8 and 10.

The data did show that adjustments

of up to 3 flats of the adjustment screw were necessary to bring

some of the valves into the proper set pressure tolerances.

Licensee personnel were not able to provide an estimate of how much

out of tolerance the valve relief pressures were in the as-found

condition.

The failure to follow procedural requirements to record as-found

main steam safety relief valve set pressure is considered an

apparent violation of NRC requirements (Violation 50-206/85-37-01).

At the exit interview on December 18, 1985, the inspector discussed

the apparent violation with licensee management. It was noted that

although proper management policies and adequate procedures were in

place in the circumstances of this violation, it appeared that

involved personnel failed to adequately implement those policies and

procedures. This is considered similar to the circumstances

surrounding the auxiliary feedwater pump violation described in

report 50-206/85-33.

In this case the procedure was performed by and the resultant

improperly recorded data was witnessed and signed for by a

maintenance mechanic, a quality control inspector, and a codes

engineer. Additionally, the improperly recorded data were

subsequently reviewed aiid approved by a maintenance supervisor, a

quality assurance engineer, and a senior reactor operator. The fact

that multiple reviews failed to note the lack of procedure

compliance strongly indicated a need for additional emphasis

focussed at the implementation level of all involved organizations.

The inspector also questioned whether two test calibration

requirements had been met. The first question was whether the

hydroset device (used to perfdrm the safety valve test) had been

calibrated as a unit within 24 months of the test as recommended by

the manufacturer. The second question was whether the hydraulic

test gages were within calibration during the required gage

recalibration after the test. :

5

The licensee could not provide the information prior to the exit

meeting on December 18; 1985. On January 8, 1986, the Supervisor of

Compliance notified the inspector that no information had been found

on the hydroset device calibration, and that the gage recalibration

had apparently been done'but no records could be found. The

licensee was generating a corrective action request to resolve the

matter.

The apparent lack of proper calibration of the test equipment used

on the main steam safety valves is considered an unresolved item and

will be examined further in a future inspection. (Unresolved item

50-206/85-37-02)

As an additional matter, the inspector noted that.the main steam

safety valve Procedure permitted the option to gag all main steam.

safeties except the one being, tested, with reactor power at up to

10%. The licensee provided information to assure the inspector that

the one remaining operable safety valve had sufficient capacity to

accommodate the steam load expected at 10% reactor power.

Additionally, the licensee stated that the procedure would be

revised to eliminate the option since it was less desirable than the

option to use the hydroset device. Followup is not considered

required since the procedure revision was underway at the time of

inspection.

b.

(Closed) Followup Item 50-206/85-13-03 -

Improper Test Pressure on

System Boundary Valves

IThis

item dealt with the'post maintenance leakage check of the.

Unit 1 residual heat removal (RHR) to reactor coolant system (RCS)

boundary valves. The valves had been tested at RHR system pressure

instead of.the RCS system pressure even though the parts replaced

(valve bonnet studs) would see the RCS pressure in service.

During this inspection, .the inspector reviewed an.analysis of the

problem as documented in armemorandum from the Station Technical

Manager to the Compliance Manager dated November 8, 1985.

The

letter recommends a change.to the procedure for-system testing

(S0123-V-4.16) to require-testing system boundary valves twice, once

at the lower system pressure and once at the higher system pressure.

The inspector then verified that the requirement to revise 'the

procedure was entered on the San Onofre Commitment Register (SOCR).

This item is considered closed based on the licensee's actions.

c.

(Closed) Followup Item 50-206/85-13-02 -

Alternate Bolting Material,

Allowed by The Piping Specification, Should be Verified Technically

Sound

This item dealt with the addition to the piping material

specification of an alternate pipe flange bolting material

(stainless steel in lieu of carbon steel).

The licensee had

committed to evaluate whether the lower strength stainless steel was

an acceptable substitute.

6

During this inspection the inspector determined that the licensee

had taken action to eliminate stainless steel as an option and had

issued DCN-3 to drawing M-18668 (the piping material specification)

on May 29, 1985 eliminating'stainless steel.as an option for the

p~iping bolting in ,question.

Prior usage of the imprdper matdrial was evaluated and either

changed of ,scheduled for change asxdescribed in"'Inspection.Report

50-206/85-31.

"

This item is considered closed based'on the licensee's actions.

d.

(Closed) Followup Item 50- 206 /80-1103.- Pressurizer Code Safety

Valves

'This item dealt with the Unit 1 pressurizer code safety valves. At

the time, the licensee performed cold testing to determine the.

relief setpoints and did ,not utilize .cold-to-hot correlation factors

which would ensure the valves would relieve at the proper set.

pressure when the valve was at normal operating temperature in

service.

The licensee has decided to implement a program similar to that used

in Units 2.and 3 wherein the Unit 1 valves will be tested hot at a

test facility thereby eliminating the need for cold-to-hot

correlation factors. The inspector reviewed the specifications

issued to control' the hot testing of the valves (501-408-01

Revision 2 and SO1-048-02 Revision 0).

This item is considered closed based on the 'licensee's actions.

e.

(Closed) Followup Items JH-82-04 Through 82-09 -

Commitments made

for Handling Heavy Loads in Unit 1

These items dealt with. :commitments made by the licensee in a letter

to the NRC dated July..6, 1982.. The commitments were in regard to

fulfilling the requirements of NUREG-0612.

The inspector determined that the licensee's commitments made' in

1982 were no longer valid and had been superseded by a-continuing

flow of correspondence between the licensee and the NRC.

The licensee's ,program for heavy lifts in Unit 1 was reviewed and

accepted by the NRC as summarized in the NRC Safety Evaluation

Report (SER) dated November 4, 1985.

The .subject followup items are considered closed on the basis of the

issuance of the SER.

7

4.

Licensee Action on IE Bulletins and Generic Letters

a.

(Closed) IE Bulletin :84-02 -'Failures of General Electric Type HFA

Relays

This item had been extensively examined in previous inspections.

The remaining action item was the completion of the licensee's

commitment to implement a comprehensive material control program as

described in the licensee's letter to NRC dated March 29, 1985. The

comprehensive program was described as.the Control of Problem

Equipment (COPE) program and was committed to be fully implemented

by June 1, 1985.

The inspector examined the COPE program and considered that it did

not represent a comprehensive program as indicated in the licensee's

response to the bulletin. This consideration was based on review of

applicable procedures, interviews with involved personnel and

examination of actions taken to date. The following were

determined:

0

The current COPE list was surprigingly short; only 16 items

were included whereas there have been hundreds of notifications

by IE Bulletins, Information Notices, INPO reports and vendor

reports regarding material problems. The low number of items

on the COPE list was apparently due to a severe screening by

project engineering. Non-conservative approaches were taken

such as (1) not adding an item to COPE if it was an older

vendor Part 21 report because "the vendor and suppliers should

have taken appropriate action" and (2) not adding an itemto

COPE if the problem applies to equipment with older

manufacturing dates because "the older material is~probably not

available any more".

o

There was a backlog of about fifty older (over a year) items

awaiting project engineering review for COPE applicability.

o

The COPE coordinator did not agree with the adequacy of some

material searches, and did not agree with decisions made

regarding.COPE applicability, but did not formally voice his

disagreement. Responsible management stated they were .not

aware of the situation.

o

Procedural requirements for responsible management to perform

"a periodic review of effectiveness" and "taking corrective

actions" had not been formalized.

One of the COPE items appeared improperly closed -

item 15 of

the COPE list, which dealt with Brown Boveri Corporation ITE-60

relays.

The relays must be tested to ensure they operate

within the required 10 milliseconds. The action identified in

the COPE package was that 9 such relays had been identified.

Instructions had been issued to test the relays. The COPE

information showed that only 8 of the 9 relays had been tested

and 6 of the 8 had failed. No corrective action for the failed

8

relays was noted and it was not known if further action was

planned. The COPE "Problem Equipment Tracker", Form

SO(123) 421.',4 was closed based on performance of the testing

only.

0

The COPE coordinator was not receiving all required

information. The COPE procedure requires all IE Bulletins,

Notices, vendor notices, etc. to be forwarded to the COPE

coordinator. In practice, however, the COPE coordinator was

only receiving screened information, items that the other

involved organizations deemed to be COPE material. Therefore,

the COPE coordinator did not have the ability to concur or

disagree with the screening done.

At the exit interview on December 18, 1985, the subject of the COPE

program was discussed. Licensee management committed to review the

COPE program status and take action as required by April 1986.

This subject of the bulletin is considered closed. Action taken

regarding the COPE program will be examined in a future inspection

(Followup Item 50-361/85-35-01).

b.

(Closed) Generic Letter 85-05 -

Inadvertent Boron Dilution Events

This genetic letter was issued January 31, 1985, and was provided

for information to all licensees. The letter did .not require

licensee action but strongly urged all licensees to assure

themselves that adequate protection against boron dilution exists.

The inspector examined licensee actions taken in response to the

generic letter. Specifically, the licensee documented a review of

existing protection against boron dilution events in Units 1, 2 and

3. The analysis dated March 11, 1985 showed multiple indications,

alarms and automatic measures in each of the units. The analysis

was reviewed by the manager of station technical and that review was

documented in a memorandum to file dated May 29, 1985.

This generic letter is considered closed based on the licensee's

actions.

5.

Licensee Action on 10 CFR Part 21 Reports

a.

(Closed) Part 21 Item 85-15-PO -

TEC Model 914-1 Analog Level

Detector

This Part 21 report was submitted to the NRC by the Technology for

Energy Corporation (TEC) onJuly 19, 1985, and concerned the TEC

Model 914-1 Acoustic Valve Flow Monitor Module. The failure

involved was one of indication, not operation; it concerned an LED

improperly remaining lit after the alarm condition had passed.

The licensee's records showed that TEC properly notified SCE of the

problem. SCE investigated and determined the components were used

in the tail pipe section of the pressurizer relief valves. The

9

licensee had completed testing for the Unit 2 detector and had

scheduled testing for the Unit 3 detectors.

This Part 21. report is considered closed based on the licensee

actions taken.

b.

(Open).Part 21 Item 85-16-PO -,Pacific Scientific Snubbers Using

Pipe 'Clamps Manufactured by NAVCO

This item involved pipe clamps manufactured by NAVCO and supplied

with snubber.' assemblies'made'by Pacific Scientific. The problem.

dealt with pipe'clamps which 'did not clamp the pipe with sufficient

force and could slip in service;

The NRC was notified by Pacific

Scientific of the Part' 21 condition in a letter dated August 23,

1985.-" The 11iensee had been dtified in a.letter dated July 19,

1985.

The corre.ctive'action recommended replacing the clamp bolting

material, with 'a highe9 strength material and increasing the

installation torque values.

Several problems were identified as a result of the inspector's

examination of licensee 'actions for this item:

o

The ISEG group performed an evaluation of the Part 21 report

and reached an improper conclusion. 'Specifically,

the

conclusion reached did not recognize the fact that new bolting

material was 'required. This was in part due to the fact that

the Pacific Scientific letter to the licensee was somewhat

obscure in stating that 'new bolting material was required.

o

The maintenance procedure group did not recognize the need or

intend to obtain design engineering concurrence when changing

the procedure torque values for the pipe clamp bolting

'material.

Increasingbolt torque values could exceed design

code allowable stresses and such a decision should be made by

the design organization.

-Theseareas were discussed with licensee' management at.the exit

interview on December 18, 1985.

The inspector was informed that the

maintenance procedure would be revised to :require new bolting

material and the procedure would be reviewed by a responsible design

organization. 'The inspector noted that there may be a broader

problem in maintenance personnel awareness of when they are

broaching design issues as evidenced by this occurrence and by the

modification of the auxiliary feedpump oil sight' glass in Unit 1

discussed in report 50-206/85-33.'

Based on the above, licensee action on the above Part 21 report is

considered open and will be examined further in a future inspection

report.

6.'

Licensee Actions on Information Notices

The inspector examined licensee actions .on several IE Information

Notices. The licensee's actions were found to be. generally thorough,

10

adequately documented and actions pifoperly administered and tracked to

completion. The inspector noted a relatively minor backlog of older

Information Notices, some of which only required finalsupervisory review

for closeout. These were processed during the course of the inspection

in a timely fashion with the net result that the licensee had 36 open IE

Notices under evaluation with an average age of 3.3 months. Only 6 of

the 36 were older than-6 months. Based on the inspector's sample the

following Information Notices were considered closed for Units 1, 2 and 3

based on the status of the licensee's action:

Information Notices 83-54, 83-55, 83-56, 83-57, 83-60, 83-61, 83-62,

83-93 and 85-23.

7.

In-office Review of LER's

The following Licensee Event Reports (LER's) were reviewed in the NRC

regional office during the period of this report. Attributes examined

included: report timeliness, inclusion .of required information, adequacy

of proposed corrective action and the need for further follow-up

inspection. The following LER's and their revisions are considered

closed based on this review:

Unit 1

  • 85-016

Fire System Nozzles Plugged with Rust

Unit 2 84-023 Rev.1 Spurious Noise Spikes on Control Room Isolation System

0*

~~

.*

(CRIS) CI)

84-02 Rev. 2

Spurious.NoiseSpikeson Containment Purge Isolation 84-046 Rev. I Revised to Correct Dates85-054

Circuit'Breakers not Tested 85-052

Spurious"Toxic Gas Isolation System (TGIS) Actuation

85-55

Fuel Handling Isolation System (FHTS) Actuation due to

Failed Monitor,

85-56

Spurious. CPIS Actuation

8S-47

Spurious TGIS Actuation

Unit. 3 85-032

Spurious HIS Actuations85-019 Rev. 1 Spurious Noise Spikes on FineS85-035

CPIS Actuation due to a contaminated tool movement

near aradiation monitor 85-034

Fpio

CS

Actuation due to grounded lead 85-033

Spurious FIS actuation

8.

Unresolved Items

Unresolved items'are matters about which more information is required in

order to ascertain whether they are acceptable items, items 'of

11

noncompliance, 'or deviations. An unresolved item disclosed during this

inspection is discussed in Paragraph 3.a of this report.

9.

Management Interview

The inspector and the NRC resident inspector met with the licensee

representatives (denoted in Paragraph 1) on November 15 and December 18,

1985.

The scope of the inspections and the inspector's findings, as

noted in this report, were discussed.