Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

0

REGION V

1990 N. CALIFORNIA BOULEVARD

SUITE 202, WALNUT CREEK PLAZA

WALNUT CREEK, CALIFORNIA 94596

JUN 2 0 1980

Docket No. 50-206

Southern California Edison Company

P. 0. Box 800

2244 Walnut Grove Avenue

Rosemead, California 91770

Attention:

Dr. L. T. Papay, Vice President

Advanced Engineering

Gentlemen:

Subject:

NRC Inspection of San Onofre Unit 1

O

This refers to the inspection conducted by Mr. D. P. Haist of this

office on May 28-30, 1980 of activities authorized by NRC Licensee

No. DPR-13, and to the discussion of our findings held by Mr. Haist

with Mr. Brunet and other members of your staff at the conclusion of the

inspection.

Areas examined during this inspection are described in the enclosed

inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, inter

views with personnel, and observations by the inspector.

No items of noncompliance with NRC requirements were identified within

the scope of this inspection.

In accordance with Section 2.790 of the NRC's "Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public

Document Room. If this report contains any information that you believe

to be proprietary, it is necessary that you submit a written application

to this office, within 20 days of the date of this letter, requesting

that such information be withheld from public disclosure. The applica

tion must include a full statement of the reasons why it is claimed that

800tS40~)

Southern California Edison Company

-2-

JUN 2 0 1%8

the information is proprietary. The application should be prepared so

that any proprietary information identified is contained in an enclosure

to the application, since the application without the enclosure will

also be placed in the Public Document Room. If we do not hear from you

in this regard within the specified period, the report will be placed in

the Public Document Room.

Should you have any questions concerning this inspection, we will be

glad to discuss them with you.

Sincerely,

G. S. Spencer, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection Report

No. 50-206/80-15

cc w/o enclosure:

R. Dietch, Vice President, Nuclear Engineering & Operations, SCE

J. M. Curran, SCE