Forwards Insp Rept 50-206/78-11 on 780814-15.No Noncompliance Noted
ML13323A557
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 09/07/1978
From: Book H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Johari Moore
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13323A558 List:
References
NUDOCS 7810300018
Download: ML13323A557 (2)


See also: IR 05000206/1978011

Text

UNITED

STATES

NUCLEAR

REGULATORY COMMISSION

REGION V

C,

PilSUITE

202, WALNUT CREEK PLAZA

1990 N. CALIFORNIA BOULEVARD

WALNUT CREEK, CALIFORNIA 94596

Ve 7~10

Docket No. 50-206/

1

Southern California Edison Company

2244 Walnut Grove Avenue

Rosemead, California 91770

Attention: Mr. J. B. Moore

Vice President

Gentlemen:

Subject: NRC Inspection at San Onofre Unit 1

This refers to the inspection conducted by Mr. J. R. Curtis of this

office on August 14-18, 1978 of activities authorized by NRC License

No. DPR-13, and to the discussion of our findings held by Mr. Curtis

with Mr. Curran and other members of your staff at the conclusion of

the inspection.

Areas examined during this inspection are described in the enclosed

inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, inter

views with personnel, and observations by the inspector.

No items of noncompliance with NRC requirements were identified within

the scope of this inspection.

In accordance with Section 2.790 of the NRC's "Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter

and the enclosed inspection report will be placed in the NRC's Public

Document Room. If this report contains any information that you believe

to be proprietary, it is necessary that you submit a written application

to this office, within 20 days of the date of this letter, requesting

that such information be withheld from public disclosure. The applica

tion must include a full statement of the reasons why it is claimed that

the information is proprietary. The application should be prepared so

II

/3Ioo)

/

Southern California Edison Co.

-2

that any proprietary information identified is contained in an enclosure

to the application, since the application without the enclosure will

also be placed in the Public Document Room. If we do not hear from you

in this regard within the specified period, the report will be placed in

the Public Document Room.

Should you have any questions concerning this inspection, we will be

glad to discuss them with you.

Sincerely,

H. E. Book, Chief

7

LFuel Facility and Materials

Safety Branch

Enclosure:

IE

Inspection Report

No. 50-206/78-11

cc w/o enc:

J. T. Head, Vice President

Power Supply, SCE

J. M. Curran, SCE

0II